Risk register example: Solar panel installation
Rooftop or ground-mounted PV: work at height, roof strength, DC electricity and grid connection.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Energy / utilities · Execution / works · 10 people · work at height (roofs, scaffolding, platforms), electrical work or work near live installations, lifting operations (cranes, hoists), mainly outdoors, works during summer or heatwaves, critical item from a single supplier, suppliers outside europe or long lead times, permits or authorisations required, subcontractors involved.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground Consequence : Crushing, fatality, major damage |
20 P4×I5 | • Lifting plan for critical lifts • Qualified operators and slingers, inspected gear |
• No one under the load |
| R-002 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
20 P4×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-003 | Heat stroke
Cause : Physical work in full sun, heatwave, insufficient hydration Consequence : Serious illness, hospitalisation, death |
20 P4×I5 | • Shifted hours and shaded breaks |
• Cool water and buddy checks |
| R-004 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
16 P4×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-005 | Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below Consequence : Serious injury to people below, material damage |
16 P4×I4 | • Toe boards, nets and tethered tools |
• Marked exclusion zone below |
| R-006 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
16 P4×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-007 | Accident during wind turbine work
Cause : Work at height and in confined spaces, difficult evacuation, weather Consequence : Fall, casualty hard to rescue |
15 P3×I5 | • Specific training and working in pairs |
• Rescue plan and evacuation equipment |
| R-008 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-009 | Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed Consequence : Severe burns, death |
15 P3×I5 | • Switching procedures and authorised person |
• Arc flash protective equipment |
| R-010 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-011 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
15 P3×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-012 | DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight Consequence : Burns, fire on the installation |
12 P3×I4 | • Compatible connectors and checked crimping • Workers trained for DC |
|
| R-013 | Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling Consequence : Fire, explosion, toxic gases |
12 P3×I4 | • Battery management system and monitoring |
• Safety distances and fire brigade plan |
| R-014 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
12 P3×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-015 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-016 | Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier Consequence : Production or site stoppage, delays, penalties |
12 P3×I4 | • Map tier-1 and tier-2 suppliers |
• Safety stock for critical components |
| R-017 | Supply disruption of a critical item
Cause : Single supplier, no qualified alternative Consequence : Work or production stopped while waiting for delivery |
12 P3×I4 | • Qualify a second supplier |
• Safety stock |
| R-018 | Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work Consequence : Site stoppages, degraded quality (concrete, paint), delay |
12 P4×I3 | • Season-aware scheduling |
• Temporary protection |
| R-019 | Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts Consequence : Damage to installations, business interruption, repair costs |
12 P3×I4 | • Climate vulnerability assessment of the site |
• Weather alert and safety plan |
| R-020 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-021 | Appeal against a renewable energy project
Cause : Local opposition, contested landscape or biodiversity impact Consequence : Project suspended or cancelled, years of delay |
9 P3×I3 | • Early consultation and robust impact studies |
• Schedule including appeal periods |
| R-022 | Local grid congestion
Cause : Insufficient injection or offtake capacity, long reinforcement times Consequence : Project capped in power or postponed |
9 P3×I3 | • Early grid connection study |
• Flexibility solutions |
| R-023 | Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers Consequence : Extra costs, customs delays, closed markets |
9 P3×I3 | • Customs watch and product origin |
• Alternative suppliers in other regions |
| R-024 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
9 P3×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-025 | Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs Consequence : Longer payback, difficulty repaying loans |
9 P3×I3 | • Profitability study with prudent scenarios |
• Production monitoring and maintenance |
| R-026 | Energy price volatility
Cause : Unstable markets, indexed contracts Consequence : Uncertain profitability, budget variances |
9 P3×I3 | • Price scenarios in the business plan |
• Hedging with fixed-price contracts |
| R-027 | Structure or roof unsuitable for the installation
Cause : Roof structure strength not checked, old or fragile roof covering Consequence : Unexpected strengthening, leaks, risk of collapse |
9 P3×I3 | • Prior structural study |
• Protect fragile areas during works |
| R-028 | Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals Consequence : Delayed start, idle teams, project to be redesigned |
9 P3×I3 | • Permit back-schedule • Pre-application meeting with authorities |
|
| R-029 | Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion Consequence : Studies and works to redo, extra costs, delay |
9 P3×I3 | • Project-specific regulatory watch |
• Change-in-law clause |
| R-030 | Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather Consequence : Nuisance to neighbours, complaints, health effects |
9 P3×I3 | • Damping down and covering stockpiles |
• Stop dusty operations in high wind |
| R-031 | Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce Consequence : Accidents in the first weeks |
9 P3×I3 | • Systematic safety induction • Buddy system in the first weeks |
|
| R-032 | Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in Consequence : Slow diagnosis, poor decisions, repeated interventions |
9 P3×I3 | • Systematic work order close-out |
• Update drawings after changes |
| R-033 | Delayed grid connection
Cause : Grid operator lead times, insufficient capacity Consequence : Commissioning postponed, lost revenue |
8 P2×I4 | • Early connection request |
• Schedule aligned with connection date |
| R-034 | Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection Consequence : Sunburn, long-term skin cancer |
6 P2×I3 | • Schedule work at less exposed times |
• Covering clothing and sunscreen |
| R-035 | Shortage of critical raw materials or components
Cause : Geopolitical tension, concentrated production, global demand Consequence : Delays, price rises, redesign |
6 P2×I3 | • Identify at-risk components |
• Design allowing alternatives |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Solar panel installation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.