Risk register example: Roof renovation

Replacing or insulating a roof: work at height, fragile roofing, weather and possibly asbestos in older buildings.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate18
● High7
● Critical10

Assumptions: Construction / civil works · Execution / works · 8 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), old building (asbestos, lead possible), mainly outdoors, works during winter, works during summer or heatwaves, subcontractors involved, dense urban area, neighbours nearby, heavy or repetitive manual handling.

Ref.RiskScorePreventionProtection
R-001 Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground
Consequence : Crushing, fatality, major damage
25 P5×I5 • Lifting plan for critical lifts
• Qualified operators and slingers, inspected gear
• No one under the load
R-002 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
25 P5×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-003 Heat stroke
Cause : Physical work in full sun, heatwave, insufficient hydration
Consequence : Serious illness, hospitalisation, death
25 P5×I5 • Shifted hours and shaded breaks
• Cool water and buddy checks
R-004 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
16 P4×I4 • Mobile platforms instead of ladders
• Visual check before use
R-005 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
16 P4×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-006 Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings
Consequence : Serious or fatal fall
15 P3×I5 • Cover and mark floor openings
• Nets or walkways on fragile roofs
R-007 Crane or aerial platform overturning
Cause : Weak ground, inadequate outriggers, high wind, overloading
Consequence : Crushing, death, major damage
15 P3×I5 • Ground assessment and outrigger pads
• Anemometer and wind stop threshold
R-008 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-009 Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work
Consequence : Site stoppages, degraded quality (concrete, paint), delay
15 P5×I3 • Season-aware scheduling
• Temporary protection
R-010 Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building
Consequence : Serious delayed illness, works stopped, costly unplanned removal
15 P3×I5 • Asbestos and lead survey before works
• Stop-work procedure on discovery
R-011 Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings
Consequence : Collision, load falling on third parties
12 P3×I4 • Layout study and anti-collision system
• No loads over public areas
R-012 Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people
Consequence : Falls of people and materials
12 P3×I4 • Erection by qualified staff and handover
• Periodic inspection and after storms
R-013 Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements
Consequence : Burial, falls
12 P3×I4 • Structural survey by an engineer
• Temporary propping
R-014 Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area
Consequence : Pedestrian or worker struck, material damage
12 P3×I4 • Delivery plan and dedicated area
• Banksman for manoeuvres
R-015 Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations
Consequence : Destruction of works, injuries, major delays
12 P4×I3 • Combustible waste management and storage areas
• Extinguishers and response plan
R-016 Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects
Consequence : Injury to a third party, prosecution
12 P3×I4 • Continuous fencing and protected footpath
• Fans and nets against falling objects
R-017 Bankruptcy of a subcontractor or site contractor
Cause : Weak cash position, prices too low, dependence on one large client
Consequence : Work package to re-tender, delay, defects left unremedied
12 P3×I4 • Financial health check
• Performance bond and retention
R-018 Defects from concreting in cold or hot weather
Cause : Frost, rapid drying, insufficient curing
Consequence : Low strength, cracking, partial demolition
9 P3×I3 • Extreme-weather concreting procedure
• Strength tests before striking formwork
R-019 Water ingress during roofing works
Cause : Roof left open, inadequate sheeting, unexpected showers
Consequence : Interior damage, claims
9 P3×I3 • Open only what can be closed the same day
• Emergency sheeting and weather watch
R-020 Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished
Consequence : Idle time, rework, accumulated delay at the end of the works
9 P3×I3 • Weekly coordination schedule
• Handover of work areas between trades
R-021 Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time
Consequence : Site blocked, delayed handover
9 P3×I3 • Requests to utilities from the design stage
• Track utilities at site meetings
R-022 Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain
Consequence : Work stoppages, damage, design to revise
9 P3×I3 • Include climate scenarios in design
• Plan to adapt hours and works
R-023 Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades
Consequence : Rework, retentions, delayed handover
9 P3×I3 • Hold points and self-inspections
• Pre-handover inspection per trade
R-024 Rising material prices
Cause : Volatile steel, concrete, timber or energy prices
Consequence : Eroded margin, difficulty holding the price
9 P3×I3 • Price revision clause
• Early purchase of key materials
R-025 Unexpected discovery in the existing building
Cause : Inaccurate old drawings, hidden structure or networks, degraded materials
Consequence : Extra studies and works, site stoppage, extra costs
8 P2×I4 • Prior surveys and investigations
• Dedicated allowance for existing-building risks
R-026 Poor ground conditions
Cause : Limited or missing geotechnical survey
Consequence : Foundations to redesign, major extra cost and delay
8 P2×I4 • Geotechnical survey suited to the project
• Costed foundation alternatives
R-027 Dispute with the client
Cause : Unsigned additional work, no meeting minutes
Consequence : Blocked payments, legal proceedings
8 P2×I4 • Signed instructions before execution
• Minutes and dated photos
R-028 Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed
Consequence : Complaints, municipal orders, delay
6 P2×I3 • Advance notice and residents’ contact
• Working hours and dust control
R-029 Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks
Consequence : Penalties, joint liability, site stoppage
6 P2×I3 • Access control and check of declarations
• Limit chain subcontracting
R-030 Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists
Consequence : Low back pain, slipped discs
6 P2×I3 • Material hoists and delivery close to the workplace
• Lighter packaging
R-031 Late permit for use of the public road
Cause : Late application, refusal, imposed conditions
Consequence : Late start, deliveries impossible
6 P2×I3 • Early application with signage plan
• Alternative logistics
R-032 Working in the cold
Cause : Low temperatures, wind, humidity, cold stores
Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground
6 P2×I3 • Suitable clothing and heated rooms
• Organise exposure time
R-033 Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection
Consequence : Sunburn, long-term skin cancer
6 P2×I3 • Schedule work at less exposed times
• Covering clothing and sunscreen
R-034 Poor indoor air quality
Cause : Insufficient ventilation, emissive products, dense occupancy
Consequence : Discomfort, headaches, absenteeism, spread of infections
6 P2×I3 • CO2 sensors and ventilation maintenance
• Low-emission materials and products
R-035 Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted
Consequence : Harm to mother or child, non-compliance
6 P2×I3 • Specific assessment once pregnancy is announced
• List of at-risk jobs prepared in advance

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Roof renovation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free