Risk register example: Bridge or civil engineering structure

Major civil works: temporary works, heavy lifting, water, traffic and public procurement.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate14
● High16
● Critical5

Assumptions: Construction / civil works · Execution / works · 40 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), excavation, trenches, earthworks, near water or flood-prone area, site vehicles, forklifts, construction machinery, work on or near public roads, mainly outdoors, works during winter, public procurement, permits or authorisations required, several companies working at the same time, protected natural area or sensitive environment.

Ref.RiskScorePreventionProtection
R-001 Drowning or burial near water
Cause : Bank works, cofferdams, shafts, flooded excavations
Consequence : Drowning, burial
15 P3×I5 • Collective protection at water edges
• Life jackets and lifebuoy nearby
R-002 Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings
Consequence : Serious or fatal fall
15 P3×I5 • Cover and mark floor openings
• Nets or walkways on fragile roofs
R-003 Crane or aerial platform overturning
Cause : Weak ground, inadequate outriggers, high wind, overloading
Consequence : Crushing, death, major damage
15 P3×I5 • Ground assessment and outrigger pads
• Anemometer and wind stop threshold
R-004 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
15 P3×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-005 Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work
Consequence : Site stoppages, degraded quality (concrete, paint), delay
15 P5×I3 • Season-aware scheduling
• Temporary protection
R-006 Struck by earthmoving equipment
Cause : Excavator or loader manoeuvring, blind spot, pedestrians within reach
Consequence : Crushing, serious injuries
12 P3×I4 • Exclusion zone and eye contact
• Cameras and presence detection on machines
R-007 Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people
Consequence : Falls of people and materials
12 P3×I4 • Erection by qualified staff and handover
• Periodic inspection and after storms
R-008 Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements
Consequence : Burial, falls
12 P3×I4 • Structural survey by an engineer
• Temporary propping
R-009 Accident in a tunnel, shaft or gallery
Cause : Oxygen-depleted air, collapse, vehicle traffic, difficult evacuation
Consequence : Suffocation, burial, casualties hard to rescue
12 P3×I4 • Ventilation and continuous gas monitoring
• Underground rescue plan
R-010 Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings
Consequence : Collision, load falling on third parties
12 P3×I4 • Layout study and anti-collision system
• No loads over public areas
R-011 Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans
Consequence : Leak, explosion, neighbourhood evacuation
12 P3×I4 • Request plans and hand-dig trial holes
• Emergency procedure for leaks
R-012 Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished
Consequence : Idle time, rework, accumulated delay at the end of the works
12 P4×I3 • Weekly coordination schedule
• Handover of work areas between trades
R-013 Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area
Consequence : Pedestrian or worker struck, material damage
12 P3×I4 • Delivery plan and dedicated area
• Banksman for manoeuvres
R-014 Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time
Consequence : Site blocked, delayed handover
12 P4×I3 • Requests to utilities from the design stage
• Track utilities at site meetings
R-015 Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations
Consequence : Destruction of works, injuries, major delays
12 P4×I3 • Combustible waste management and storage areas
• Extinguishers and response plan
R-016 Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects
Consequence : Injury to a third party, prosecution
12 P3×I4 • Continuous fencing and protected footpath
• Fans and nets against falling objects
R-017 Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure
Consequence : Loss-making project, tension with the client
12 P3×I4 • Bid review by a second person
• Explicit pricing of risks
R-018 Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts
Consequence : Damage to installations, business interruption, repair costs
12 P3×I4 • Climate vulnerability assessment of the site
• Weather alert and safety plan
R-019 Pollution of a watercourse or sensitive environment
Cause : Run-off, fuel stored without bunding, accidental release
Consequence : Harm to wildlife and plants, sanctions, costly restoration
12 P3×I4 • Bunding, refuelling area and settling ponds
• Spill kits and alert procedure
R-020 Poor ground conditions
Cause : Limited or missing geotechnical survey
Consequence : Foundations to redesign, major extra cost and delay
12 P3×I4 • Geotechnical survey suited to the project
• Costed foundation alternatives
R-021 Rising material prices
Cause : Volatile steel, concrete, timber or energy prices
Consequence : Eroded margin, difficulty holding the price
12 P3×I4 • Price revision clause
• Early purchase of key materials
R-022 Defects from concreting in cold or hot weather
Cause : Frost, rapid drying, insufficient curing
Consequence : Low strength, cracking, partial demolition
9 P3×I3 • Extreme-weather concreting procedure
• Strength tests before striking formwork
R-023 Water ingress during roofing works
Cause : Roof left open, inadequate sheeting, unexpected showers
Consequence : Interior damage, claims
9 P3×I3 • Open only what can be closed the same day
• Emergency sheeting and weather watch
R-024 Late permit for use of the public road
Cause : Late application, refusal, imposed conditions
Consequence : Late start, deliveries impossible
9 P3×I3 • Early application with signage plan
• Alternative logistics
R-025 Contaminated soil or materials discovered
Cause : Former industrial site, fill of unknown quality
Consequence : Costly disposal, delay, environmental obligations
9 P3×I3 • Prior soil study and analyses
• Unforeseen ground clause in the contract
R-026 Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain
Consequence : Work stoppages, damage, design to revise
9 P3×I3 • Include climate scenarios in design
• Plan to adapt hours and works
R-027 Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather
Consequence : Nuisance to neighbours, complaints, health effects
9 P3×I3 • Damping down and covering stockpiles
• Stop dusty operations in high wind
R-028 Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction
Consequence : Serious and irreversible respiratory diseases
9 P3×I3 • Tools with water suppression or on-tool extraction
• Suitable respiratory protection
R-029 Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions
Consequence : Rework, clashes between trades, extra costs
9 P3×I3 • Coordination and clash detection
• Drawing version control
R-030 Harm to a protected species or habitat
Cause : Works during nesting season, destruction of hedges or wetlands
Consequence : Site stoppage, penalties, compensation duties
9 P3×I3 • Prior ecological survey
• Schedule avoiding sensitive periods
R-031 Damage to neighbouring buildings
Cause : Vibrations, excavation, dewatering, underpinning
Consequence : Cracks in neighbouring properties, disputes, site stoppage
8 P2×I4 • Pre-works condition survey
• Vibration and crack monitoring
R-032 BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities
Consequence : Undetected clashes, rework
8 P2×I4 • BIM execution plan at the start
• BIM coordinator
R-033 Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks
Consequence : Penalties, joint liability, site stoppage
6 P2×I3 • Access control and check of declarations
• Limit chain subcontracting
R-034 Working in the cold
Cause : Low temperatures, wind, humidity, cold stores
Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground
6 P2×I3 • Suitable clothing and heated rooms
• Organise exposure time
R-035 Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection
Consequence : Sunburn, long-term skin cancer
6 P2×I3 • Schedule work at less exposed times
• Covering clothing and sunscreen

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Bridge or civil engineering structure”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples