Risk register example: Demolition and asbestos removal

Demolishing a building: structural collapse, asbestos and lead, dust, noise and neighbours.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate18
● High10
● Critical7

Assumptions: Construction / civil works · Execution / works · 15 people · demolition or dismantling, old building (asbestos, lead possible), work at height (roofs, scaffolding, platforms), site vehicles, forklifts, construction machinery, noise or vibration, heavy or repetitive manual handling, dense urban area, neighbours nearby, permits or authorisations required, subcontractors involved.

Ref.RiskScorePreventionProtection
R-001 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
20 P4×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-002 Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building
Consequence : Serious delayed illness, works stopped, costly unplanned removal
20 P4×I5 • Asbestos and lead survey before works
• Stop-work procedure on discovery
R-003 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
16 P4×I4 • Mobile platforms instead of ladders
• Visual check before use
R-004 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
16 P4×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-005 Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings
Consequence : Serious or fatal fall
15 P3×I5 • Cover and mark floor openings
• Nets or walkways on fragile roofs
R-006 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-007 Unplanned collapse during demolition
Cause : Poorly known structure, unsuitable demolition sequence
Consequence : Burial, injuries, damage to neighbouring structures
15 P3×I5 • Structural assessment and method statement
• Extended safety perimeter
R-008 Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements
Consequence : Burial, falls
12 P3×I4 • Structural survey by an engineer
• Temporary propping
R-009 Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area
Consequence : Pedestrian or worker struck, material damage
12 P3×I4 • Delivery plan and dedicated area
• Banksman for manoeuvres
R-010 Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people
Consequence : Falls of people and materials
12 P3×I4 • Erection by qualified staff and handover
• Periodic inspection and after storms
R-011 Struck by earthmoving equipment
Cause : Excavator or loader manoeuvring, blind spot, pedestrians within reach
Consequence : Crushing, serious injuries
12 P3×I4 • Exclusion zone and eye contact
• Cameras and presence detection on machines
R-012 Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects
Consequence : Injury to a third party, prosecution
12 P3×I4 • Continuous fencing and protected footpath
• Fans and nets against falling objects
R-013 Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings
Consequence : Collision, load falling on third parties
12 P3×I4 • Layout study and anti-collision system
• No loads over public areas
R-014 Theft or vandalism on site
Cause : Unfenced site, valuable equipment left overnight
Consequence : Losses, delays, damage to works
12 P3×I4 • Fencing, lighting and security
• Contractor’s all-risks insurance
R-015 Bankruptcy of a subcontractor or site contractor
Cause : Weak cash position, prices too low, dependence on one large client
Consequence : Work package to re-tender, delay, defects left unremedied
12 P3×I4 • Financial health check
• Performance bond and retention
R-016 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-017 Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures
Consequence : Chronic pain, sick leave, unfitness for work
12 P4×I3 • Handling aids
• Task rotation and handling training
R-018 Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction
Consequence : Serious and irreversible respiratory diseases
9 P3×I3 • Tools with water suppression or on-tool extraction
• Suitable respiratory protection
R-019 Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time
Consequence : Site blocked, delayed handover
9 P3×I3 • Requests to utilities from the design stage
• Track utilities at site meetings
R-020 Contaminated soil or materials discovered
Cause : Former industrial site, fill of unknown quality
Consequence : Costly disposal, delay, environmental obligations
9 P3×I3 • Prior soil study and analyses
• Unforeseen ground clause in the contract
R-021 Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished
Consequence : Idle time, rework, accumulated delay at the end of the works
9 P3×I3 • Weekly coordination schedule
• Handover of work areas between trades
R-022 Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather
Consequence : Nuisance to neighbours, complaints, health effects
9 P3×I3 • Damping down and covering stockpiles
• Stop dusty operations in high wind
R-023 Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades
Consequence : Rework, retentions, delayed handover
9 P3×I3 • Hold points and self-inspections
• Pre-handover inspection per trade
R-024 Rising material prices
Cause : Volatile steel, concrete, timber or energy prices
Consequence : Eroded margin, difficulty holding the price
9 P3×I3 • Price revision clause
• Early purchase of key materials
R-025 Unexpected discovery in the existing building
Cause : Inaccurate old drawings, hidden structure or networks, degraded materials
Consequence : Extra studies and works, site stoppage, extra costs
8 P2×I4 • Prior surveys and investigations
• Dedicated allowance for existing-building risks
R-026 Damage to neighbouring buildings
Cause : Vibrations, excavation, dewatering, underpinning
Consequence : Cracks in neighbouring properties, disputes, site stoppage
8 P2×I4 • Pre-works condition survey
• Vibration and crack monitoring
R-027 Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability
Consequence : Fines, producer liability, damaged image
8 P4×I2 • Sorting at source and approved contractors
• Waste register and transfer notes
R-028 Poor ground conditions
Cause : Limited or missing geotechnical survey
Consequence : Foundations to redesign, major extra cost and delay
8 P2×I4 • Geotechnical survey suited to the project
• Costed foundation alternatives
R-029 Dispute with the client
Cause : Unsigned additional work, no meeting minutes
Consequence : Blocked payments, legal proceedings
8 P2×I4 • Signed instructions before execution
• Minutes and dated photos
R-030 Late permit for use of the public road
Cause : Late application, refusal, imposed conditions
Consequence : Late start, deliveries impossible
6 P2×I3 • Early application with signage plan
• Alternative logistics
R-031 Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed
Consequence : Complaints, municipal orders, delay
6 P2×I3 • Advance notice and residents’ contact
• Working hours and dust control
R-032 Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks
Consequence : Penalties, joint liability, site stoppage
6 P2×I3 • Access control and check of declarations
• Limit chain subcontracting
R-033 Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists
Consequence : Low back pain, slipped discs
6 P2×I3 • Material hoists and delivery close to the workplace
• Lighter packaging
R-034 Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register
Consequence : Fines, liability for fly-tipping
6 P2×I3 • Separate skips and signage
• Register and transfer notes kept
R-035 Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction
Consequence : Respiratory diseases, irritation
6 P2×I3 • Local extraction and wet methods
• Suitable respiratory protection

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Demolition and asbestos removal”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free