Risk register example: Outdoor festival
A festival in the open air: crowds, temporary structures, weather, alcohol, security and permits.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Events · Planning / design · 150 people · large crowds (more than 1,000 people), site open to the public, temporary structures (stages, tents, stands), mainly outdoors, works during summer or heatwaves, alcohol served, food service, night or shift work, electrical work or work near live installations, permits or authorisations required, several companies working at the same time, tight or immovable deadline.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Crowd crush
Cause : Capacity exceeded, bottlenecks, insufficient or blocked exits Consequence : Crushing, many injured, criminal liability of the organiser |
20 P4×I5 | • Crowd management plan and counting |
• Clear emergency exits and trained stewards |
| R-002 | Temporary structure collapse
Cause : Unchecked assembly, strong wind, overload Consequence : Injuries, event interrupted |
20 P4×I5 | • Inspection by an accredited body |
• Wind limit and evacuation procedure |
| R-003 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
16 P4×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-004 | Bad weather on the day
Cause : Outdoor event with no fallback option Consequence : Cancellation, refunds, lost revenue |
16 P4×I4 | • Covered fallback option • Cancellation insurance |
|
| R-005 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
15 P5×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-006 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-007 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-008 | Medical emergencies among the audience
Cause : Heat, dehydration, alcohol, drugs, dense crowds Consequence : Casualties, overwhelmed emergency services |
12 P3×I4 | • Free water points and shaded areas |
• Sized first-aid provision |
| R-009 | Supporter disorder at a sports event
Cause : Rivalries, alcohol, counterfeit tickets, insufficient segregation Consequence : Violence, damage, sanctions |
12 P3×I4 | • Risk assessment with the police • Named ticketing and access control |
|
| R-010 | Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination Consequence : Injuries, panic, authority held responsible |
12 P3×I4 | • Safety meeting with police, fire and medical services |
• Command post and cancellation procedure |
| R-011 | Structures blown over by high wind
Cause : Tents, banners, screens or sets not ballasted, no evacuation threshold Consequence : Injuries, damage, cancellation |
12 P3×I4 | • Ballast per instructions and check before opening |
• Wind thresholds and structure evacuation plan |
| R-012 | Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff Consequence : Panic, injuries during evacuation |
12 P3×I4 | • Evacuation plan and drill |
• Safety PA system and assembly point |
| R-013 | Malicious act or intrusion
Cause : Insufficient access control, unchecked items Consequence : Theft, vandalism, assault, serious threat |
12 P3×I4 | • Access control and searches if needed |
• Liaison with the police |
| R-014 | Accident during build-up or tear-down
Cause : Very short timeframes, work at height, contractors working together, fatigue Consequence : Fall, crushing, late opening |
12 P3×I4 | • Build-up schedule and contractor coordination • Prevention plan with each contractor |
|
| R-015 | Accident during a road race
Cause : Poorly secured course, vehicles on the route, heat Consequence : Injured runners and spectators |
12 P3×I4 | • Course closure and marshals |
• First-aid posts along the route |
| R-016 | Lower attendance than forecast
Cause : Late promotion, competing events, pricing Consequence : Insufficient revenue, deficit |
12 P3×I4 | • Promotion plan and pre-sales |
• Flexible budget |
| R-017 | Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations Consequence : Stress, verbal aggression, staff burnout |
12 P4×I3 | • Conflict-management training |
• Post-incident support and reporting |
| R-018 | Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions Consequence : Chronic stress, errors, accidents, absenteeism |
12 P4×I3 | • Realistic workload planning |
• Spot warning signs |
| R-019 | Child lost during the event
Cause : Dense crowd, no meeting point, insufficient information Consequence : Distress, search mobilising teams, risk to the child |
9 P3×I3 | • Wristbands with contact number and meeting point |
• Lost child procedure |
| R-020 | Build-up delay before opening
Cause : Limited logistics access, late deliveries, poorly coordinated suppliers Consequence : Delayed opening, rushed and dangerous build-up |
9 P3×I3 | • Detailed build-up schedule and delivery slots |
• Safety check before opening |
| R-021 | Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection Consequence : Sunburn, long-term skin cancer |
9 P3×I3 | • Schedule work at less exposed times |
• Covering clothing and sunscreen |
| R-022 | Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted Consequence : Harm to mother or child, non-compliance |
9 P3×I3 | • Specific assessment once pregnancy is announced • List of at-risk jobs prepared in advance |
|
| R-023 | Supplier no-show or late
Cause : Unconfirmed contracts, tight logistics on the day Consequence : Disrupted programme, dissatisfied audience |
9 P3×I3 | • Written confirmation and detailed run sheet |
• Identified backup suppliers |
| R-024 | Poorly managed interfaces between work packages or teams
Cause : Unclear responsibilities at boundaries, information not passed on Consequence : Omissions, duplication, delays and disputes |
9 P3×I3 | • Interface matrix |
• Interface review at coordination meetings |
| R-025 | Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response Consequence : Loss of trust, lost customers, pressure from authorities |
8 P2×I4 | • Crisis communication procedure • Quick-reaction sheet and press contacts |
|
| R-026 | Power or sound failure during the event
Cause : Undersized generator, exposed cables, no redundancy Consequence : Show interrupted, crowd movement, dissatisfaction |
8 P2×I4 | • Power budget and checked installation |
• Backup generator and independent safety lighting |
| R-027 | Event permits refused or late
Cause : Incomplete safety file, late submission, negative opinion from fire services Consequence : Event reduced, postponed or cancelled |
8 P2×I4 | • Permit backward schedule • Early meeting with authorities |
|
| R-028 | Event cancellation
Cause : Authority ban, extreme weather, artist withdrawal, health crisis Consequence : Refunds, losses, damaged image |
8 P2×I4 | • Suitable cancellation insurance • Terms of sale providing for postponement |
|
| R-029 | Poor participant experience
Cause : Queues, insufficient toilets, confusing information Consequence : Negative reviews, fewer participants next year |
6 P2×I3 | • Size services to attendance |
• Real-time information |
| R-030 | Copyright and broadcast permission breaches
Cause : Music played without declaration, unauthorised recordings Consequence : Increased fees, disputes |
6 P2×I3 | • Declarations to collecting societies • Written permissions from artists and speakers |
|
| R-031 | Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media Consequence : Loss of trust, lower activity, media crisis |
6 P2×I3 | • Monitor online mentions • Ready messages and spokesperson |
|
| R-032 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
6 P2×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-033 | Ticketing fraud or failure
Cause : Fake tickets, overloaded platform, fraudulent payments Consequence : Lost revenue, queues, public dissatisfaction |
6 P2×I3 | • Named or uniquely coded tickets |
• Fallback mode for access control |
| R-034 | Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available Consequence : Lost contracts, costlier financing, greenwashing accusations |
6 P2×I3 | • Collect key sustainability indicators • Verifiable environmental claims |
|
| R-035 | Waste and site damage after the event
Cause : Poor sorting, trampling, waterlogged ground Consequence : Restoration costs, dispute with owner or municipality |
4 P2×I2 | • Waste plan and ground protection |
• Entry and exit inspection |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.