5×5 risk matrix: how to use it, with an example

A risk matrix (or probability-impact matrix) is the most widely used tool to rank risks. It combines the probability that an event happens with its impact if it does. The result, the score, tells you where to act first. This guide explains the 5×5 matrix used by most organisations and standards (ISO 31000, ISO 45001, site risk assessments).

The two axes: probability and impact

Each axis is rated from 1 to 5. A scale shared by the whole project is essential: without one, two people will score the same risk differently.

RatingProbabilityImpact
1Rare: has never happened in this contextNegligible: no injury, insignificant cost or delay
2Unlikely: has happened elsewhereMinor: first aid, small extra cost
3Possible: may happen during the projectModerate: lost-time injury, delay of a few weeks
4Likely: will probably happenMajor: serious injury, large budget overrun
5Almost certain: happens regularlySevere: fatality, project stopped, lasting damage to reputation

Adapt the impact examples to your project: on a €200,000 job, a €20,000 overrun is major; on a €20 million programme it is minor. For people’s safety, however, the scale must not depend on the size of the project.

Calculating the score and reading the levels

The score is the product of the two ratings: score = probability × impact, from 1 to 25. Risqure uses four levels:

Example: work at height on a roof

A team must replace sheets on a roof with no guardrails. A fall from height is possible (3) and its consequences severe (5): the gross score is 15, a critical risk. With perimeter guardrails and safety nets under fragile areas, the probability drops to 1: the residual score becomes 5, a moderate level. This gap between gross and residual risk shows how effective the action plan is.

See the full entries in our risk register examples, or the list of construction project risks.

Gross risk and residual risk

Gross risk is assessed without the measures you plan to add. Residual risk is the expected level once the actions are done. Prevention actions lower the probability (training, procedures, collective protection); protection actions reduce the impact (emergency plan, insurance, back-up solution). In Risqure the matrix shows both views, and you can drag a risk to another cell to re-score it.

The most common mistakes

3×3, 4×4 or 5×5 matrix?

A 3×3 matrix is quick but not very discriminating: many risks end up in the same cell. A 5×5 matrix is fine enough to prioritise without becoming subjective. It is the best compromise for most projects, and the one Risqure uses.

From the matrix to the register

The matrix is only a view: the risks themselves are described in the risk register, with their cause, consequence, owner and actions. With Risqure you describe your project and the tool proposes the risks, their score on the 5×5 matrix and the related measures, for free.