Risk register example: Energy renovation and heat pumps
Insulation, heat pumps and controls: performance not achieved, refrigerants, grants and occupied buildings.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Energy / utilities · Execution / works · 5 people · electrical work or work near live installations, pressure systems, gas, steam, work at height (roofs, scaffolding, platforms), occupied site (staff, residents, patients nearby), new technology or method, critical item from a single supplier.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
20 P4×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-002 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
16 P4×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-003 | Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below Consequence : Serious injury to people below, material damage |
16 P4×I4 | • Toe boards, nets and tethered tools |
• Marked exclusion zone below |
| R-004 | Accident during wind turbine work
Cause : Work at height and in confined spaces, difficult evacuation, weather Consequence : Fall, casualty hard to rescue |
15 P3×I5 | • Specific training and working in pairs |
• Rescue plan and evacuation equipment |
| R-005 | Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure Consequence : Equipment energised or moving with a worker exposed |
15 P3×I5 | • Lockout procedure with personal padlocks • Check before restart |
|
| R-006 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-007 | Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed Consequence : Severe burns, death |
15 P3×I5 | • Switching procedures and authorised person |
• Arc flash protective equipment |
| R-008 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-009 | DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight Consequence : Burns, fire on the installation |
12 P3×I4 | • Compatible connectors and checked crimping • Workers trained for DC |
|
| R-010 | Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling Consequence : Fire, explosion, toxic gases |
12 P3×I4 | • Battery management system and monitoring |
• Safety distances and fire brigade plan |
| R-011 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
12 P3×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-012 | Damage to a gas pipeline
Cause : Work nearby without precise location, inaccurate plans Consequence : Leak, explosion, neighbourhood evacuation |
12 P3×I4 | • Request plans and hand-dig trial holes |
• Emergency procedure for leaks |
| R-013 | Burn from hot fluid or corrosive product
Cause : Opening a pressurised or hot circuit, splash, no PPE Consequence : Serious burns, eye injury |
12 P3×I4 | • Drain, cool and depressurise before opening |
• Face shield, gloves and safety shower |
| R-014 | Supply disruption of a critical item
Cause : Single supplier, no qualified alternative Consequence : Work or production stopped while waiting for delivery |
12 P3×I4 | • Qualify a second supplier |
• Safety stock |
| R-015 | Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier Consequence : Production or site stoppage, delays, penalties |
12 P3×I4 | • Map tier-1 and tier-2 suppliers |
• Safety stock for critical components |
| R-016 | Underperforming heat pump or heating installation
Cause : Wrong sizing, incorrect settings, incompatible emitters Consequence : Poor comfort, higher consumption than expected |
9 P3×I3 | • Heat-loss study and sizing |
• Commissioning and first-season monitoring |
| R-017 | Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs Consequence : Longer payback, difficulty repaying loans |
9 P3×I3 | • Profitability study with prudent scenarios |
• Production monitoring and maintenance |
| R-018 | Energy price volatility
Cause : Unstable markets, indexed contracts Consequence : Uncertain profitability, budget variances |
9 P3×I3 | • Price scenarios in the business plan |
• Hedging with fixed-price contracts |
| R-019 | Structure or roof unsuitable for the installation
Cause : Roof structure strength not checked, old or fragile roof covering Consequence : Unexpected strengthening, leaks, risk of collapse |
9 P3×I3 | • Prior structural study |
• Protect fragile areas during works |
| R-020 | Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers Consequence : Extra costs, customs delays, closed markets |
9 P3×I3 | • Customs watch and product origin |
• Alternative suppliers in other regions |
| R-021 | Poor command of a new technology or method
Cause : Lack of experience, limited field feedback Consequence : Defects, rework, unplanned learning time |
9 P3×I3 | • Pilot test or prototype • Expert support |
|
| R-022 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
9 P3×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-023 | Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in Consequence : Slow diagnosis, poor decisions, repeated interventions |
9 P3×I3 | • Systematic work order close-out |
• Update drawings after changes |
| R-024 | Uncontrolled use of generative AI tools
Cause : Staff pasting confidential or personal data into public tools Consequence : Information leak, GDPR non-compliance, loss of trade secrets |
9 P3×I3 | • AI acceptable-use policy • Enterprise AI tool with contractual commitments |
|
| R-025 | Unchecked error produced by an AI system
Cause : Inaccurate output presented as reliable, no review, data bias Consequence : Wrong decision, customer harm, liability |
9 P3×I3 | • Human review of content and decisions • Testing and quality metrics before deployment |
|
| R-026 | Lack of in-house digital skills
Cause : Reliance on one person or a provider, insufficient training Consequence : Stalled projects, poor use of tools, security risks |
9 P3×I3 | • Targeted training plan |
• Documentation and support contract |
| R-027 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-028 | Operating without an up-to-date environmental permit
Cause : Undeclared change of activity, operating conditions not met Consequence : Formal notice, fine, suspension of activity |
8 P2×I4 | • Register of permit obligations • Regulatory check before any modification |
|
| R-029 | Delayed grid connection
Cause : Grid operator lead times, insufficient capacity Consequence : Commissioning postponed, lost revenue |
8 P2×I4 | • Early connection request |
• Schedule aligned with connection date |
| R-030 | Non-compliance with the EU AI Act
Cause : High-risk AI system not identified, insufficient transparency, missing documentation Consequence : Fines, system withdrawn, reputational damage |
8 P2×I4 | • Inventory and classification of AI uses • User information and technical documentation |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Energy renovation and heat pumps”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.