Risk register example: Outdoor festival

A festival in the open air: crowds, temporary structures, weather, alcohol, security and permits.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low1
● Moderate16
● High11
● Critical7

Assumptions: Events · Planning / design · 150 people · large crowds (more than 1,000 people), site open to the public, temporary structures (stages, tents, stands), mainly outdoors, works during summer or heatwaves, alcohol served, food service, night or shift work, electrical work or work near live installations, permits or authorisations required, several companies working at the same time, tight or immovable deadline.

Ref.RiskScorePreventionProtection
R-001 Crowd crush
Cause : Capacity exceeded, bottlenecks, insufficient or blocked exits
Consequence : Crushing, many injured, criminal liability of the organiser
20 P4×I5 • Crowd management plan and counting
• Clear emergency exits and trained stewards
R-002 Temporary structure collapse
Cause : Unchecked assembly, strong wind, overload
Consequence : Injuries, event interrupted
20 P4×I5 • Inspection by an accredited body
• Wind limit and evacuation procedure
R-003 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
16 P4×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-004 Bad weather on the day
Cause : Outdoor event with no fallback option
Consequence : Cancellation, refunds, lost revenue
16 P4×I4 • Covered fallback option
• Cancellation insurance
R-005 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
15 P5×I3 • Workload monitoring
• Confidential counsellor and support
R-006 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
15 P3×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-007 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-008 Medical emergencies among the audience
Cause : Heat, dehydration, alcohol, drugs, dense crowds
Consequence : Casualties, overwhelmed emergency services
12 P3×I4 • Free water points and shaded areas
• Sized first-aid provision
R-009 Supporter disorder at a sports event
Cause : Rivalries, alcohol, counterfeit tickets, insufficient segregation
Consequence : Violence, damage, sanctions
12 P3×I4 • Risk assessment with the police
• Named ticketing and access control
R-010 Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination
Consequence : Injuries, panic, authority held responsible
12 P3×I4 • Safety meeting with police, fire and medical services
• Command post and cancellation procedure
R-011 Structures blown over by high wind
Cause : Tents, banners, screens or sets not ballasted, no evacuation threshold
Consequence : Injuries, damage, cancellation
12 P3×I4 • Ballast per instructions and check before opening
• Wind thresholds and structure evacuation plan
R-012 Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff
Consequence : Panic, injuries during evacuation
12 P3×I4 • Evacuation plan and drill
• Safety PA system and assembly point
R-013 Malicious act or intrusion
Cause : Insufficient access control, unchecked items
Consequence : Theft, vandalism, assault, serious threat
12 P3×I4 • Access control and searches if needed
• Liaison with the police
R-014 Accident during build-up or tear-down
Cause : Very short timeframes, work at height, contractors working together, fatigue
Consequence : Fall, crushing, late opening
12 P3×I4 • Build-up schedule and contractor coordination
• Prevention plan with each contractor
R-015 Accident during a road race
Cause : Poorly secured course, vehicles on the route, heat
Consequence : Injured runners and spectators
12 P3×I4 • Course closure and marshals
• First-aid posts along the route
R-016 Lower attendance than forecast
Cause : Late promotion, competing events, pricing
Consequence : Insufficient revenue, deficit
12 P3×I4 • Promotion plan and pre-sales
• Flexible budget
R-017 Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations
Consequence : Stress, verbal aggression, staff burnout
12 P4×I3 • Conflict-management training
• Post-incident support and reporting
R-018 Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions
Consequence : Chronic stress, errors, accidents, absenteeism
12 P4×I3 • Realistic workload planning
• Spot warning signs
R-019 Child lost during the event
Cause : Dense crowd, no meeting point, insufficient information
Consequence : Distress, search mobilising teams, risk to the child
9 P3×I3 • Wristbands with contact number and meeting point
• Lost child procedure
R-020 Build-up delay before opening
Cause : Limited logistics access, late deliveries, poorly coordinated suppliers
Consequence : Delayed opening, rushed and dangerous build-up
9 P3×I3 • Detailed build-up schedule and delivery slots
• Safety check before opening
R-021 Exposure to solar ultraviolet radiation
Cause : Long outdoor work in summer without protection
Consequence : Sunburn, long-term skin cancer
9 P3×I3 • Schedule work at less exposed times
• Covering clothing and sunscreen
R-022 Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted
Consequence : Harm to mother or child, non-compliance
9 P3×I3 • Specific assessment once pregnancy is announced
• List of at-risk jobs prepared in advance
R-023 Supplier no-show or late
Cause : Unconfirmed contracts, tight logistics on the day
Consequence : Disrupted programme, dissatisfied audience
9 P3×I3 • Written confirmation and detailed run sheet
• Identified backup suppliers
R-024 Poorly managed interfaces between work packages or teams
Cause : Unclear responsibilities at boundaries, information not passed on
Consequence : Omissions, duplication, delays and disputes
9 P3×I3 • Interface matrix
• Interface review at coordination meetings
R-025 Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response
Consequence : Loss of trust, lost customers, pressure from authorities
8 P2×I4 • Crisis communication procedure
• Quick-reaction sheet and press contacts
R-026 Power or sound failure during the event
Cause : Undersized generator, exposed cables, no redundancy
Consequence : Show interrupted, crowd movement, dissatisfaction
8 P2×I4 • Power budget and checked installation
• Backup generator and independent safety lighting
R-027 Event permits refused or late
Cause : Incomplete safety file, late submission, negative opinion from fire services
Consequence : Event reduced, postponed or cancelled
8 P2×I4 • Permit backward schedule
• Early meeting with authorities
R-028 Event cancellation
Cause : Authority ban, extreme weather, artist withdrawal, health crisis
Consequence : Refunds, losses, damaged image
8 P2×I4 • Suitable cancellation insurance
• Terms of sale providing for postponement
R-029 Poor participant experience
Cause : Queues, insufficient toilets, confusing information
Consequence : Negative reviews, fewer participants next year
6 P2×I3 • Size services to attendance
• Real-time information
R-030 Copyright and broadcast permission breaches
Cause : Music played without declaration, unauthorised recordings
Consequence : Increased fees, disputes
6 P2×I3 • Declarations to collecting societies
• Written permissions from artists and speakers
R-031 Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media
Consequence : Loss of trust, lower activity, media crisis
6 P2×I3 • Monitor online mentions
• Ready messages and spokesperson
R-032 Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain
Consequence : Work stoppages, damage, design to revise
6 P2×I3 • Include climate scenarios in design
• Plan to adapt hours and works
R-033 Ticketing fraud or failure
Cause : Fake tickets, overloaded platform, fraudulent payments
Consequence : Lost revenue, queues, public dissatisfaction
6 P2×I3 • Named or uniquely coded tickets
• Fallback mode for access control
R-034 Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available
Consequence : Lost contracts, costlier financing, greenwashing accusations
6 P2×I3 • Collect key sustainability indicators
• Verifiable environmental claims
R-035 Waste and site damage after the event
Cause : Poor sorting, trampling, waterlogged ground
Consequence : Restoration costs, dispute with owner or municipality
4 P2×I2 • Waste plan and ground protection
• Entry and exit inspection

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Outdoor festival”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free