Risk register example: Roof renovation
Replacing or insulating a roof: work at height, fragile roofing, weather and possibly asbestos in older buildings.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Construction / civil works · Execution / works · 8 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), old building (asbestos, lead possible), mainly outdoors, works during winter, works during summer or heatwaves, subcontractors involved, dense urban area, neighbours nearby, heavy or repetitive manual handling.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground Consequence : Crushing, fatality, major damage |
25 P5×I5 | • Lifting plan for critical lifts • Qualified operators and slingers, inspected gear |
• No one under the load |
| R-002 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
25 P5×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-003 | Heat stroke
Cause : Physical work in full sun, heatwave, insufficient hydration Consequence : Serious illness, hospitalisation, death |
25 P5×I5 | • Shifted hours and shaded breaks |
• Cool water and buddy checks |
| R-004 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
16 P4×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-005 | Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below Consequence : Serious injury to people below, material damage |
16 P4×I4 | • Toe boards, nets and tethered tools |
• Marked exclusion zone below |
| R-006 | Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings Consequence : Serious or fatal fall |
15 P3×I5 | • Cover and mark floor openings • Nets or walkways on fragile roofs |
|
| R-007 | Crane or aerial platform overturning
Cause : Weak ground, inadequate outriggers, high wind, overloading Consequence : Crushing, death, major damage |
15 P3×I5 | • Ground assessment and outrigger pads • Anemometer and wind stop threshold |
|
| R-008 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-009 | Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work Consequence : Site stoppages, degraded quality (concrete, paint), delay |
15 P5×I3 | • Season-aware scheduling |
• Temporary protection |
| R-010 | Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building Consequence : Serious delayed illness, works stopped, costly unplanned removal |
15 P3×I5 | • Asbestos and lead survey before works |
• Stop-work procedure on discovery |
| R-011 | Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings Consequence : Collision, load falling on third parties |
12 P3×I4 | • Layout study and anti-collision system • No loads over public areas |
|
| R-012 | Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people Consequence : Falls of people and materials |
12 P3×I4 | • Erection by qualified staff and handover • Periodic inspection and after storms |
|
| R-013 | Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements Consequence : Burial, falls |
12 P3×I4 | • Structural survey by an engineer • Temporary propping |
|
| R-014 | Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area Consequence : Pedestrian or worker struck, material damage |
12 P3×I4 | • Delivery plan and dedicated area • Banksman for manoeuvres |
|
| R-015 | Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations Consequence : Destruction of works, injuries, major delays |
12 P4×I3 | • Combustible waste management and storage areas |
• Extinguishers and response plan |
| R-016 | Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects Consequence : Injury to a third party, prosecution |
12 P3×I4 | • Continuous fencing and protected footpath • Fans and nets against falling objects |
|
| R-017 | Bankruptcy of a subcontractor or site contractor
Cause : Weak cash position, prices too low, dependence on one large client Consequence : Work package to re-tender, delay, defects left unremedied |
12 P3×I4 | • Financial health check |
• Performance bond and retention |
| R-018 | Defects from concreting in cold or hot weather
Cause : Frost, rapid drying, insufficient curing Consequence : Low strength, cracking, partial demolition |
9 P3×I3 | • Extreme-weather concreting procedure |
• Strength tests before striking formwork |
| R-019 | Water ingress during roofing works
Cause : Roof left open, inadequate sheeting, unexpected showers Consequence : Interior damage, claims |
9 P3×I3 | • Open only what can be closed the same day |
• Emergency sheeting and weather watch |
| R-020 | Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished Consequence : Idle time, rework, accumulated delay at the end of the works |
9 P3×I3 | • Weekly coordination schedule |
• Handover of work areas between trades |
| R-021 | Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time Consequence : Site blocked, delayed handover |
9 P3×I3 | • Requests to utilities from the design stage |
• Track utilities at site meetings |
| R-022 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
9 P3×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-023 | Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades Consequence : Rework, retentions, delayed handover |
9 P3×I3 | • Hold points and self-inspections |
• Pre-handover inspection per trade |
| R-024 | Rising material prices
Cause : Volatile steel, concrete, timber or energy prices Consequence : Eroded margin, difficulty holding the price |
9 P3×I3 | • Price revision clause |
• Early purchase of key materials |
| R-025 | Unexpected discovery in the existing building
Cause : Inaccurate old drawings, hidden structure or networks, degraded materials Consequence : Extra studies and works, site stoppage, extra costs |
8 P2×I4 | • Prior surveys and investigations |
• Dedicated allowance for existing-building risks |
| R-026 | Poor ground conditions
Cause : Limited or missing geotechnical survey Consequence : Foundations to redesign, major extra cost and delay |
8 P2×I4 | • Geotechnical survey suited to the project |
• Costed foundation alternatives |
| R-027 | Dispute with the client
Cause : Unsigned additional work, no meeting minutes Consequence : Blocked payments, legal proceedings |
8 P2×I4 | • Signed instructions before execution |
• Minutes and dated photos |
| R-028 | Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed Consequence : Complaints, municipal orders, delay |
6 P2×I3 | • Advance notice and residents’ contact • Working hours and dust control |
|
| R-029 | Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks Consequence : Penalties, joint liability, site stoppage |
6 P2×I3 | • Access control and check of declarations • Limit chain subcontracting |
|
| R-030 | Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists Consequence : Low back pain, slipped discs |
6 P2×I3 | • Material hoists and delivery close to the workplace • Lighter packaging |
|
| R-031 | Late permit for use of the public road
Cause : Late application, refusal, imposed conditions Consequence : Late start, deliveries impossible |
6 P2×I3 | • Early application with signage plan |
• Alternative logistics |
| R-032 | Working in the cold
Cause : Low temperatures, wind, humidity, cold stores Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground |
6 P2×I3 | • Suitable clothing and heated rooms • Organise exposure time |
|
| R-033 | Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection Consequence : Sunburn, long-term skin cancer |
6 P2×I3 | • Schedule work at less exposed times |
• Covering clothing and sunscreen |
| R-034 | Poor indoor air quality
Cause : Insufficient ventilation, emissive products, dense occupancy Consequence : Discomfort, headaches, absenteeism, spread of infections |
6 P2×I3 | • CO2 sensors and ventilation maintenance • Low-emission materials and products |
|
| R-035 | Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted Consequence : Harm to mother or child, non-compliance |
6 P2×I3 | • Specific assessment once pregnancy is announced • List of at-risk jobs prepared in advance |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Roof renovation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.