Risk register example: House or apartment renovation
Renovating a home: hidden defects, old materials, small budget overruns that add up and coordination between trades.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Construction / civil works · Execution / works · 6 people · old building (asbestos, lead possible), electrical work or work near live installations, heavy or repetitive manual handling, noise or vibration, subcontractors involved, several companies working at the same time, fixed-price contract, occupied site (staff, residents, patients nearby), dense urban area, neighbours nearby.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
20 P5×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-002 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
16 P4×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-003 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-004 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-005 | Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building Consequence : Serious delayed illness, works stopped, costly unplanned removal |
15 P3×I5 | • Asbestos and lead survey before works |
• Stop-work procedure on discovery |
| R-006 | Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations Consequence : Destruction of works, injuries, major delays |
12 P4×I3 | • Combustible waste management and storage areas |
• Extinguishers and response plan |
| R-007 | Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area Consequence : Pedestrian or worker struck, material damage |
12 P3×I4 | • Delivery plan and dedicated area • Banksman for manoeuvres |
|
| R-008 | Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects Consequence : Injury to a third party, prosecution |
12 P3×I4 | • Continuous fencing and protected footpath • Fans and nets against falling objects |
|
| R-009 | Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings Consequence : Collision, load falling on third parties |
12 P3×I4 | • Layout study and anti-collision system • No loads over public areas |
|
| R-010 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
12 P4×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-011 | Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures Consequence : Chronic pain, sick leave, unfitness for work |
12 P4×I3 | • Handling aids • Task rotation and handling training |
|
| R-012 | Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation Consequence : Tendinitis, carpal tunnel syndrome, sick leave |
12 P4×I3 | • Ergonomic analysis of repetitive tasks • Job rotation |
|
| R-013 | Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection Consequence : Lacerations, tendon injuries |
12 P4×I3 | • Retractable-blade tools |
• Suitable cut-resistant gloves |
| R-014 | Theft or vandalism on site
Cause : Unfenced site, valuable equipment left overnight Consequence : Losses, delays, damage to works |
12 P3×I4 | • Fencing, lighting and security |
• Contractor’s all-risks insurance |
| R-015 | Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished Consequence : Idle time, rework, accumulated delay at the end of the works |
9 P3×I3 | • Weekly coordination schedule |
• Handover of work areas between trades |
| R-016 | Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time Consequence : Site blocked, delayed handover |
9 P3×I3 | • Requests to utilities from the design stage |
• Track utilities at site meetings |
| R-017 | Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions Consequence : Rework, clashes between trades, extra costs |
9 P3×I3 | • Coordination and clash detection • Drawing version control |
|
| R-018 | Extra work not approved in writing
Cause : Verbal client requests, changes during construction Consequence : Unpaid work, dispute at completion |
9 P3×I3 | • Written instruction before execution |
• Variation tracking table |
| R-019 | Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure Consequence : Loss-making project, tension with the client |
9 P3×I3 | • Bid review by a second person • Explicit pricing of risks |
|
| R-020 | Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture Consequence : Bruises, cuts, falls |
9 P3×I3 | • Daily tidy-up and defined storage areas • Regular safety walks |
|
| R-021 | Handover delayed by numerous snags
Cause : Rushed finishes at the end, late inspections Consequence : Delayed payment, penalties, dissatisfaction |
9 P3×I3 | • Pre-handover by area |
• Snag clearance schedule |
| R-022 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
9 P3×I3 | • External dependency log |
• Prepared workaround |
| R-023 | Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction Consequence : Serious and irreversible respiratory diseases |
9 P3×I3 | • Tools with water suppression or on-tool extraction |
• Suitable respiratory protection |
| R-024 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-025 | Unexpected discovery in the existing building
Cause : Inaccurate old drawings, hidden structure or networks, degraded materials Consequence : Extra studies and works, site stoppage, extra costs |
8 P2×I4 | • Prior surveys and investigations |
• Dedicated allowance for existing-building risks |
| R-026 | Post-handover defects engaging the builder’s liability
Cause : Waterproofing, structural or equipment defects appearing after handover Consequence : Costly repairs, insurance claims, reputation |
8 P2×I4 | • Self-checks and quality hold points |
• Suitable warranties and liability insurance |
| R-027 | BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities Consequence : Undetected clashes, rework |
8 P2×I4 | • BIM execution plan at the start • BIM coordinator |
|
| R-028 | Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance Consequence : Unpaid invoices, lost revenue, cash strain |
8 P2×I4 | • Monitor key customers’ financial health |
• Credit insurance or payment guarantees |
| R-029 | Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed Consequence : Complaints, municipal orders, delay |
6 P2×I3 | • Advance notice and residents’ contact • Working hours and dust control |
|
| R-030 | Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks Consequence : Penalties, joint liability, site stoppage |
6 P2×I3 | • Access control and check of declarations • Limit chain subcontracting |
|
| R-031 | Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists Consequence : Low back pain, slipped discs |
6 P2×I3 | • Material hoists and delivery close to the workplace • Lighter packaging |
|
| R-032 | Late permit for use of the public road
Cause : Late application, refusal, imposed conditions Consequence : Late start, deliveries impossible |
6 P2×I3 | • Early application with signage plan |
• Alternative logistics |
| R-033 | Poorly drafted or incomplete contract
Cause : Unclear liabilities, deadlines, acceptance or penalties, no legal review Consequence : Disputes, unpaid work, excessive liability |
6 P2×I3 | • Checklist of essential clauses • Legal review of major contracts |
|
| R-034 | No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified Consequence : Avoidable accidents, non-compliance on inspection |
6 P2×I3 | • Annual review and after every change • Worker participation |
|
| R-035 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “House or apartment renovation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.