Risk register example: Battery energy storage
Installing a battery system: thermal runaway and fire, electrical hazards, grid rules and new technology.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Energy / utilities · Planning / design · 12 people · electrical work or work near live installations, hazardous chemicals, new technology or method, suppliers outside europe or long lead times, permits or authorisations required, industrial control systems (automation, scada), remote or hard-to-access site.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Lower profitability than forecast
Cause : Overestimated output, changes to feed-in prices or support schemes, underestimated operating costs Consequence : Longer payback, difficulty repaying loans |
12 P3×I4 | • Profitability study with prudent scenarios |
• Production monitoring and maintenance |
| R-002 | Exposure to hazardous chemicals
Cause : Safety data sheets unknown, unsuitable ventilation and PPE Consequence : Poisoning, burns, occupational disease |
12 P3×I4 | • Substitute with a less hazardous product • Inventory, safety data sheets and training |
• Eyewash and emergency kit |
| R-003 | Energy price volatility
Cause : Unstable markets, indexed contracts Consequence : Uncertain profitability, budget variances |
12 P3×I4 | • Price scenarios in the business plan |
• Hedging with fixed-price contracts |
| R-004 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-005 | Adverse exchange rate movements
Cause : Purchases or sales in foreign currency, long delays between order and payment Consequence : Reduced margin, unpredictable cost price |
12 P3×I4 | • Invoice in euros where possible |
• Currency hedging for large amounts |
| R-006 | Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier Consequence : Production or site stoppage, delays, penalties |
12 P3×I4 | • Map tier-1 and tier-2 suppliers |
• Safety stock for critical components |
| R-007 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
10 P2×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-008 | Arc flash during high-voltage switching
Cause : Unsuitable equipment, procedure not followed Consequence : Severe burns, death |
10 P2×I5 | • Switching procedures and authorised person |
• Arc flash protective equipment |
| R-009 | Fire or explosion in the plant
Cause : Combustible dust or explosive atmospheres, flammable storage Consequence : Serious injuries, destruction of facilities |
10 P2×I5 | • ATEX zoning and suitable equipment |
• Automatic detection and suppression |
| R-010 | Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation Consequence : Systems down, data lost, ransom demanded |
10 P2×I5 | • Patching and endpoint protection |
• Tested offline backups |
| R-011 | Cyberattack on industrial control systems
Cause : Industrial network connected to office IT, uncontrolled maintenance access Consequence : Production stopped or disrupted, safety hazard |
10 P2×I5 | • Industrial network segmentation |
• Documented manual fallback mode |
| R-012 | Underperforming heat pump or heating installation
Cause : Wrong sizing, incorrect settings, incompatible emitters Consequence : Poor comfort, higher consumption than expected |
9 P3×I3 | • Heat-loss study and sizing |
• Commissioning and first-season monitoring |
| R-013 | Appeal against a renewable energy project
Cause : Local opposition, contested landscape or biodiversity impact Consequence : Project suspended or cancelled, years of delay |
9 P3×I3 | • Early consultation and robust impact studies |
• Schedule including appeal periods |
| R-014 | Local grid congestion
Cause : Insufficient injection or offtake capacity, long reinforcement times Consequence : Project capped in power or postponed |
9 P3×I3 | • Early grid connection study |
• Flexibility solutions |
| R-015 | Poor command of a new technology or method
Cause : Lack of experience, limited field feedback Consequence : Defects, rework, unplanned learning time |
9 P3×I3 | • Pilot test or prototype • Expert support |
|
| R-016 | Uncontrolled use of generative AI tools
Cause : Staff pasting confidential or personal data into public tools Consequence : Information leak, GDPR non-compliance, loss of trade secrets |
9 P3×I3 | • AI acceptable-use policy • Enterprise AI tool with contractual commitments |
|
| R-017 | Unchecked error produced by an AI system
Cause : Inaccurate output presented as reliable, no review, data bias Consequence : Wrong decision, customer harm, liability |
9 P3×I3 | • Human review of content and decisions • Testing and quality metrics before deployment |
|
| R-018 | Lack of in-house digital skills
Cause : Reliance on one person or a provider, insufficient training Consequence : Stalled projects, poor use of tools, security risks |
9 P3×I3 | • Targeted training plan |
• Documentation and support contract |
| R-019 | Underestimated project complexity
Cause : Many actors, interdependencies, new technologies Consequence : Many surprises, schedule and cost drift |
9 P3×I3 | • Complexity assessment at launch |
• Short phases with decision points |
| R-020 | Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers Consequence : Extra costs, customs delays, closed markets |
9 P3×I3 | • Customs watch and product origin |
• Alternative suppliers in other regions |
| R-021 | DC electric arc
Cause : Poorly crimped or incompatible connectors, work on energised strings in daylight Consequence : Burns, fire on the installation |
8 P2×I4 | • Compatible connectors and checked crimping • Workers trained for DC |
|
| R-022 | Thermal runaway in battery storage
Cause : Cell defect, overcharging, failed ventilation or cooling Consequence : Fire, explosion, toxic gases |
8 P2×I4 | • Battery management system and monitoring |
• Safety distances and fire brigade plan |
| R-023 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
8 P2×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-024 | Burn from hot fluid or corrosive product
Cause : Opening a pressurised or hot circuit, splash, no PPE Consequence : Serious burns, eye injury |
8 P2×I4 | • Drain, cool and depressurise before opening |
• Face shield, gloves and safety shower |
| R-025 | Operating without an up-to-date environmental permit
Cause : Undeclared change of activity, operating conditions not met Consequence : Formal notice, fine, suspension of activity |
8 P2×I4 | • Register of permit obligations • Regulatory check before any modification |
|
| R-026 | Delayed grid connection
Cause : Grid operator lead times, insufficient capacity Consequence : Commissioning postponed, lost revenue |
8 P2×I4 | • Early connection request |
• Schedule aligned with connection date |
| R-027 | Non-compliance with the EU AI Act
Cause : High-risk AI system not identified, insufficient transparency, missing documentation Consequence : Fines, system withdrawn, reputational damage |
8 P2×I4 | • Inventory and classification of AI uses • User information and technical documentation |
|
| R-028 | Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks Consequence : Remediation, use restrictions, dispute with the seller |
8 P2×I4 | • Historical and soil study before acquisition |
• Environmental liability warranties |
| R-029 | Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability Consequence : Fines, producer liability, damaged image |
6 P3×I2 | • Sorting at source and approved contractors |
• Waste register and transfer notes |
| R-030 | Intellectual property infringement
Cause : Use of protected content without rights, no transfer of rights by contractors Consequence : Dispute, product withdrawal, damages |
6 P2×I3 | • Assignment-of-rights clause in contracts • Check licences used |
|
| R-031 | Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose Consequence : Soil and water pollution, costly clean-up |
6 P2×I3 | • Sealed refuelling area |
• Spill kit and response procedure |
| R-032 | Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register Consequence : Fines, liability for fly-tipping |
6 P2×I3 | • Separate skips and signage • Register and transfer notes kept |
|
| R-033 | Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction Consequence : Respiratory diseases, irritation |
6 P2×I3 | • Local extraction and wet methods |
• Suitable respiratory protection |
| R-034 | Excessive reliance on external consultants
Cause : Key skills held by contractors, no knowledge transfer Consequence : Loss of control, recurring costs, knowledge leaving |
6 P2×I3 | • Internal-external pairs |
• Knowledge transfer deliverables |
| R-035 | Occupational skin disease
Cause : Repeated contact with water, detergents, cement or solvents Consequence : Eczema, skin allergies, unfitness for work |
6 P2×I3 | • Substitute irritating products |
• Suitable gloves and skin care |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Battery energy storage”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.