Risk register example: Corporate event or seminar
A conference, seminar or company party: suppliers, attendance, venue safety and catering.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Events · Planning / design · 10 people · site open to the public, food service, alcohol served, temporary structures (stages, tents, stands), tight or immovable deadline, several companies working at the same time.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
16 P4×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-002 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-003 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
12 P3×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-004 | Bad weather on the day
Cause : Outdoor event with no fallback option Consequence : Cancellation, refunds, lost revenue |
12 P3×I4 | • Covered fallback option • Cancellation insurance |
|
| R-005 | Lower attendance than forecast
Cause : Late promotion, competing events, pricing Consequence : Insufficient revenue, deficit |
12 P3×I4 | • Promotion plan and pre-sales |
• Flexible budget |
| R-006 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-007 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
10 P2×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-008 | Temporary structure collapse
Cause : Unchecked assembly, strong wind, overload Consequence : Injuries, event interrupted |
10 P2×I5 | • Inspection by an accredited body |
• Wind limit and evacuation procedure |
| R-009 | Build-up delay before opening
Cause : Limited logistics access, late deliveries, poorly coordinated suppliers Consequence : Delayed opening, rushed and dangerous build-up |
9 P3×I3 | • Detailed build-up schedule and delivery slots |
• Safety check before opening |
| R-010 | Alcohol-related incidents
Cause : Excessive drinking, no control Consequence : Fights, accidents, organiser liability |
9 P3×I3 | • Responsible serving policy |
• Security staff and first-aid post |
| R-011 | Supplier no-show or late
Cause : Unconfirmed contracts, tight logistics on the day Consequence : Disrupted programme, dissatisfied audience |
9 P3×I3 | • Written confirmation and detailed run sheet |
• Identified backup suppliers |
| R-012 | Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations Consequence : Stress, verbal aggression, staff burnout |
9 P3×I3 | • Conflict-management training |
• Post-incident support and reporting |
| R-013 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
9 P3×I3 | • External dependency log |
• Prepared workaround |
| R-014 | Medical emergencies among the audience
Cause : Heat, dehydration, alcohol, drugs, dense crowds Consequence : Casualties, overwhelmed emergency services |
8 P2×I4 | • Free water points and shaded areas |
• Sized first-aid provision |
| R-015 | Supporter disorder at a sports event
Cause : Rivalries, alcohol, counterfeit tickets, insufficient segregation Consequence : Violence, damage, sanctions |
8 P2×I4 | • Risk assessment with the police • Named ticketing and access control |
|
| R-016 | Accident during build-up or tear-down
Cause : Very short timeframes, work at height, contractors working together, fatigue Consequence : Fall, crushing, late opening |
8 P2×I4 | • Build-up schedule and contractor coordination • Prevention plan with each contractor |
|
| R-017 | Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination Consequence : Injuries, panic, authority held responsible |
8 P2×I4 | • Safety meeting with police, fire and medical services |
• Command post and cancellation procedure |
| R-018 | Structures blown over by high wind
Cause : Tents, banners, screens or sets not ballasted, no evacuation threshold Consequence : Injuries, damage, cancellation |
8 P2×I4 | • Ballast per instructions and check before opening |
• Wind thresholds and structure evacuation plan |
| R-019 | Power or sound failure during the event
Cause : Undersized generator, exposed cables, no redundancy Consequence : Show interrupted, crowd movement, dissatisfaction |
8 P2×I4 | • Power budget and checked installation |
• Backup generator and independent safety lighting |
| R-020 | Food poisoning
Cause : Broken cold chain, poor hygiene, undeclared allergens Consequence : Illness, complaints, health inspection |
8 P2×I4 | • Approved caterer and temperature checks • Allergen information |
|
| R-021 | Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff Consequence : Panic, injuries during evacuation |
8 P2×I4 | • Evacuation plan and drill |
• Safety PA system and assembly point |
| R-022 | Malicious act or intrusion
Cause : Insufficient access control, unchecked items Consequence : Theft, vandalism, assault, serious threat |
8 P2×I4 | • Access control and searches if needed |
• Liaison with the police |
| R-023 | Event permits refused or late
Cause : Incomplete safety file, late submission, negative opinion from fire services Consequence : Event reduced, postponed or cancelled |
8 P2×I4 | • Permit backward schedule • Early meeting with authorities |
|
| R-024 | Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response Consequence : Loss of trust, lost customers, pressure from authorities |
8 P2×I4 | • Crisis communication procedure • Quick-reaction sheet and press contacts |
|
| R-025 | Event cancellation
Cause : Authority ban, extreme weather, artist withdrawal, health crisis Consequence : Refunds, losses, damaged image |
8 P2×I4 | • Suitable cancellation insurance • Terms of sale providing for postponement |
|
| R-026 | Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads Consequence : Sprains, fractures |
8 P2×I4 | • Anti-slip nosings and handrails • Hoists or trolleys for loads |
|
| R-027 | Poor participant experience
Cause : Queues, insufficient toilets, confusing information Consequence : Negative reviews, fewer participants next year |
6 P2×I3 | • Size services to attendance |
• Real-time information |
| R-028 | Copyright and broadcast permission breaches
Cause : Music played without declaration, unauthorised recordings Consequence : Increased fees, disputes |
6 P2×I3 | • Declarations to collecting societies • Written permissions from artists and speakers |
|
| R-029 | Child lost during the event
Cause : Dense crowd, no meeting point, insufficient information Consequence : Distress, search mobilising teams, risk to the child |
6 P2×I3 | • Wristbands with contact number and meeting point |
• Lost child procedure |
| R-030 | Ticketing fraud or failure
Cause : Fake tickets, overloaded platform, fraudulent payments Consequence : Lost revenue, queues, public dissatisfaction |
6 P2×I3 | • Named or uniquely coded tickets |
• Fallback mode for access control |
| R-031 | Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available Consequence : Lost contracts, costlier financing, greenwashing accusations |
6 P2×I3 | • Collect key sustainability indicators • Verifiable environmental claims |
|
| R-032 | Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media Consequence : Loss of trust, lower activity, media crisis |
6 P2×I3 | • Monitor online mentions • Ready messages and spokesperson |
|
| R-033 | Exposure to biological agents
Cause : Contact with sick people, waste, animals or contaminated water Consequence : Infections, absences |
6 P2×I3 | • Hand hygiene and recommended vaccination |
• Protective equipment and exposure procedure |
| R-034 | Occupational skin disease
Cause : Repeated contact with water, detergents, cement or solvents Consequence : Eczema, skin allergies, unfitness for work |
6 P2×I3 | • Substitute irritating products |
• Suitable gloves and skin care |
| R-035 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Corporate event or seminar”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.