Risqure
Risqure › Risk register examples › Solar panel installation

Risk register example: Solar panel installation

Rooftop or ground-mounted PV: work at height, roof strength, DC electricity and grid connection.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate15
● High9
● Critical11

Assumptions: Energy / utilities · Execution / works · 10 people · work at height (roofs, scaffolding, platforms), electrical work or work near live installations, lifting operations (cranes, hoists), mainly outdoors, works during summer or heatwaves, critical item from a single supplier, suppliers outside europe or long lead times, permits or authorisations required, subcontractors involved.

Ref.RiskScorePreventionProtection
R-001 Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground
Consequence : Crushing, fatality, major damage
20 P4×I5 • Lifting plan for critical lifts
• Qualified operators and slingers, inspected gear
• No one under the load
R-002 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
20 P4×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-003 Heat stroke
Cause : Physical work in full sun, heatwave, insufficient hydration
Consequence : Serious illness, hospitalisation, death
20 P4×I5 • Shifted hours and shaded breaks
• Cool water and buddy checks
R-004 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
16 P4×I4 • Mobile platforms instead of ladders
• Visual check before use
R-005 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
16 P4×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-006 Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan
Consequence : Serious accident, shared liability, site stoppage
16 P4×I4 • Prevention plan and joint inspection
• Daily coordination of work
R-007 Accident during wind turbine work
Cause : Work at height and in confined spaces, difficult evacuation, weather
Consequence : Fall, casualty hard to rescue
15 P3×I5 • Specific training and working in pairs
• Rescue plan and evacuation equipment
R-008 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-009 Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed
Consequence : Severe burns, death
15 P3×I5 • Switching procedures and authorised person
• Arc flash protective equipment
R-010 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-011 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
15 P3×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-012 DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight
Consequence : Burns, fire on the installation
12 P3×I4 • Compatible connectors and checked crimping
• Workers trained for DC
R-013 Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling
Consequence : Fire, explosion, toxic gases
12 P3×I4 • Battery management system and monitoring
• Safety distances and fire brigade plan
R-014 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
12 P3×I4 • Isolate all energy sources
• Lockout sheets per machine
R-015 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-016 Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier
Consequence : Production or site stoppage, delays, penalties
12 P3×I4 • Map tier-1 and tier-2 suppliers
• Safety stock for critical components
R-017 Supply disruption of a critical item
Cause : Single supplier, no qualified alternative
Consequence : Work or production stopped while waiting for delivery
12 P3×I4 • Qualify a second supplier
• Safety stock
R-018 Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work
Consequence : Site stoppages, degraded quality (concrete, paint), delay
12 P4×I3 • Season-aware scheduling
• Temporary protection
R-019 Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts
Consequence : Damage to installations, business interruption, repair costs
12 P3×I4 • Climate vulnerability assessment of the site
• Weather alert and safety plan
R-020 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-021 Appeal against a renewable energy project
Cause : Local opposition, contested landscape or biodiversity impact
Consequence : Project suspended or cancelled, years of delay
9 P3×I3 • Early consultation and robust impact studies
• Schedule including appeal periods
R-022 Local grid congestion
Cause : Insufficient injection or offtake capacity, long reinforcement times
Consequence : Project capped in power or postponed
9 P3×I3 • Early grid connection study
• Flexibility solutions
R-023 Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers
Consequence : Extra costs, customs delays, closed markets
9 P3×I3 • Customs watch and product origin
• Alternative suppliers in other regions
R-024 Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain
Consequence : Work stoppages, damage, design to revise
9 P3×I3 • Include climate scenarios in design
• Plan to adapt hours and works
R-025 Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs
Consequence : Longer payback, difficulty repaying loans
9 P3×I3 • Profitability study with prudent scenarios
• Production monitoring and maintenance
R-026 Energy price volatility
Cause : Unstable markets, indexed contracts
Consequence : Uncertain profitability, budget variances
9 P3×I3 • Price scenarios in the business plan
• Hedging with fixed-price contracts
R-027 Structure or roof unsuitable for the installation
Cause : Roof structure strength not checked, old or fragile roof covering
Consequence : Unexpected strengthening, leaks, risk of collapse
9 P3×I3 • Prior structural study
• Protect fragile areas during works
R-028 Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals
Consequence : Delayed start, idle teams, project to be redesigned
9 P3×I3 • Permit back-schedule
• Pre-application meeting with authorities
R-029 Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion
Consequence : Studies and works to redo, extra costs, delay
9 P3×I3 • Project-specific regulatory watch
• Change-in-law clause
R-030 Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather
Consequence : Nuisance to neighbours, complaints, health effects
9 P3×I3 • Damping down and covering stockpiles
• Stop dusty operations in high wind
R-031 Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce
Consequence : Accidents in the first weeks
9 P3×I3 • Systematic safety induction
• Buddy system in the first weeks
R-032 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-033 Delayed grid connection
Cause : Grid operator lead times, insufficient capacity
Consequence : Commissioning postponed, lost revenue
8 P2×I4 • Early connection request
• Schedule aligned with connection date
R-034 Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection
Consequence : Sunburn, long-term skin cancer
6 P2×I3 • Schedule work at less exposed times
• Covering clothing and sunscreen
R-035 Shortage of critical raw materials or components
Cause : Geopolitical tension, concentrated production, global demand
Consequence : Delays, price rises, redesign
6 P2×I3 • Identify at-risk components
• Design allowing alternatives

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Solar panel installation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples