Risk register example: Plant shutdown and turnaround
A short and dense maintenance stop: many contractors, permits to work, confined spaces and hot work.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Industry / manufacturing · Execution / works · 120 people · confined spaces (tanks, pits, sewers), hot work (welding, cutting, grinding), work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), hazardous chemicals, pressure systems, gas, steam, electrical work or work near live installations, night or shift work, several companies working at the same time, subcontractors involved, tight or immovable deadline.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Fire caused by hot work
Cause : Sparks near combustible materials, no fire watch after work Consequence : Building fire, injuries, business interruption |
25 P5×I5 | • Hot work permit |
• Two-hour fire watch after work |
| R-002 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
25 P5×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-003 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
20 P5×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-004 | Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure Consequence : Equipment energised or moving with a worker exposed |
20 P4×I5 | • Lockout procedure with personal padlocks • Check before restart |
|
| R-005 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
20 P5×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-006 | Molten metal or spark projection
Cause : Casting, welding, thermal cutting without suitable protection Consequence : Serious burns, fire |
16 P4×I4 | • Protective screens and marked zones |
• Flame-resistant clothing and suitable equipment |
| R-007 | Leak of a hazardous product or gas
Cause : Faulty seal, corrosion, handling error during transfer Consequence : Poisoning, fire, pollution |
16 P4×I4 | • Inspect transfer and storage equipment |
• Bunding, detectors and spill kits |
| R-008 | Burn from hot fluid or corrosive product
Cause : Opening a pressurised or hot circuit, splash, no PPE Consequence : Serious burns, eye injury |
16 P4×I4 | • Drain, cool and depressurise before opening |
• Face shield, gloves and safety shower |
| R-009 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
16 P4×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-010 | Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source Consequence : Explosion, fire, collapse |
16 P4×I4 | • Regular cleaning and dust extraction |
• Venting and isolation of equipment |
| R-011 | Load falling from an overhead crane
Cause : Worn slings, incorrect rigging, overload Consequence : Crushing, material damage |
16 P4×I4 | • Check lifting accessories • Train riggers and crane operators |
|
| R-012 | Incompatible products stored together
Cause : Acids and bases, oxidisers and flammables side by side Consequence : Dangerous reaction, fire, toxic gases |
16 P4×I4 | • Storage plan by hazard class |
• Separate bunds and detection |
| R-013 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-014 | Exposure to hazardous chemicals
Cause : Safety data sheets unknown, unsuitable ventilation and PPE Consequence : Poisoning, burns, occupational disease |
16 P4×I4 | • Substitute with a less hazardous product • Inventory, safety data sheets and training |
• Eyewash and emergency kit |
| R-015 | Runaway chemical reaction
Cause : Dosing error, cooling failure, contamination Consequence : Explosion, toxic release, casualties |
15 P3×I5 | • Process safety study |
• Relief vents and internal emergency plan |
| R-016 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
15 P5×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-017 | Exposure to carcinogens
Cause : Welding fumes, wood dust, solvents, silica Consequence : Occupational cancers, employer liability |
12 P3×I4 | • Substitution and local exhaust • Exposure measurement and health surveillance |
|
| R-018 | Discharge limits exceeded
Cause : Saturated treatment plant, process drift Consequence : Formal notice, fine, administrative shutdown |
12 P3×I4 | • Self-monitoring and threshold alarms |
• Output reduction procedure |
| R-019 | Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions Consequence : Chronic stress, errors, accidents, absenteeism |
12 P4×I3 | • Realistic workload planning |
• Spot warning signs |
| R-020 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-021 | Fatigue and reduced alertness from night work
Cause : Shifted hours, insufficient sleep, poor lighting Consequence : Mistakes, accidents, health problems |
12 P4×I3 | • Shift and break planning • Adequate lighting everywhere |
|
| R-022 | Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce Consequence : Accidents in the first weeks |
12 P4×I3 | • Systematic safety induction • Buddy system in the first weeks |
|
| R-023 | Unplanned production stoppage
Cause : Critical equipment failure, no spare parts Consequence : Late orders, operating losses |
12 P3×I4 | • Equipment criticality analysis |
• Critical spare parts stock |
| R-024 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-025 | Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks Consequence : Remediation, use restrictions, dispute with the seller |
12 P3×I4 | • Historical and soil study before acquisition |
• Environmental liability warranties |
| R-026 | Product recall
Cause : Manufacturing defect, contamination, labelling error Consequence : Withdrawal costs, loss of customers, brand damage |
10 P2×I5 | • Quality checks at critical steps |
• Batch traceability and tested recall procedure |
| R-027 | Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance Consequence : Unpaid invoices, lost revenue, cash strain |
10 P2×I5 | • Monitor key customers’ financial health |
• Credit insurance or payment guarantees |
| R-028 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
9 P3×I3 | • External dependency log |
• Prepared workaround |
| R-029 | Poor management of hazardous waste
Cause : Mixed waste, non-compliant storage, unauthorised disposal route Consequence : Pollution, penalties, producer liability |
9 P3×I3 | • Sorting, labelling and bunded storage • Licensed collectors and traceability |
|
| R-030 | No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified Consequence : Avoidable accidents, non-compliance on inspection |
9 P3×I3 | • Annual review and after every change • Worker participation |
|
| R-031 | Poorly managed interfaces between work packages or teams
Cause : Unclear responsibilities at boundaries, information not passed on Consequence : Omissions, duplication, delays and disputes |
9 P3×I3 | • Interface matrix |
• Interface review at coordination meetings |
| R-032 | Non-conforming product delivered
Cause : Process drift, insufficient inspections Consequence : Claims, recalls, loss of customers |
9 P3×I3 | • Control plan and statistical monitoring |
• Batch traceability |
| R-033 | Operating without an up-to-date environmental permit
Cause : Undeclared change of activity, operating conditions not met Consequence : Formal notice, fine, suspension of activity |
8 P2×I4 | • Register of permit obligations • Regulatory check before any modification |
|
| R-034 | Non-compliance with chemical registration and restriction rules
Cause : Substance subject to authorisation or restriction used unknowingly Consequence : Forced stop, reformulation, penalties |
8 P2×I4 | • Watch substances of concern |
• Early substitution plan |
| R-035 | Non-compliant safety data sheets and labelling
Cause : Products without up-to-date sheets, misclassified mixtures, missing labels Consequence : Poor prevention, penalties, customer refusal |
6 P2×I3 | • Product inventory with current sheets • Label secondary containers |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Plant shutdown and turnaround”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.