Risk register example: Sports event

A race or tournament: public roads, participant health, weather, volunteers and crowds.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low1
● Moderate13
● High12
● Critical9

Assumptions: Events · Planning / design · 80 people · large crowds (more than 1,000 people), site open to the public, work on or near public roads, mainly outdoors, works during summer or heatwaves, vulnerable people (patients, children, elderly), permits or authorisations required, new or temporary team.

Ref.RiskScorePreventionProtection
R-001 Heat stroke
Cause : Physical work in full sun, heatwave, insufficient hydration
Consequence : Serious illness, hospitalisation, death
25 P5×I5 • Shifted hours and shaded breaks
• Cool water and buddy checks
R-002 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
20 P4×I5 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-003 Worker struck by road traffic
Cause : Insufficient signage, driver speed, poor visibility
Consequence : Serious injury or death, road user accident
20 P4×I5 • Compliant protected temporary signage
• Traffic order and high-visibility clothing
R-004 Bad weather on the day
Cause : Outdoor event with no fallback option
Consequence : Cancellation, refunds, lost revenue
16 P4×I4 • Covered fallback option
• Cancellation insurance
R-005 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
15 P3×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-006 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-007 Difficulty recruiting qualified staff
Cause : Labour shortage, uncompetitive pay, long hiring times
Consequence : Vacant positions, delays, team overload
15 P5×I3 • Anticipate skill needs
• Partnerships and in-house training
R-008 Pedestrian struck by a delivery vehicle on site
Cause : Pedestrian and vehicle areas not separated, reversing, blind spots
Consequence : Serious or fatal injuries
15 P3×I5 • Physical separation of traffic
• Traffic plan and driver instructions
R-009 Crowd crush
Cause : Capacity exceeded, bottlenecks, insufficient or blocked exits
Consequence : Crushing, many injured, criminal liability of the organiser
15 P3×I5 • Crowd management plan and counting
• Clear emergency exits and trained stewards
R-010 Supporter disorder at a sports event
Cause : Rivalries, alcohol, counterfeit tickets, insufficient segregation
Consequence : Violence, damage, sanctions
12 P3×I4 • Risk assessment with the police
• Named ticketing and access control
R-011 Accident during a road race
Cause : Poorly secured course, vehicles on the route, heat
Consequence : Injured runners and spectators
12 P3×I4 • Course closure and marshals
• First-aid posts along the route
R-012 Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination
Consequence : Injuries, panic, authority held responsible
12 P3×I4 • Safety meeting with police, fire and medical services
• Command post and cancellation procedure
R-013 Medical emergencies among the audience
Cause : Heat, dehydration, alcohol, drugs, dense crowds
Consequence : Casualties, overwhelmed emergency services
12 P3×I4 • Free water points and shaded areas
• Sized first-aid provision
R-014 Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff
Consequence : Panic, injuries during evacuation
12 P3×I4 • Evacuation plan and drill
• Safety PA system and assembly point
R-015 Malicious act or intrusion
Cause : Insufficient access control, unchecked items
Consequence : Theft, vandalism, assault, serious threat
12 P3×I4 • Access control and searches if needed
• Liaison with the police
R-016 Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations
Consequence : Stress, verbal aggression, staff burnout
12 P4×I3 • Conflict-management training
• Post-incident support and reporting
R-017 Structures blown over by high wind
Cause : Tents, banners, screens or sets not ballasted, no evacuation threshold
Consequence : Injuries, damage, cancellation
12 P3×I4 • Ballast per instructions and check before opening
• Wind thresholds and structure evacuation plan
R-018 Lower attendance than forecast
Cause : Late promotion, competing events, pricing
Consequence : Insufficient revenue, deficit
12 P3×I4 • Promotion plan and pre-sales
• Flexible budget
R-019 Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals
Consequence : Delayed start, idle teams, project to be redesigned
12 P4×I3 • Permit back-schedule
• Pre-application meeting with authorities
R-020 New or temporary team unfamiliar with the rules
Cause : Insufficient induction and training, turnover
Consequence : Mistakes, accidents, procedures not followed
12 P4×I3 • Mandatory safety and job induction
• Mentoring by an experienced colleague
R-021 Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce
Consequence : Accidents in the first weeks
12 P4×I3 • Systematic safety induction
• Buddy system in the first weeks
R-022 Child lost during the event
Cause : Dense crowd, no meeting point, insufficient information
Consequence : Distress, search mobilising teams, risk to the child
9 P3×I3 • Wristbands with contact number and meeting point
• Lost child procedure
R-023 Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection
Consequence : Sunburn, long-term skin cancer
9 P3×I3 • Schedule work at less exposed times
• Covering clothing and sunscreen
R-024 Supplier no-show or late
Cause : Unconfirmed contracts, tight logistics on the day
Consequence : Disrupted programme, dissatisfied audience
9 P3×I3 • Written confirmation and detailed run sheet
• Identified backup suppliers
R-025 Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response
Consequence : Loss of trust, lost customers, pressure from authorities
8 P2×I4 • Crisis communication procedure
• Quick-reaction sheet and press contacts
R-026 Event permits refused or late
Cause : Incomplete safety file, late submission, negative opinion from fire services
Consequence : Event reduced, postponed or cancelled
8 P2×I4 • Permit backward schedule
• Early meeting with authorities
R-027 Event cancellation
Cause : Authority ban, extreme weather, artist withdrawal, health crisis
Consequence : Refunds, losses, damaged image
8 P2×I4 • Suitable cancellation insurance
• Terms of sale providing for postponement
R-028 Poor participant experience
Cause : Queues, insufficient toilets, confusing information
Consequence : Negative reviews, fewer participants next year
6 P2×I3 • Size services to attendance
• Real-time information
R-029 Copyright and broadcast permission breaches
Cause : Music played without declaration, unauthorised recordings
Consequence : Increased fees, disputes
6 P2×I3 • Declarations to collecting societies
• Written permissions from artists and speakers
R-030 Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media
Consequence : Loss of trust, lower activity, media crisis
6 P2×I3 • Monitor online mentions
• Ready messages and spokesperson
R-031 Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain
Consequence : Work stoppages, damage, design to revise
6 P2×I3 • Include climate scenarios in design
• Plan to adapt hours and works
R-032 Ticketing fraud or failure
Cause : Fake tickets, overloaded platform, fraudulent payments
Consequence : Lost revenue, queues, public dissatisfaction
6 P2×I3 • Named or uniquely coded tickets
• Fallback mode for access control
R-033 Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available
Consequence : Lost contracts, costlier financing, greenwashing accusations
6 P2×I3 • Collect key sustainability indicators
• Verifiable environmental claims
R-034 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan
R-035 Waste and site damage after the event
Cause : Poor sorting, trampling, waterlogged ground
Consequence : Restoration costs, dispute with owner or municipality
4 P2×I2 • Waste plan and ground protection
• Entry and exit inspection

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Sports event”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples