Risk register example: Demolition and asbestos removal
Demolishing a building: structural collapse, asbestos and lead, dust, noise and neighbours.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Construction / civil works · Execution / works · 15 people · demolition or dismantling, old building (asbestos, lead possible), work at height (roofs, scaffolding, platforms), site vehicles, forklifts, construction machinery, noise or vibration, heavy or repetitive manual handling, dense urban area, neighbours nearby, permits or authorisations required, subcontractors involved.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
20 P4×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-002 | Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building Consequence : Serious delayed illness, works stopped, costly unplanned removal |
20 P4×I5 | • Asbestos and lead survey before works |
• Stop-work procedure on discovery |
| R-003 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
16 P4×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-004 | Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below Consequence : Serious injury to people below, material damage |
16 P4×I4 | • Toe boards, nets and tethered tools |
• Marked exclusion zone below |
| R-005 | Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings Consequence : Serious or fatal fall |
15 P3×I5 | • Cover and mark floor openings • Nets or walkways on fragile roofs |
|
| R-006 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-007 | Unplanned collapse during demolition
Cause : Poorly known structure, unsuitable demolition sequence Consequence : Burial, injuries, damage to neighbouring structures |
15 P3×I5 | • Structural assessment and method statement |
• Extended safety perimeter |
| R-008 | Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements Consequence : Burial, falls |
12 P3×I4 | • Structural survey by an engineer • Temporary propping |
|
| R-009 | Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area Consequence : Pedestrian or worker struck, material damage |
12 P3×I4 | • Delivery plan and dedicated area • Banksman for manoeuvres |
|
| R-010 | Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people Consequence : Falls of people and materials |
12 P3×I4 | • Erection by qualified staff and handover • Periodic inspection and after storms |
|
| R-011 | Struck by earthmoving equipment
Cause : Excavator or loader manoeuvring, blind spot, pedestrians within reach Consequence : Crushing, serious injuries |
12 P3×I4 | • Exclusion zone and eye contact • Cameras and presence detection on machines |
|
| R-012 | Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects Consequence : Injury to a third party, prosecution |
12 P3×I4 | • Continuous fencing and protected footpath • Fans and nets against falling objects |
|
| R-013 | Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings Consequence : Collision, load falling on third parties |
12 P3×I4 | • Layout study and anti-collision system • No loads over public areas |
|
| R-014 | Theft or vandalism on site
Cause : Unfenced site, valuable equipment left overnight Consequence : Losses, delays, damage to works |
12 P3×I4 | • Fencing, lighting and security |
• Contractor’s all-risks insurance |
| R-015 | Bankruptcy of a subcontractor or site contractor
Cause : Weak cash position, prices too low, dependence on one large client Consequence : Work package to re-tender, delay, defects left unremedied |
12 P3×I4 | • Financial health check |
• Performance bond and retention |
| R-016 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-017 | Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures Consequence : Chronic pain, sick leave, unfitness for work |
12 P4×I3 | • Handling aids • Task rotation and handling training |
|
| R-018 | Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction Consequence : Serious and irreversible respiratory diseases |
9 P3×I3 | • Tools with water suppression or on-tool extraction |
• Suitable respiratory protection |
| R-019 | Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time Consequence : Site blocked, delayed handover |
9 P3×I3 | • Requests to utilities from the design stage |
• Track utilities at site meetings |
| R-020 | Contaminated soil or materials discovered
Cause : Former industrial site, fill of unknown quality Consequence : Costly disposal, delay, environmental obligations |
9 P3×I3 | • Prior soil study and analyses |
• Unforeseen ground clause in the contract |
| R-021 | Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished Consequence : Idle time, rework, accumulated delay at the end of the works |
9 P3×I3 | • Weekly coordination schedule |
• Handover of work areas between trades |
| R-022 | Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather Consequence : Nuisance to neighbours, complaints, health effects |
9 P3×I3 | • Damping down and covering stockpiles |
• Stop dusty operations in high wind |
| R-023 | Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades Consequence : Rework, retentions, delayed handover |
9 P3×I3 | • Hold points and self-inspections |
• Pre-handover inspection per trade |
| R-024 | Rising material prices
Cause : Volatile steel, concrete, timber or energy prices Consequence : Eroded margin, difficulty holding the price |
9 P3×I3 | • Price revision clause |
• Early purchase of key materials |
| R-025 | Unexpected discovery in the existing building
Cause : Inaccurate old drawings, hidden structure or networks, degraded materials Consequence : Extra studies and works, site stoppage, extra costs |
8 P2×I4 | • Prior surveys and investigations |
• Dedicated allowance for existing-building risks |
| R-026 | Damage to neighbouring buildings
Cause : Vibrations, excavation, dewatering, underpinning Consequence : Cracks in neighbouring properties, disputes, site stoppage |
8 P2×I4 | • Pre-works condition survey |
• Vibration and crack monitoring |
| R-027 | Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability Consequence : Fines, producer liability, damaged image |
8 P4×I2 | • Sorting at source and approved contractors |
• Waste register and transfer notes |
| R-028 | Poor ground conditions
Cause : Limited or missing geotechnical survey Consequence : Foundations to redesign, major extra cost and delay |
8 P2×I4 | • Geotechnical survey suited to the project |
• Costed foundation alternatives |
| R-029 | Dispute with the client
Cause : Unsigned additional work, no meeting minutes Consequence : Blocked payments, legal proceedings |
8 P2×I4 | • Signed instructions before execution |
• Minutes and dated photos |
| R-030 | Late permit for use of the public road
Cause : Late application, refusal, imposed conditions Consequence : Late start, deliveries impossible |
6 P2×I3 | • Early application with signage plan |
• Alternative logistics |
| R-031 | Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed Consequence : Complaints, municipal orders, delay |
6 P2×I3 | • Advance notice and residents’ contact • Working hours and dust control |
|
| R-032 | Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks Consequence : Penalties, joint liability, site stoppage |
6 P2×I3 | • Access control and check of declarations • Limit chain subcontracting |
|
| R-033 | Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists Consequence : Low back pain, slipped discs |
6 P2×I3 | • Material hoists and delivery close to the workplace • Lighter packaging |
|
| R-034 | Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register Consequence : Fines, liability for fly-tipping |
6 P2×I3 | • Separate skips and signage • Register and transfer notes kept |
|
| R-035 | Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction Consequence : Respiratory diseases, irritation |
6 P2×I3 | • Local extraction and wet methods |
• Suitable respiratory protection |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.