Site opening and closing checklist
A free printable checklist to open and close a construction site: Belgian and French formalities (coordination, prior notice, post-intervention file), set-up, first aid, induction, withdrawal and acceptance.
Site opening checklist BE
| Site or project | |||
|---|---|---|---|
| Site address | |||
| Client | Safety and health coordinator | ||
| Site manager | Date | ||
1. Formalities and coordination
| Point to check | OK | N/A | Person in charge, date, note |
|---|---|---|---|
| Safety and health coordinator appointed (design and execution) when two or more contractors work on the site AR 25/01/2001 | ☐ | ☐ | |
| Prior notice sent before the works start if the site exceeds the thresholds (more than 30 working days with more than 20 workers at the same time, or more than 500 man-days) AR 25/01/2001, art. 26 | ☐ | ☐ | |
| Safety and health plan received and its measures passed on to each contractor | ☐ | ☐ | |
| Coordination log opened on the site | ☐ | ☐ | |
| Attendance registration (Checkin@Work) in place if the site is subject to it | ☐ | ☐ | |
| Plans of underground cables and pipes requested (KLIM-CICC, KLIP, PowaLin) and answers received | ☐ | ☐ | |
| Permits and authorisations obtained (building permit, road occupation, traffic signs) | ☐ | ☐ | |
| Insurance certificates of all contractors received | ☐ | ☐ | |
| List of contractors and subcontractors on site, with their contacts | ☐ | ☐ |
2. Site set-up
| Point to check | OK | N/A | Person in charge, date, note |
|---|---|---|---|
| Site fenced off from the public and signs displayed at the entrances | ☐ | ☐ | |
| Pedestrian and vehicle access and traffic routes defined and marked | ☐ | ☐ | |
| Welfare facilities in place: changing room, toilets, drinking water, break area | ☐ | ☐ | |
| Underground and overhead networks located and marked on the ground | ☐ | ☐ | |
| Temporary electrical installation inspected before use | ☐ | ☐ | |
| Storage areas for materials, waste and hazardous products defined | ☐ | ☐ | |
| Lighting sufficient for work areas and routes | ☐ | ☐ |
3. First aid and emergencies
| Point to check | OK | N/A | Person in charge, date, note |
|---|---|---|---|
| First aid kit on site and trained first aiders present | ☐ | ☐ | |
| Fire extinguishers suited to the risks, in place and accessible | ☐ | ☐ | |
| Emergency numbers and the site address displayed | ☐ | ☐ | |
| Access for the emergency services kept clear | ☐ | ☐ | |
| Evacuation route and assembly point defined and explained | ☐ | ☐ |
4. Workers and equipment
| Point to check | OK | N/A | Person in charge, date, note |
|---|---|---|---|
| Safety induction given to every worker and subcontractor, with a signed attendance sheet | ☐ | ☐ | |
| Training and authorisations checked (machine operators, electrical work, work at height) | ☐ | ☐ | |
| Personal protective equipment available and suited to the risks | ☐ | ☐ | |
| Scaffolds, lifting equipment and machinery inspected, inspection reports available | ☐ | ☐ | |
| Specific permits in place where needed (hot work, excavation, confined space) | ☐ | ☐ | |
| Risks of the site identified and recorded in the risk register | ☐ | ☐ |
5. Approval
| Site manager | Client | Safety and health coordinator |
|---|---|---|
This checklist is a reminder: check the rules that apply to your site with your coordinator or prevention adviser. risqure.com
In Risqure, each point gets a status, a person in charge and a date, and the signed report is generated in PDF. Free.
Opening a site the right way
Before work starts, several formalities add up: appointing a health and safety coordinator when several contractors are involved, sending a prior notice above certain thresholds, the health and safety plan, insurance and road permits. The checklist gathers these points for Belgium and France, followed by site set-up, first aid and team induction.
Closing and handing over a site
Closing matters as much as opening: removing the facilities, clearing waste, resolving snags, handing the post-intervention file to the client and holding a lessons-learned review. Ticking off these steps avoids costly omissions after acceptance.
From a paper checklist to a signed report
The free version prints as it is. In a Risqure project, the same checklist is filled in online with an owner and a date for each point, plus the list of contractors on site with their order references, and produces a PDF report.
Frequently asked questions
When must the prior notice be sent?
In Belgium and France, before work starts when the site exceeds the thresholds: more than 30 working days with more than 20 workers at the same time, or more than 500 person-days. Check the exact conditions that apply to your site.
What is the post-intervention file?
The file that gathers the information needed to work safely on the building later (maintenance, repair, demolition). It is handed to the client at acceptance.
Does the checklist replace the coordinator’s advice?
No. It is a reminder. The rules that apply to the site and the advice of the coordinator and prevention adviser always come first.
This information is general and does not replace advice adapted to your situation. Always check the official texts in force. Disclaimer