Risk register example: Office fit-out

Fitting out offices, often in an occupied building: coordination of trades, dust, noise and a fixed move-in date.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate19
● High11
● Critical5

Assumptions: Construction / civil works · Execution / works · 15 people · occupied site (staff, residents, patients nearby), electrical work or work near live installations, heavy or repetitive manual handling, noise or vibration, several companies working at the same time, tight or immovable deadline, fixed-price contract, dense urban area, neighbours nearby.

Ref.RiskScorePreventionProtection
R-001 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
16 P4×I4 • Mobile platforms instead of ladders
• Visual check before use
R-002 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
16 P4×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-003 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-004 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-005 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
15 P3×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-006 Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations
Consequence : Destruction of works, injuries, major delays
12 P4×I3 • Combustible waste management and storage areas
• Extinguishers and response plan
R-007 Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking
Consequence : Complaints, imposed working-hour restrictions, delay
12 P4×I3 • Neighbour information and dedicated contact
• Dust control and suitable hours
R-008 Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished
Consequence : Idle time, rework, accumulated delay at the end of the works
12 P4×I3 • Weekly coordination schedule
• Handover of work areas between trades
R-009 Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area
Consequence : Pedestrian or worker struck, material damage
12 P3×I4 • Delivery plan and dedicated area
• Banksman for manoeuvres
R-010 Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects
Consequence : Injury to a third party, prosecution
12 P3×I4 • Continuous fencing and protected footpath
• Fans and nets against falling objects
R-011 Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings
Consequence : Collision, load falling on third parties
12 P3×I4 • Layout study and anti-collision system
• No loads over public areas
R-012 Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures
Consequence : Chronic pain, sick leave, unfitness for work
12 P4×I3 • Handling aids
• Task rotation and handling training
R-013 Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation
Consequence : Tendinitis, carpal tunnel syndrome, sick leave
12 P4×I3 • Ergonomic analysis of repetitive tasks
• Job rotation
R-014 Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection
Consequence : Lacerations, tendon injuries
12 P4×I3 • Retractable-blade tools
• Suitable cut-resistant gloves
R-015 Theft or vandalism on site
Cause : Unfenced site, valuable equipment left overnight
Consequence : Losses, delays, damage to works
12 P3×I4 • Fencing, lighting and security
• Contractor’s all-risks insurance
R-016 Temporary works instability
Cause : Undersized props, formwork or temporary walls
Consequence : Collapse, injuries, rework
12 P3×I4 • Temporary works design check
• Check before loading
R-017 Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture
Consequence : Bruises, cuts, falls
9 P3×I3 • Daily tidy-up and defined storage areas
• Regular safety walks
R-018 Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time
Consequence : Site blocked, delayed handover
9 P3×I3 • Requests to utilities from the design stage
• Track utilities at site meetings
R-019 Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions
Consequence : Rework, clashes between trades, extra costs
9 P3×I3 • Coordination and clash detection
• Drawing version control
R-020 Extra work not approved in writing
Cause : Verbal client requests, changes during construction
Consequence : Unpaid work, dispute at completion
9 P3×I3 • Written instruction before execution
• Variation tracking table
R-021 Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure
Consequence : Loss-making project, tension with the client
9 P3×I3 • Bid review by a second person
• Explicit pricing of risks
R-022 Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements
Consequence : Complaints, enforced stoppage, fines
9 P3×I3 • Quieter equipment and acoustic screens
• Noise measurements and adapted hours
R-023 Handover delayed by numerous snags
Cause : Rushed finishes at the end, late inspections
Consequence : Delayed payment, penalties, dissatisfaction
9 P3×I3 • Pre-handover by area
• Snag clearance schedule
R-024 Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction
Consequence : Serious and irreversible respiratory diseases
9 P3×I3 • Tools with water suppression or on-tool extraction
• Suitable respiratory protection
R-025 Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades
Consequence : Rework, retentions, delayed handover
9 P3×I3 • Hold points and self-inspections
• Pre-handover inspection per trade
R-026 Rising material prices
Cause : Volatile steel, concrete, timber or energy prices
Consequence : Eroded margin, difficulty holding the price
9 P3×I3 • Price revision clause
• Early purchase of key materials
R-027 Post-handover defects engaging the builder’s liability
Cause : Waterproofing, structural or equipment defects appearing after handover
Consequence : Costly repairs, insurance claims, reputation
8 P2×I4 • Self-checks and quality hold points
• Suitable warranties and liability insurance
R-028 BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities
Consequence : Undetected clashes, rework
8 P2×I4 • BIM execution plan at the start
• BIM coordinator
R-029 Poor ground conditions
Cause : Limited or missing geotechnical survey
Consequence : Foundations to redesign, major extra cost and delay
8 P2×I4 • Geotechnical survey suited to the project
• Costed foundation alternatives
R-030 Dispute with the client
Cause : Unsigned additional work, no meeting minutes
Consequence : Blocked payments, legal proceedings
8 P2×I4 • Signed instructions before execution
• Minutes and dated photos
R-031 Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed
Consequence : Complaints, municipal orders, delay
6 P2×I3 • Advance notice and residents’ contact
• Working hours and dust control
R-032 Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists
Consequence : Low back pain, slipped discs
6 P2×I3 • Material hoists and delivery close to the workplace
• Lighter packaging
R-033 Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks
Consequence : Penalties, joint liability, site stoppage
6 P2×I3 • Access control and check of declarations
• Limit chain subcontracting
R-034 Late permit for use of the public road
Cause : Late application, refusal, imposed conditions
Consequence : Late start, deliveries impossible
6 P2×I3 • Early application with signage plan
• Alternative logistics
R-035 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Office fit-out”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free