Risk register example: New building construction

Building from the ground up: earthworks, structure, lifting, many trades on site and a tight schedule.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate12
● High9
● Critical14

Assumptions: Construction / civil works · Execution / works · 60 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), excavation, trenches, earthworks, site vehicles, forklifts, construction machinery, electrical work or work near live installations, hot work (welding, cutting, grinding), noise or vibration, mainly outdoors, works during winter, subcontractors involved, several companies working at the same time, permits or authorisations required, fixed-price contract, dense urban area, neighbours nearby.

Ref.RiskScorePreventionProtection
R-001 Fall through a fragile roof or floor opening
Cause : Rooflights, fibre cement, unprotected openings
Consequence : Serious or fatal fall
20 P4×I5 • Cover and mark floor openings
• Nets or walkways on fragile roofs
R-002 Crane or aerial platform overturning
Cause : Weak ground, inadequate outriggers, high wind, overloading
Consequence : Crushing, death, major damage
20 P4×I5 • Ground assessment and outrigger pads
• Anemometer and wind stop threshold
R-003 Drowning or burial near water
Cause : Bank works, cofferdams, shafts, flooded excavations
Consequence : Drowning, burial
20 P4×I5 • Collective protection at water edges
• Life jackets and lifebuoy nearby
R-004 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
20 P4×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-005 Struck by earthmoving equipment
Cause : Excavator or loader manoeuvring, blind spot, pedestrians within reach
Consequence : Crushing, serious injuries
16 P4×I4 • Exclusion zone and eye contact
• Cameras and presence detection on machines
R-006 Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings
Consequence : Collision, load falling on third parties
16 P4×I4 • Layout study and anti-collision system
• No loads over public areas
R-007 Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area
Consequence : Pedestrian or worker struck, material damage
16 P4×I4 • Delivery plan and dedicated area
• Banksman for manoeuvres
R-008 Scaffold collapse or fall from scaffolding
Cause : Non-compliant erection, inadequate anchors, overloading, alterations by unqualified people
Consequence : Falls of people and materials
16 P4×I4 • Erection by qualified staff and handover
• Periodic inspection and after storms
R-009 Collapse of an existing floor or wall during renovation
Cause : Weakened structure, material overload, removal of load-bearing elements
Consequence : Burial, falls
16 P4×I4 • Structural survey by an engineer
• Temporary propping
R-010 Accident in a tunnel, shaft or gallery
Cause : Oxygen-depleted air, collapse, vehicle traffic, difficult evacuation
Consequence : Suffocation, burial, casualties hard to rescue
16 P4×I4 • Ventilation and continuous gas monitoring
• Underground rescue plan
R-011 Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans
Consequence : Leak, explosion, neighbourhood evacuation
16 P4×I4 • Request plans and hand-dig trial holes
• Emergency procedure for leaks
R-012 Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects
Consequence : Injury to a third party, prosecution
16 P4×I4 • Continuous fencing and protected footpath
• Fans and nets against falling objects
R-013 Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations
Consequence : Destruction of works, injuries, major delays
15 P5×I3 • Combustible waste management and storage areas
• Extinguishers and response plan
R-014 Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work
Consequence : Site stoppages, degraded quality (concrete, paint), delay
15 P5×I3 • Season-aware scheduling
• Temporary protection
R-015 Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished
Consequence : Idle time, rework, accumulated delay at the end of the works
12 P4×I3 • Weekly coordination schedule
• Handover of work areas between trades
R-016 Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction
Consequence : Serious and irreversible respiratory diseases
12 P4×I3 • Tools with water suppression or on-tool extraction
• Suitable respiratory protection
R-017 Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time
Consequence : Site blocked, delayed handover
12 P4×I3 • Requests to utilities from the design stage
• Track utilities at site meetings
R-018 Extra work not approved in writing
Cause : Verbal client requests, changes during construction
Consequence : Unpaid work, dispute at completion
12 P3×I4 • Written instruction before execution
• Variation tracking table
R-019 Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure
Consequence : Loss-making project, tension with the client
12 P3×I4 • Bid review by a second person
• Explicit pricing of risks
R-020 Handover delayed by numerous snags
Cause : Rushed finishes at the end, late inspections
Consequence : Delayed payment, penalties, dissatisfaction
12 P4×I3 • Pre-handover by area
• Snag clearance schedule
R-021 Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision
Consequence : Critical path blocked, delay
12 P4×I3 • External dependency log
• Prepared workaround
R-022 No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified
Consequence : Avoidable accidents, non-compliance on inspection
12 P4×I3 • Annual review and after every change
• Worker participation
R-023 Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance
Consequence : Unpaid invoices, lost revenue, cash strain
10 P2×I5 • Monitor key customers’ financial health
• Credit insurance or payment guarantees
R-024 Defects from concreting in cold or hot weather
Cause : Frost, rapid drying, insufficient curing
Consequence : Low strength, cracking, partial demolition
9 P3×I3 • Extreme-weather concreting procedure
• Strength tests before striking formwork
R-025 Water ingress during roofing works
Cause : Roof left open, inadequate sheeting, unexpected showers
Consequence : Interior damage, claims
9 P3×I3 • Open only what can be closed the same day
• Emergency sheeting and weather watch
R-026 Late permit for use of the public road
Cause : Late application, refusal, imposed conditions
Consequence : Late start, deliveries impossible
9 P3×I3 • Early application with signage plan
• Alternative logistics
R-027 Contaminated soil or materials discovered
Cause : Former industrial site, fill of unknown quality
Consequence : Costly disposal, delay, environmental obligations
9 P3×I3 • Prior soil study and analyses
• Unforeseen ground clause in the contract
R-028 Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather
Consequence : Nuisance to neighbours, complaints, health effects
9 P3×I3 • Damping down and covering stockpiles
• Stop dusty operations in high wind
R-029 Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions
Consequence : Rework, clashes between trades, extra costs
9 P3×I3 • Coordination and clash detection
• Drawing version control
R-030 Working in the cold
Cause : Low temperatures, wind, humidity, cold stores
Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground
9 P3×I3 • Suitable clothing and heated rooms
• Organise exposure time
R-031 Damage to neighbouring buildings
Cause : Vibrations, excavation, dewatering, underpinning
Consequence : Cracks in neighbouring properties, disputes, site stoppage
8 P2×I4 • Pre-works condition survey
• Vibration and crack monitoring
R-032 Post-handover defects engaging the builder’s liability
Cause : Waterproofing, structural or equipment defects appearing after handover
Consequence : Costly repairs, insurance claims, reputation
8 P2×I4 • Self-checks and quality hold points
• Suitable warranties and liability insurance
R-033 BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities
Consequence : Undetected clashes, rework
8 P2×I4 • BIM execution plan at the start
• BIM coordinator
R-034 Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks
Consequence : Penalties, joint liability, site stoppage
6 P2×I3 • Access control and check of declarations
• Limit chain subcontracting
R-035 Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed
Consequence : Complaints, municipal orders, delay
6 P2×I3 • Advance notice and residents’ contact
• Working hours and dust control

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “New building construction”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples