Risk register example: EV charging stations
Deploying charging points: grid capacity, trenching, public access, payment and software.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Energy / utilities · Execution / works · 6 people · electrical work or work near live installations, excavation, trenches, earthworks, site open to the public, work on or near public roads, online payments, cloud or saas services, permits or authorisations required, several sites.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Worker struck by road traffic
Cause : Insufficient signage, driver speed, poor visibility Consequence : Serious injury or death, road user accident |
20 P4×I5 | • Compliant protected temporary signage • Traffic order and high-visibility clothing |
|
| R-002 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
16 P4×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-003 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-004 | Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed Consequence : Severe burns, death |
15 P3×I5 | • Switching procedures and authorised person |
• Arc flash protective equipment |
| R-005 | Trench or excavation collapse
Cause : No shoring, slopes too steep, waterlogged ground Consequence : Burial, fatality |
15 P3×I5 | • Systematic shoring or battering • Daily excavation inspection |
|
| R-006 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-007 | Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration Consequence : Mandatory notification, loss of trust, fines, claims |
15 P3×I5 | • Least-privilege access management |
• Breach notification procedure |
| R-008 | DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight Consequence : Burns, fire on the installation |
12 P3×I4 | • Compatible connectors and checked crimping • Workers trained for DC |
|
| R-009 | Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling Consequence : Fire, explosion, toxic gases |
12 P3×I4 | • Battery management system and monitoring |
• Safety distances and fire brigade plan |
| R-010 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
12 P3×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-011 | Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans Consequence : Leak, explosion, neighbourhood evacuation |
12 P3×I4 | • Request plans and hand-dig trial holes |
• Emergency procedure for leaks |
| R-012 | Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff Consequence : Panic, injuries during evacuation |
12 P3×I4 | • Evacuation plan and drill |
• Safety PA system and assembly point |
| R-013 | Malicious act or intrusion
Cause : Insufficient access control, unchecked items Consequence : Theft, vandalism, assault, serious threat |
12 P3×I4 | • Access control and searches if needed |
• Liaison with the police |
| R-014 | Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads Consequence : Sprains, fractures |
12 P3×I4 | • Anti-slip nosings and handrails • Hoists or trolleys for loads |
|
| R-015 | Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals Consequence : Delayed start, idle teams, project to be redesigned |
12 P4×I3 | • Permit back-schedule • Pre-application meeting with authorities |
|
| R-016 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-017 | Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory Consequence : Intrusion, data theft, service outage |
12 P3×I4 | • Inventory of exposed assets and priority patching • Regular vulnerability scanning |
|
| R-018 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-019 | Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation Consequence : Systems down, data lost, ransom demanded |
10 P2×I5 | • Patching and endpoint protection |
• Tested offline backups |
| R-020 | Appeal against a renewable energy project
Cause : Local opposition, contested landscape or biodiversity impact Consequence : Project suspended or cancelled, years of delay |
9 P3×I3 | • Early consultation and robust impact studies |
• Schedule including appeal periods |
| R-021 | Local grid congestion
Cause : Insufficient injection or offtake capacity, long reinforcement times Consequence : Project capped in power or postponed |
9 P3×I3 | • Early grid connection study |
• Flexibility solutions |
| R-022 | Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs Consequence : Longer payback, difficulty repaying loans |
9 P3×I3 | • Profitability study with prudent scenarios |
• Production monitoring and maintenance |
| R-023 | Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather Consequence : Nuisance to neighbours, complaints, health effects |
9 P3×I3 | • Damping down and covering stockpiles |
• Stop dusty operations in high wind |
| R-024 | Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations Consequence : Stress, verbal aggression, staff burnout |
9 P3×I3 | • Conflict-management training |
• Post-incident support and reporting |
| R-025 | Energy price volatility
Cause : Unstable markets, indexed contracts Consequence : Uncertain profitability, budget variances |
9 P3×I3 | • Price scenarios in the business plan |
• Hedging with fixed-price contracts |
| R-026 | Structure or roof unsuitable for the installation
Cause : Roof structure strength not checked, old or fragile roof covering Consequence : Unexpected strengthening, leaks, risk of collapse |
9 P3×I3 | • Prior structural study |
• Protect fragile areas during works |
| R-027 | Internal fraud or embezzlement
Cause : Insufficient segregation of duties, rare accounting checks, shared bank access Consequence : Financial losses, misstated accounts, dispute and proceedings |
8 P2×I4 | • Segregation of duties for payments |
• Bank reconciliations and surprise checks |
| R-028 | Delayed grid connection
Cause : Grid operator lead times, insufficient capacity Consequence : Commissioning postponed, lost revenue |
8 P2×I4 | • Early connection request |
• Schedule aligned with connection date |
| R-029 | Damage to underground utilities
Cause : Incomplete utility maps, digging without prior detection Consequence : Gas, power or water outage, explosion, injuries |
8 P2×I4 | • Utility maps and detection before digging |
• Hand digging near utilities |
| R-030 | Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability Consequence : Fines, producer liability, damaged image |
8 P4×I2 | • Sorting at source and approved contractors |
• Waste register and transfer notes |
| R-031 | Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response Consequence : Loss of trust, lost customers, pressure from authorities |
8 P2×I4 | • Crisis communication procedure • Quick-reaction sheet and press contacts |
|
| R-032 | Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction Consequence : Respiratory diseases, irritation |
6 P2×I3 | • Local extraction and wet methods |
• Suitable respiratory protection |
| R-033 | Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available Consequence : Lost contracts, costlier financing, greenwashing accusations |
6 P2×I3 | • Collect key sustainability indicators • Verifiable environmental claims |
|
| R-034 | Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media Consequence : Loss of trust, lower activity, media crisis |
6 P2×I3 | • Monitor online mentions • Ready messages and spokesperson |
|
| R-035 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.