Risk register example: Bridge or civil engineering structure
Major civil works: temporary works, heavy lifting, water, traffic and public procurement.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Construction / civil works · Execution / works · 40 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), excavation, trenches, earthworks, near water or flood-prone area, site vehicles, forklifts, construction machinery, work on or near public roads, mainly outdoors, works during winter, public procurement, permits or authorisations required, several companies working at the same time, protected natural area or sensitive environment.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Drowning or burial near water
Cause : Bank works, cofferdams, shafts, flooded excavations Consequence : Drowning, burial |
15 P3×I5 | • Collective protection at water edges |
• Life jackets and lifebuoy nearby |
| R-002 | Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings Consequence : Serious or fatal fall |
15 P3×I5 | • Cover and mark floor openings • Nets or walkways on fragile roofs |
|
| R-003 | Crane or aerial platform overturning
Cause : Weak ground, inadequate outriggers, high wind, overloading Consequence : Crushing, death, major damage |
15 P3×I5 | • Ground assessment and outrigger pads • Anemometer and wind stop threshold |
|
| R-004 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
15 P3×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-005 | Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work Consequence : Site stoppages, degraded quality (concrete, paint), delay |
15 P5×I3 | • Season-aware scheduling |
• Temporary protection |
| R-006 | Struck by earthmoving equipment
Cause : Excavator or loader manoeuvring, blind spot, pedestrians within reach Consequence : Crushing, serious injuries |
12 P3×I4 | • Exclusion zone and eye contact • Cameras and presence detection on machines |
|
| R-007 | Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people Consequence : Falls of people and materials |
12 P3×I4 | • Erection by qualified staff and handover • Periodic inspection and after storms |
|
| R-008 | Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements Consequence : Burial, falls |
12 P3×I4 | • Structural survey by an engineer • Temporary propping |
|
| R-009 | Accident in a tunnel, shaft or gallery
Cause : Oxygen-depleted air, collapse, vehicle traffic, difficult evacuation Consequence : Suffocation, burial, casualties hard to rescue |
12 P3×I4 | • Ventilation and continuous gas monitoring |
• Underground rescue plan |
| R-010 | Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings Consequence : Collision, load falling on third parties |
12 P3×I4 | • Layout study and anti-collision system • No loads over public areas |
|
| R-011 | Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans Consequence : Leak, explosion, neighbourhood evacuation |
12 P3×I4 | • Request plans and hand-dig trial holes |
• Emergency procedure for leaks |
| R-012 | Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished Consequence : Idle time, rework, accumulated delay at the end of the works |
12 P4×I3 | • Weekly coordination schedule |
• Handover of work areas between trades |
| R-013 | Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area Consequence : Pedestrian or worker struck, material damage |
12 P3×I4 | • Delivery plan and dedicated area • Banksman for manoeuvres |
|
| R-014 | Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time Consequence : Site blocked, delayed handover |
12 P4×I3 | • Requests to utilities from the design stage |
• Track utilities at site meetings |
| R-015 | Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations Consequence : Destruction of works, injuries, major delays |
12 P4×I3 | • Combustible waste management and storage areas |
• Extinguishers and response plan |
| R-016 | Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects Consequence : Injury to a third party, prosecution |
12 P3×I4 | • Continuous fencing and protected footpath • Fans and nets against falling objects |
|
| R-017 | Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure Consequence : Loss-making project, tension with the client |
12 P3×I4 | • Bid review by a second person • Explicit pricing of risks |
|
| R-018 | Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts Consequence : Damage to installations, business interruption, repair costs |
12 P3×I4 | • Climate vulnerability assessment of the site |
• Weather alert and safety plan |
| R-019 | Pollution of a watercourse or sensitive environment
Cause : Run-off, fuel stored without bunding, accidental release Consequence : Harm to wildlife and plants, sanctions, costly restoration |
12 P3×I4 | • Bunding, refuelling area and settling ponds |
• Spill kits and alert procedure |
| R-020 | Poor ground conditions
Cause : Limited or missing geotechnical survey Consequence : Foundations to redesign, major extra cost and delay |
12 P3×I4 | • Geotechnical survey suited to the project |
• Costed foundation alternatives |
| R-021 | Rising material prices
Cause : Volatile steel, concrete, timber or energy prices Consequence : Eroded margin, difficulty holding the price |
12 P3×I4 | • Price revision clause |
• Early purchase of key materials |
| R-022 | Defects from concreting in cold or hot weather
Cause : Frost, rapid drying, insufficient curing Consequence : Low strength, cracking, partial demolition |
9 P3×I3 | • Extreme-weather concreting procedure |
• Strength tests before striking formwork |
| R-023 | Water ingress during roofing works
Cause : Roof left open, inadequate sheeting, unexpected showers Consequence : Interior damage, claims |
9 P3×I3 | • Open only what can be closed the same day |
• Emergency sheeting and weather watch |
| R-024 | Late permit for use of the public road
Cause : Late application, refusal, imposed conditions Consequence : Late start, deliveries impossible |
9 P3×I3 | • Early application with signage plan |
• Alternative logistics |
| R-025 | Contaminated soil or materials discovered
Cause : Former industrial site, fill of unknown quality Consequence : Costly disposal, delay, environmental obligations |
9 P3×I3 | • Prior soil study and analyses |
• Unforeseen ground clause in the contract |
| R-026 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
9 P3×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-027 | Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather Consequence : Nuisance to neighbours, complaints, health effects |
9 P3×I3 | • Damping down and covering stockpiles |
• Stop dusty operations in high wind |
| R-028 | Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction Consequence : Serious and irreversible respiratory diseases |
9 P3×I3 | • Tools with water suppression or on-tool extraction |
• Suitable respiratory protection |
| R-029 | Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions Consequence : Rework, clashes between trades, extra costs |
9 P3×I3 | • Coordination and clash detection • Drawing version control |
|
| R-030 | Harm to a protected species or habitat
Cause : Works during nesting season, destruction of hedges or wetlands Consequence : Site stoppage, penalties, compensation duties |
9 P3×I3 | • Prior ecological survey • Schedule avoiding sensitive periods |
|
| R-031 | Damage to neighbouring buildings
Cause : Vibrations, excavation, dewatering, underpinning Consequence : Cracks in neighbouring properties, disputes, site stoppage |
8 P2×I4 | • Pre-works condition survey |
• Vibration and crack monitoring |
| R-032 | BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities Consequence : Undetected clashes, rework |
8 P2×I4 | • BIM execution plan at the start • BIM coordinator |
|
| R-033 | Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks Consequence : Penalties, joint liability, site stoppage |
6 P2×I3 | • Access control and check of declarations • Limit chain subcontracting |
|
| R-034 | Working in the cold
Cause : Low temperatures, wind, humidity, cold stores Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground |
6 P2×I3 | • Suitable clothing and heated rooms • Organise exposure time |
|
| R-035 | Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection Consequence : Sunburn, long-term skin cancer |
6 P2×I3 | • Schedule work at less exposed times |
• Covering clothing and sunscreen |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Bridge or civil engineering structure”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.