Risk register example: Power grid works
Works on medium or high-voltage networks: switching, arc flash, excavation and public roads.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Energy / utilities · Execution / works · 20 people · electrical work or work near live installations, site in operation (co-activity with production), excavation, trenches, earthworks, work on or near public roads, work at height (roofs, scaffolding, platforms), night or shift work, mainly outdoors, works during winter.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
25 P5×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-002 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
20 P4×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-003 | Worker struck by road traffic
Cause : Insufficient signage, driver speed, poor visibility Consequence : Serious injury or death, road user accident |
20 P4×I5 | • Compliant protected temporary signage • Traffic order and high-visibility clothing |
|
| R-004 | Heat stroke
Cause : Physical work in full sun, heatwave, insufficient hydration Consequence : Serious illness, hospitalisation, death |
20 P4×I5 | • Shifted hours and shaded breaks |
• Cool water and buddy checks |
| R-005 | Interference between work and ongoing operations
Cause : Unexpected start-up of installations, production flows not stopped Consequence : Accident, production stoppage, damage |
16 P4×I4 | • Work permit issued by the operator |
• Direct link with the control room |
| R-006 | Accident during wind turbine work
Cause : Work at height and in confined spaces, difficult evacuation, weather Consequence : Fall, casualty hard to rescue |
15 P3×I5 | • Specific training and working in pairs |
• Rescue plan and evacuation equipment |
| R-007 | Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure Consequence : Equipment energised or moving with a worker exposed |
15 P3×I5 | • Lockout procedure with personal padlocks • Check before restart |
|
| R-008 | Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work Consequence : Site stoppages, degraded quality (concrete, paint), delay |
15 P5×I3 | • Season-aware scheduling |
• Temporary protection |
| R-009 | Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed Consequence : Severe burns, death |
15 P3×I5 | • Switching procedures and authorised person |
• Arc flash protective equipment |
| R-010 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-011 | Trench or excavation collapse
Cause : No shoring, slopes too steep, waterlogged ground Consequence : Burial, fatality |
15 P3×I5 | • Systematic shoring or battering • Daily excavation inspection |
|
| R-012 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
12 P3×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-013 | DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight Consequence : Burns, fire on the installation |
12 P3×I4 | • Compatible connectors and checked crimping • Workers trained for DC |
|
| R-014 | Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling Consequence : Fire, explosion, toxic gases |
12 P3×I4 | • Battery management system and monitoring |
• Safety distances and fire brigade plan |
| R-015 | Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans Consequence : Leak, explosion, neighbourhood evacuation |
12 P3×I4 | • Request plans and hand-dig trial holes |
• Emergency procedure for leaks |
| R-016 | Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs Consequence : Longer payback, difficulty repaying loans |
12 P3×I4 | • Profitability study with prudent scenarios |
• Production monitoring and maintenance |
| R-017 | Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks Consequence : Remediation, use restrictions, dispute with the seller |
12 P3×I4 | • Historical and soil study before acquisition |
• Environmental liability warranties |
| R-018 | Energy price volatility
Cause : Unstable markets, indexed contracts Consequence : Uncertain profitability, budget variances |
12 P3×I4 | • Price scenarios in the business plan |
• Hedging with fixed-price contracts |
| R-019 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-020 | Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts Consequence : Damage to installations, business interruption, repair costs |
12 P3×I4 | • Climate vulnerability assessment of the site |
• Weather alert and safety plan |
| R-021 | Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather Consequence : Nuisance to neighbours, complaints, health effects |
9 P3×I3 | • Damping down and covering stockpiles |
• Stop dusty operations in high wind |
| R-022 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
9 P3×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-023 | Structure or roof unsuitable for the installation
Cause : Roof structure strength not checked, old or fragile roof covering Consequence : Unexpected strengthening, leaks, risk of collapse |
9 P3×I3 | • Prior structural study |
• Protect fragile areas during works |
| R-024 | Fatigue and reduced alertness from night work
Cause : Shifted hours, insufficient sleep, poor lighting Consequence : Mistakes, accidents, health problems |
9 P3×I3 | • Shift and break planning • Adequate lighting everywhere |
|
| R-025 | Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in Consequence : Slow diagnosis, poor decisions, repeated interventions |
9 P3×I3 | • Systematic work order close-out |
• Update drawings after changes |
| R-026 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-027 | Delayed grid connection
Cause : Grid operator lead times, insufficient capacity Consequence : Commissioning postponed, lost revenue |
8 P2×I4 | • Early connection request |
• Schedule aligned with connection date |
| R-028 | Damage to underground utilities
Cause : Incomplete utility maps, digging without prior detection Consequence : Gas, power or water outage, explosion, injuries |
8 P2×I4 | • Utility maps and detection before digging |
• Hand digging near utilities |
| R-029 | Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability Consequence : Fines, producer liability, damaged image |
8 P4×I2 | • Sorting at source and approved contractors |
• Waste register and transfer notes |
| R-030 | Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords Consequence : Physical or digital intrusion, sabotage, espionage |
8 P2×I4 | • Change default passwords and keep an inventory • Separate network for connected devices |
|
| R-031 | Working in the cold
Cause : Low temperatures, wind, humidity, cold stores Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground |
6 P2×I3 | • Suitable clothing and heated rooms • Organise exposure time |
|
| R-032 | Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection Consequence : Sunburn, long-term skin cancer |
6 P2×I3 | • Schedule work at less exposed times |
• Covering clothing and sunscreen |
| R-033 | Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted Consequence : Harm to mother or child, non-compliance |
6 P2×I3 | • Specific assessment once pregnancy is announced • List of at-risk jobs prepared in advance |
|
| R-034 | Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction Consequence : Respiratory diseases, irritation |
6 P2×I3 | • Local extraction and wet methods |
• Suitable respiratory protection |
| R-035 | Poor indoor air quality
Cause : Insufficient ventilation, emissive products, dense occupancy Consequence : Discomfort, headaches, absenteeism, spread of infections |
6 P2×I3 | • CO2 sensors and ventilation maintenance • Low-emission materials and products |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.