Risk register example: Office fit-out
Fitting out offices, often in an occupied building: coordination of trades, dust, noise and a fixed move-in date.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Construction / civil works · Execution / works · 15 people · occupied site (staff, residents, patients nearby), electrical work or work near live installations, heavy or repetitive manual handling, noise or vibration, several companies working at the same time, tight or immovable deadline, fixed-price contract, dense urban area, neighbours nearby.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
16 P4×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-002 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
16 P4×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-003 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-004 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-005 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-006 | Fire on the construction site
Cause : Stored combustible materials, hot work, temporary installations Consequence : Destruction of works, injuries, major delays |
12 P4×I3 | • Combustible waste management and storage areas |
• Extinguishers and response plan |
| R-007 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
12 P4×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-008 | Poor sequencing of trades
Cause : Uncoordinated trade schedule, preparatory work not finished Consequence : Idle time, rework, accumulated delay at the end of the works |
12 P4×I3 | • Weekly coordination schedule |
• Handover of work areas between trades |
| R-009 | Accident during site deliveries
Cause : Narrow access, reversing manoeuvres, no banksman, unmarked area Consequence : Pedestrian or worker struck, material damage |
12 P3×I4 | • Delivery plan and dedicated area • Banksman for manoeuvres |
|
| R-010 | Accident involving a passer-by near the site
Cause : Inadequate fencing, diverted pavement without protection, falling objects Consequence : Injury to a third party, prosecution |
12 P3×I4 | • Continuous fencing and protected footpath • Fans and nets against falling objects |
|
| R-011 | Crane interference or loads over occupied areas
Cause : Several cranes on one site, loads over public roads or buildings Consequence : Collision, load falling on third parties |
12 P3×I4 | • Layout study and anti-collision system • No loads over public areas |
|
| R-012 | Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures Consequence : Chronic pain, sick leave, unfitness for work |
12 P4×I3 | • Handling aids • Task rotation and handling training |
|
| R-013 | Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation Consequence : Tendinitis, carpal tunnel syndrome, sick leave |
12 P4×I3 | • Ergonomic analysis of repetitive tasks • Job rotation |
|
| R-014 | Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection Consequence : Lacerations, tendon injuries |
12 P4×I3 | • Retractable-blade tools |
• Suitable cut-resistant gloves |
| R-015 | Theft or vandalism on site
Cause : Unfenced site, valuable equipment left overnight Consequence : Losses, delays, damage to works |
12 P3×I4 | • Fencing, lighting and security |
• Contractor’s all-risks insurance |
| R-016 | Temporary works instability
Cause : Undersized props, formwork or temporary walls Consequence : Collapse, injuries, rework |
12 P3×I4 | • Temporary works design check • Check before loading |
|
| R-017 | Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture Consequence : Bruises, cuts, falls |
9 P3×I3 | • Daily tidy-up and defined storage areas • Regular safety walks |
|
| R-018 | Delays from utility companies
Cause : Diversions or connections for water, gas, electricity or telecoms not planned in time Consequence : Site blocked, delayed handover |
9 P3×I3 | • Requests to utilities from the design stage |
• Track utilities at site meetings |
| R-019 | Errors or inconsistencies in construction drawings
Cause : Drawings not coordinated between disciplines, multiple versions Consequence : Rework, clashes between trades, extra costs |
9 P3×I3 | • Coordination and clash detection • Drawing version control |
|
| R-020 | Extra work not approved in writing
Cause : Verbal client requests, changes during construction Consequence : Unpaid work, dispute at completion |
9 P3×I3 | • Written instruction before execution |
• Variation tracking table |
| R-021 | Underpriced bid to win the contract
Cause : Incomplete quantities, unpriced risks, competitive pressure Consequence : Loss-making project, tension with the client |
9 P3×I3 | • Bid review by a second person • Explicit pricing of risks |
|
| R-022 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-023 | Handover delayed by numerous snags
Cause : Rushed finishes at the end, late inspections Consequence : Delayed payment, penalties, dissatisfaction |
9 P3×I3 | • Pre-handover by area |
• Snag clearance schedule |
| R-024 | Exposure to silica dust
Cause : Cutting, grinding or demolishing concrete, stone or brick without extraction Consequence : Serious and irreversible respiratory diseases |
9 P3×I3 | • Tools with water suppression or on-tool extraction |
• Suitable respiratory protection |
| R-025 | Workmanship defects and snags at handover
Cause : Insufficient quality checks, poorly managed interfaces between trades Consequence : Rework, retentions, delayed handover |
9 P3×I3 | • Hold points and self-inspections |
• Pre-handover inspection per trade |
| R-026 | Rising material prices
Cause : Volatile steel, concrete, timber or energy prices Consequence : Eroded margin, difficulty holding the price |
9 P3×I3 | • Price revision clause |
• Early purchase of key materials |
| R-027 | Post-handover defects engaging the builder’s liability
Cause : Waterproofing, structural or equipment defects appearing after handover Consequence : Costly repairs, insurance claims, reputation |
8 P2×I4 | • Self-checks and quality hold points |
• Suitable warranties and liability insurance |
| R-028 | BIM model not shared or inconsistent
Cause : Incompatible formats, different levels of detail, unclear responsibilities Consequence : Undetected clashes, rework |
8 P2×I4 | • BIM execution plan at the start • BIM coordinator |
|
| R-029 | Poor ground conditions
Cause : Limited or missing geotechnical survey Consequence : Foundations to redesign, major extra cost and delay |
8 P2×I4 | • Geotechnical survey suited to the project |
• Costed foundation alternatives |
| R-030 | Dispute with the client
Cause : Unsigned additional work, no meeting minutes Consequence : Blocked payments, legal proceedings |
8 P2×I4 | • Signed instructions before execution |
• Minutes and dated photos |
| R-031 | Disruption for residents and shops
Cause : Blocked access, noise, dust, parking removed Consequence : Complaints, municipal orders, delay |
6 P2×I3 | • Advance notice and residents’ contact • Working hours and dust control |
|
| R-032 | Handling heavy blocks, boards and bags
Cause : Heavy materials carried by hand, floors without hoists Consequence : Low back pain, slipped discs |
6 P2×I3 | • Material hoists and delivery close to the workplace • Lighter packaging |
|
| R-033 | Undeclared work or irregular posting of workers on site
Cause : Chain subcontracting, no identity checks Consequence : Penalties, joint liability, site stoppage |
6 P2×I3 | • Access control and check of declarations • Limit chain subcontracting |
|
| R-034 | Late permit for use of the public road
Cause : Late application, refusal, imposed conditions Consequence : Late start, deliveries impossible |
6 P2×I3 | • Early application with signage plan |
• Alternative logistics |
| R-035 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.