Risk register example: House or apartment renovation

Renovating a home: hidden defects, old materials, small budget overruns that add up and coordination between trades.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate21
● High9
● Critical5

Assumptions: Construction / civil works · Execution / works · 6 people · old building (asbestos, lead possible), electrical work or work near live installations, heavy or repetitive manual handling, noise or vibration, subcontractors involved, several companies working at the same time, fixed-price contract, occupied site (staff, residents, patients nearby), dense urban area, neighbours nearby.

Ref.RiskScorePreventionProtection
R-001 Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan
Consequence : Serious accident, shared liability, site stoppage
20 P5×I4 • Prevention plan and joint inspection
• Daily coordination of work
R-002 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
16 P4×I4 • Mobile platforms instead of ladders
• Visual check before use
R-003 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-004 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-005 Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building
Consequence : Serious delayed illness, works stopped, costly unplanned removal
15 P3×I5 • Asbestos and lead survey before works
• Stop-work procedure on discovery
R-006 Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations
Consequence : Destruction of works, injuries, major delays
12 P4×I3 • Combustible waste management and storage areas
• Extinguishers and response plan
R-007 Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area
Consequence : Pedestrian or worker struck, material damage
12 P3×I4 • Delivery plan and dedicated area
• Banksman for manoeuvres
R-008 Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects
Consequence : Injury to a third party, prosecution
12 P3×I4 • Continuous fencing and protected footpath
• Fans and nets against falling objects
R-009 Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings
Consequence : Collision, load falling on third parties
12 P3×I4 • Layout study and anti-collision system
• No loads over public areas
R-010 Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking
Consequence : Complaints, imposed working-hour restrictions, delay
12 P4×I3 • Neighbour information and dedicated contact
• Dust control and suitable hours
R-011 Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures
Consequence : Chronic pain, sick leave, unfitness for work
12 P4×I3 • Handling aids
• Task rotation and handling training
R-012 Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation
Consequence : Tendinitis, carpal tunnel syndrome, sick leave
12 P4×I3 • Ergonomic analysis of repetitive tasks
• Job rotation
R-013 Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection
Consequence : Lacerations, tendon injuries
12 P4×I3 • Retractable-blade tools
• Suitable cut-resistant gloves
R-014 Theft or vandalism on site
Cause : Unfenced site, valuable equipment left overnight
Consequence : Losses, delays, damage to works
12 P3×I4 • Fencing, lighting and security
• Contractor’s all-risks insurance
R-015 Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished
Consequence : Idle time, rework, accumulated delay at the end of the works
9 P3×I3 • Weekly coordination schedule
• Handover of work areas between trades
R-016 Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time
Consequence : Site blocked, delayed handover
9 P3×I3 • Requests to utilities from the design stage
• Track utilities at site meetings
R-017 Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions
Consequence : Rework, clashes between trades, extra costs
9 P3×I3 • Coordination and clash detection
• Drawing version control
R-018 Extra work not approved in writing
Cause : Verbal client requests, changes during construction
Consequence : Unpaid work, dispute at completion
9 P3×I3 • Written instruction before execution
• Variation tracking table
R-019 Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure
Consequence : Loss-making project, tension with the client
9 P3×I3 • Bid review by a second person
• Explicit pricing of risks
R-020 Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture
Consequence : Bruises, cuts, falls
9 P3×I3 • Daily tidy-up and defined storage areas
• Regular safety walks
R-021 Handover delayed by numerous snags
Cause : Rushed finishes at the end, late inspections
Consequence : Delayed payment, penalties, dissatisfaction
9 P3×I3 • Pre-handover by area
• Snag clearance schedule
R-022 Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision
Consequence : Critical path blocked, delay
9 P3×I3 • External dependency log
• Prepared workaround
R-023 Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction
Consequence : Serious and irreversible respiratory diseases
9 P3×I3 • Tools with water suppression or on-tool extraction
• Suitable respiratory protection
R-024 Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements
Consequence : Complaints, enforced stoppage, fines
9 P3×I3 • Quieter equipment and acoustic screens
• Noise measurements and adapted hours
R-025 Unexpected discovery in the existing building
Cause : Inaccurate old drawings, hidden structure or networks, degraded materials
Consequence : Extra studies and works, site stoppage, extra costs
8 P2×I4 • Prior surveys and investigations
• Dedicated allowance for existing-building risks
R-026 Post-handover defects engaging the builder’s liability
Cause : Waterproofing, structural or equipment defects appearing after handover
Consequence : Costly repairs, insurance claims, reputation
8 P2×I4 • Self-checks and quality hold points
• Suitable warranties and liability insurance
R-027 BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities
Consequence : Undetected clashes, rework
8 P2×I4 • BIM execution plan at the start
• BIM coordinator
R-028 Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance
Consequence : Unpaid invoices, lost revenue, cash strain
8 P2×I4 • Monitor key customers’ financial health
• Credit insurance or payment guarantees
R-029 Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed
Consequence : Complaints, municipal orders, delay
6 P2×I3 • Advance notice and residents’ contact
• Working hours and dust control
R-030 Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks
Consequence : Penalties, joint liability, site stoppage
6 P2×I3 • Access control and check of declarations
• Limit chain subcontracting
R-031 Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists
Consequence : Low back pain, slipped discs
6 P2×I3 • Material hoists and delivery close to the workplace
• Lighter packaging
R-032 Late permit for use of the public road
Cause : Late application, refusal, imposed conditions
Consequence : Late start, deliveries impossible
6 P2×I3 • Early application with signage plan
• Alternative logistics
R-033 Poorly drafted or incomplete contract
Cause : Unclear liabilities, deadlines, acceptance or penalties, no legal review
Consequence : Disputes, unpaid work, excessive liability
6 P2×I3 • Checklist of essential clauses
• Legal review of major contracts
R-034 No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified
Consequence : Avoidable accidents, non-compliance on inspection
6 P2×I3 • Annual review and after every change
• Worker participation
R-035 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “House or apartment renovation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free