Risk register example: Trade fair stand

Designing and building a stand: tight build-up, suppliers, transport and visitors.

Adapt it to my project (free) Download for Excel (CSV)

Risks29
● Low0
● Moderate15
● High12
● Critical2

Assumptions: Events · Planning / design · 8 people · temporary structures (stages, tents, stands), lifting operations (cranes, hoists), electrical work or work near live installations, site open to the public, tight or immovable deadline, road travel or deliveries, subcontractors involved.

Ref.RiskScorePreventionProtection
R-001 Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer
Consequence : Rushed work, mistakes, penalties, lower quality
16 P4×I4 • Phased delivery
• Pre-identified extra resources
R-002 Road accident while travelling
Cause : Fatigue, tight deadlines, phone use while driving, weather
Consequence : Injuries, employer liability, vehicle off the road
16 P4×I4 • Driving rules and trip planning
• Vehicle maintenance and winter equipment
R-003 Bad weather on the day
Cause : Outdoor event with no fallback option
Consequence : Cancellation, refunds, lost revenue
12 P3×I4 • Covered fallback option
• Cancellation insurance
R-004 Lower attendance than forecast
Cause : Late promotion, competing events, pricing
Consequence : Insufficient revenue, deficit
12 P3×I4 • Promotion plan and pre-sales
• Flexible budget
R-005 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-006 Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan
Consequence : Serious accident, shared liability, site stoppage
12 P3×I4 • Prevention plan and joint inspection
• Daily coordination of work
R-007 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-008 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
12 P3×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-009 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-010 Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground
Consequence : Crushing, fatality, major damage
10 P2×I5 • Lifting plan for critical lifts
• Qualified operators and slingers, inspected gear
• No one under the load
R-011 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
10 P2×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-012 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
10 P2×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-013 Temporary structure collapse
Cause : Unchecked assembly, strong wind, overload
Consequence : Injuries, event interrupted
10 P2×I5 • Inspection by an accredited body
• Wind limit and evacuation procedure
R-014 Pedestrian struck by a delivery vehicle on site
Cause : Pedestrian and vehicle areas not separated, reversing, blind spots
Consequence : Serious or fatal injuries
10 P2×I5 • Physical separation of traffic
• Traffic plan and driver instructions
R-015 Build-up delay before opening
Cause : Limited logistics access, late deliveries, poorly coordinated suppliers
Consequence : Delayed opening, rushed and dangerous build-up
9 P3×I3 • Detailed build-up schedule and delivery slots
• Safety check before opening
R-016 Supplier no-show or late
Cause : Unconfirmed contracts, tight logistics on the day
Consequence : Disrupted programme, dissatisfied audience
9 P3×I3 • Written confirmation and detailed run sheet
• Identified backup suppliers
R-017 Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce
Consequence : Accidents in the first weeks
9 P3×I3 • Systematic safety induction
• Buddy system in the first weeks
R-018 Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision
Consequence : Critical path blocked, delay
9 P3×I3 • External dependency log
• Prepared workaround
R-019 Accident during build-up or tear-down
Cause : Very short timeframes, work at height, contractors working together, fatigue
Consequence : Fall, crushing, late opening
8 P2×I4 • Build-up schedule and contractor coordination
• Prevention plan with each contractor
R-020 Structures blown over by high wind
Cause : Tents, banners, screens or sets not ballasted, no evacuation threshold
Consequence : Injuries, damage, cancellation
8 P2×I4 • Ballast per instructions and check before opening
• Wind thresholds and structure evacuation plan
R-021 Power or sound failure during the event
Cause : Undersized generator, exposed cables, no redundancy
Consequence : Show interrupted, crowd movement, dissatisfaction
8 P2×I4 • Power budget and checked installation
• Backup generator and independent safety lighting
R-022 Supporter disorder at a sports event
Cause : Rivalries, alcohol, counterfeit tickets, insufficient segregation
Consequence : Violence, damage, sanctions
8 P2×I4 • Risk assessment with the police
• Named ticketing and access control
R-023 Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination
Consequence : Injuries, panic, authority held responsible
8 P2×I4 • Safety meeting with police, fire and medical services
• Command post and cancellation procedure
R-024 Event permits refused or late
Cause : Incomplete safety file, late submission, negative opinion from fire services
Consequence : Event reduced, postponed or cancelled
8 P2×I4 • Permit backward schedule
• Early meeting with authorities
R-025 Event cancellation
Cause : Authority ban, extreme weather, artist withdrawal, health crisis
Consequence : Refunds, losses, damaged image
8 P2×I4 • Suitable cancellation insurance
• Terms of sale providing for postponement
R-026 Poor participant experience
Cause : Queues, insufficient toilets, confusing information
Consequence : Negative reviews, fewer participants next year
6 P2×I3 • Size services to attendance
• Real-time information
R-027 Copyright and broadcast permission breaches
Cause : Music played without declaration, unauthorised recordings
Consequence : Increased fees, disputes
6 P2×I3 • Declarations to collecting societies
• Written permissions from artists and speakers
R-028 Child lost during the event
Cause : Dense crowd, no meeting point, insufficient information
Consequence : Distress, search mobilising teams, risk to the child
6 P2×I3 • Wristbands with contact number and meeting point
• Lost child procedure
R-029 Ticketing fraud or failure
Cause : Fake tickets, overloaded platform, fraudulent payments
Consequence : Lost revenue, queues, public dissatisfaction
6 P2×I3 • Named or uniquely coded tickets
• Fallback mode for access control

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Trade fair stand”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free