Risk register example: EV charging stations

Deploying charging points: grid capacity, trenching, public access, payment and software.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate16
● High12
● Critical7

Assumptions: Energy / utilities · Execution / works · 6 people · electrical work or work near live installations, excavation, trenches, earthworks, site open to the public, work on or near public roads, online payments, cloud or saas services, permits or authorisations required, several sites.

Ref.RiskScorePreventionProtection
R-001 Worker struck by road traffic
Cause : Insufficient signage, driver speed, poor visibility
Consequence : Serious injury or death, road user accident
20 P4×I5 • Compliant protected temporary signage
• Traffic order and high-visibility clothing
R-002 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
16 P4×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-003 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-004 Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed
Consequence : Severe burns, death
15 P3×I5 • Switching procedures and authorised person
• Arc flash protective equipment
R-005 Trench or excavation collapse
Cause : No shoring, slopes too steep, waterlogged ground
Consequence : Burial, fatality
15 P3×I5 • Systematic shoring or battering
• Daily excavation inspection
R-006 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
15 P3×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-007 Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration
Consequence : Mandatory notification, loss of trust, fines, claims
15 P3×I5 • Least-privilege access management
• Breach notification procedure
R-008 DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight
Consequence : Burns, fire on the installation
12 P3×I4 • Compatible connectors and checked crimping
• Workers trained for DC
R-009 Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling
Consequence : Fire, explosion, toxic gases
12 P3×I4 • Battery management system and monitoring
• Safety distances and fire brigade plan
R-010 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
12 P3×I4 • Isolate all energy sources
• Lockout sheets per machine
R-011 Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans
Consequence : Leak, explosion, neighbourhood evacuation
12 P3×I4 • Request plans and hand-dig trial holes
• Emergency procedure for leaks
R-012 Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff
Consequence : Panic, injuries during evacuation
12 P3×I4 • Evacuation plan and drill
• Safety PA system and assembly point
R-013 Malicious act or intrusion
Cause : Insufficient access control, unchecked items
Consequence : Theft, vandalism, assault, serious threat
12 P3×I4 • Access control and searches if needed
• Liaison with the police
R-014 Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads
Consequence : Sprains, fractures
12 P3×I4 • Anti-slip nosings and handrails
• Hoists or trolleys for loads
R-015 Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals
Consequence : Delayed start, idle teams, project to be redesigned
12 P4×I3 • Permit back-schedule
• Pre-application meeting with authorities
R-016 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-017 Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory
Consequence : Intrusion, data theft, service outage
12 P3×I4 • Inventory of exposed assets and priority patching
• Regular vulnerability scanning
R-018 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-019 Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation
Consequence : Systems down, data lost, ransom demanded
10 P2×I5 • Patching and endpoint protection
• Tested offline backups
R-020 Appeal against a renewable energy project
Cause : Local opposition, contested landscape or biodiversity impact
Consequence : Project suspended or cancelled, years of delay
9 P3×I3 • Early consultation and robust impact studies
• Schedule including appeal periods
R-021 Local grid congestion
Cause : Insufficient injection or offtake capacity, long reinforcement times
Consequence : Project capped in power or postponed
9 P3×I3 • Early grid connection study
• Flexibility solutions
R-022 Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs
Consequence : Longer payback, difficulty repaying loans
9 P3×I3 • Profitability study with prudent scenarios
• Production monitoring and maintenance
R-023 Dust emissions beyond the site
Cause : Demolition, earthworks, storage of fine materials in dry, windy weather
Consequence : Nuisance to neighbours, complaints, health effects
9 P3×I3 • Damping down and covering stockpiles
• Stop dusty operations in high wind
R-024 Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations
Consequence : Stress, verbal aggression, staff burnout
9 P3×I3 • Conflict-management training
• Post-incident support and reporting
R-025 Energy price volatility
Cause : Unstable markets, indexed contracts
Consequence : Uncertain profitability, budget variances
9 P3×I3 • Price scenarios in the business plan
• Hedging with fixed-price contracts
R-026 Structure or roof unsuitable for the installation
Cause : Roof structure strength not checked, old or fragile roof covering
Consequence : Unexpected strengthening, leaks, risk of collapse
9 P3×I3 • Prior structural study
• Protect fragile areas during works
R-027 Internal fraud or embezzlement
Cause : Insufficient segregation of duties, rare accounting checks, shared bank access
Consequence : Financial losses, misstated accounts, dispute and proceedings
8 P2×I4 • Segregation of duties for payments
• Bank reconciliations and surprise checks
R-028 Delayed grid connection
Cause : Grid operator lead times, insufficient capacity
Consequence : Commissioning postponed, lost revenue
8 P2×I4 • Early connection request
• Schedule aligned with connection date
R-029 Damage to underground utilities
Cause : Incomplete utility maps, digging without prior detection
Consequence : Gas, power or water outage, explosion, injuries
8 P2×I4 • Utility maps and detection before digging
• Hand digging near utilities
R-030 Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability
Consequence : Fines, producer liability, damaged image
8 P4×I2 • Sorting at source and approved contractors
• Waste register and transfer notes
R-031 Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response
Consequence : Loss of trust, lost customers, pressure from authorities
8 P2×I4 • Crisis communication procedure
• Quick-reaction sheet and press contacts
R-032 Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction
Consequence : Respiratory diseases, irritation
6 P2×I3 • Local extraction and wet methods
• Suitable respiratory protection
R-033 Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available
Consequence : Lost contracts, costlier financing, greenwashing accusations
6 P2×I3 • Collect key sustainability indicators
• Verifiable environmental claims
R-034 Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media
Consequence : Loss of trust, lower activity, media crisis
6 P2×I3 • Monitor online mentions
• Ready messages and spokesperson
R-035 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “EV charging stations”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free