Risk register example: Road and utility works
Works on public roads: traffic, underground networks, trenches, machinery and night shifts.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Construction / civil works · Execution / works · 20 people · work on or near public roads, excavation, trenches, earthworks, site vehicles, forklifts, construction machinery, noise or vibration, night or shift work, mainly outdoors, works during winter, works during summer or heatwaves, dense urban area, neighbours nearby, permits or authorisations required, public procurement.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Road worker struck by a vehicle at roadworks
Cause : Inadequate signage, speeding traffic, night work Consequence : Serious or fatal injuries |
20 P4×I5 | • Compliant temporary signage and buffer zone |
• Protection vehicle and high-visibility clothing |
| R-002 | Person struck by a vehicle or forklift
Cause : Pedestrians and vehicles sharing routes, poor visibility, reversing Consequence : Serious injury or death |
20 P4×I5 | • Traffic plan separating pedestrians and vehicles • Alarms, reversing cameras and hi-vis |
|
| R-003 | Pedestrian struck by a delivery vehicle on site
Cause : Pedestrian and vehicle areas not separated, reversing, blind spots Consequence : Serious or fatal injuries |
15 P3×I5 | • Physical separation of traffic • Traffic plan and driver instructions |
|
| R-004 | Drowning or burial near water
Cause : Bank works, cofferdams, shafts, flooded excavations Consequence : Drowning, burial |
15 P3×I5 | • Collective protection at water edges |
• Life jackets and lifebuoy nearby |
| R-005 | Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work Consequence : Site stoppages, degraded quality (concrete, paint), delay |
15 P5×I3 | • Season-aware scheduling |
• Temporary protection |
| R-006 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-007 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
15 P3×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-008 | Struck by earthmoving equipment
Cause : Excavator or loader manoeuvring, blind spot, pedestrians within reach Consequence : Crushing, serious injuries |
12 P3×I4 | • Exclusion zone and eye contact • Cameras and presence detection on machines |
|
| R-009 | Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area Consequence : Pedestrian or worker struck, material damage |
12 P3×I4 | • Delivery plan and dedicated area • Banksman for manoeuvres |
|
| R-010 | Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects Consequence : Injury to a third party, prosecution |
12 P3×I4 | • Continuous fencing and protected footpath • Fans and nets against falling objects |
|
| R-011 | Accident in a tunnel, shaft or gallery
Cause : Oxygen-depleted air, collapse, vehicle traffic, difficult evacuation Consequence : Suffocation, burial, casualties hard to rescue |
12 P3×I4 | • Ventilation and continuous gas monitoring |
• Underground rescue plan |
| R-012 | Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans Consequence : Leak, explosion, neighbourhood evacuation |
12 P3×I4 | • Request plans and hand-dig trial holes |
• Emergency procedure for leaks |
| R-013 | Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations Consequence : Destruction of works, injuries, major delays |
12 P4×I3 | • Combustible waste management and storage areas |
• Extinguishers and response plan |
| R-014 | Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings Consequence : Collision, load falling on third parties |
12 P3×I4 | • Layout study and anti-collision system • No loads over public areas |
|
| R-015 | Damage to underground utilities
Cause : Incomplete utility maps, digging without prior detection Consequence : Gas, power or water outage, explosion, injuries |
12 P3×I4 | • Utility maps and detection before digging |
• Hand digging near utilities |
| R-016 | Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction Consequence : Serious and irreversible respiratory diseases |
9 P3×I3 | • Tools with water suppression or on-tool extraction |
• Suitable respiratory protection |
| R-017 | Defects from concreting in cold or hot weather
Cause : Frost, rapid drying, insufficient curing Consequence : Low strength, cracking, partial demolition |
9 P3×I3 | • Extreme-weather concreting procedure |
• Strength tests before striking formwork |
| R-018 | Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time Consequence : Site blocked, delayed handover |
9 P3×I3 | • Requests to utilities from the design stage |
• Track utilities at site meetings |
| R-019 | Water ingress during roofing works
Cause : Roof left open, inadequate sheeting, unexpected showers Consequence : Interior damage, claims |
9 P3×I3 | • Open only what can be closed the same day |
• Emergency sheeting and weather watch |
| R-020 | Contaminated soil or materials discovered
Cause : Former industrial site, fill of unknown quality Consequence : Costly disposal, delay, environmental obligations |
9 P3×I3 | • Prior soil study and analyses |
• Unforeseen ground clause in the contract |
| R-021 | Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather Consequence : Nuisance to neighbours, complaints, health effects |
9 P3×I3 | • Damping down and covering stockpiles |
• Stop dusty operations in high wind |
| R-022 | Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure Consequence : Loss-making project, tension with the client |
9 P3×I3 | • Bid review by a second person • Explicit pricing of risks |
|
| R-023 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-024 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
9 P3×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-025 | Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades Consequence : Rework, retentions, delayed handover |
9 P3×I3 | • Hold points and self-inspections |
• Pre-handover inspection per trade |
| R-026 | Rising material prices
Cause : Volatile steel, concrete, timber or energy prices Consequence : Eroded margin, difficulty holding the price |
9 P3×I3 | • Price revision clause |
• Early purchase of key materials |
| R-027 | Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose Consequence : Soil and water pollution, costly clean-up |
9 P3×I3 | • Sealed refuelling area |
• Spill kit and response procedure |
| R-028 | Damage to neighbouring buildings
Cause : Vibrations, excavation, dewatering, underpinning Consequence : Cracks in neighbouring properties, disputes, site stoppage |
8 P2×I4 | • Pre-works condition survey |
• Vibration and crack monitoring |
| R-029 | Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability Consequence : Fines, producer liability, damaged image |
8 P4×I2 | • Sorting at source and approved contractors |
• Waste register and transfer notes |
| R-030 | Late permit for use of the public road
Cause : Late application, refusal, imposed conditions Consequence : Late start, deliveries impossible |
6 P2×I3 | • Early application with signage plan |
• Alternative logistics |
| R-031 | Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed Consequence : Complaints, municipal orders, delay |
6 P2×I3 | • Advance notice and residents’ contact • Working hours and dust control |
|
| R-032 | Working in the cold
Cause : Low temperatures, wind, humidity, cold stores Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground |
6 P2×I3 | • Suitable clothing and heated rooms • Organise exposure time |
|
| R-033 | Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection Consequence : Sunburn, long-term skin cancer |
6 P2×I3 | • Schedule work at less exposed times |
• Covering clothing and sunscreen |
| R-034 | Poor indoor air quality
Cause : Insufficient ventilation, emissive products, dense occupancy Consequence : Discomfort, headaches, absenteeism, spread of infections |
6 P2×I3 | • CO2 sensors and ventilation maintenance • Low-emission materials and products |
|
| R-035 | Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted Consequence : Harm to mother or child, non-compliance |
6 P2×I3 | • Specific assessment once pregnancy is announced • List of at-risk jobs prepared in advance |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Road and utility works”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.