Risk register example: Chemical storage facility

Storing hazardous products: compatibility, retention, fire and explosion risks, permits.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate24
● High9
● Critical2

Assumptions: Industry / manufacturing · Planning / design · 10 people · hazardous chemicals, pressure systems, gas, steam, hot work (welding, cutting, grinding), site in operation (co-activity with production), permits or authorisations required, near water or flood-prone area, protected natural area or sensitive environment.

Ref.RiskScorePreventionProtection
R-001 Fire caused by hot work
Cause : Sparks near combustible materials, no fire watch after work
Consequence : Building fire, injuries, business interruption
20 P4×I5 • Hot work permit
• Two-hour fire watch after work
R-002 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-003 Pollution of a watercourse or sensitive environment
Cause : Run-off, fuel stored without bunding, accidental release
Consequence : Harm to wildlife and plants, sanctions, costly restoration
12 P3×I4 • Bunding, refuelling area and settling ponds
• Spill kits and alert procedure
R-004 Exposure to hazardous chemicals
Cause : Safety data sheets unknown, unsuitable ventilation and PPE
Consequence : Poisoning, burns, occupational disease
12 P3×I4 • Substitute with a less hazardous product
• Inventory, safety data sheets and training
• Eyewash and emergency kit
R-005 Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals
Consequence : Delayed start, idle teams, project to be redesigned
12 P4×I3 • Permit back-schedule
• Pre-application meeting with authorities
R-006 Interference between work and ongoing operations
Cause : Unexpected start-up of installations, production flows not stopped
Consequence : Accident, production stoppage, damage
12 P3×I4 • Work permit issued by the operator
• Direct link with the control room
R-007 Unplanned production stoppage
Cause : Critical equipment failure, no spare parts
Consequence : Late orders, operating losses
12 P3×I4 • Equipment criticality analysis
• Critical spare parts stock
R-008 Accident during an urgent breakdown repair
Cause : Pressure to restart quickly, risk assessment skipped
Consequence : Serious injury, worse breakdown
12 P3×I4 • Quick risk check before each repair
• Stop-work authority backed by management
R-009 Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure
Consequence : Equipment energised or moving with a worker exposed
10 P2×I5 • Lockout procedure with personal padlocks
• Check before restart
R-010 Explosion or leak of pressure equipment or gas
Cause : Uninspected equipment, faulty fittings, mishandling
Consequence : Burns, serious injuries, fire
10 P2×I5 • Statutory inspections and maintenance
• Gas detection and emergency procedure
R-011 Product recall
Cause : Manufacturing defect, contamination, labelling error
Consequence : Withdrawal costs, loss of customers, brand damage
10 P2×I5 • Quality checks at critical steps
• Batch traceability and tested recall procedure
R-012 Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion
Consequence : Studies and works to redo, extra costs, delay
9 P3×I3 • Project-specific regulatory watch
• Change-in-law clause
R-013 Non-conforming product delivered
Cause : Process drift, insufficient inspections
Consequence : Claims, recalls, loss of customers
9 P3×I3 • Control plan and statistical monitoring
• Batch traceability
R-014 Raw material shortage
Cause : Tight markets, failing supplier
Consequence : Reduced production, higher costs
9 P3×I3 • Dual sourcing of critical materials
• Sized safety stock
R-015 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-016 Molten metal or spark projection
Cause : Casting, welding, thermal cutting without suitable protection
Consequence : Serious burns, fire
8 P2×I4 • Protective screens and marked zones
• Flame-resistant clothing and suitable equipment
R-017 Leak of a hazardous product or gas
Cause : Faulty seal, corrosion, handling error during transfer
Consequence : Poisoning, fire, pollution
8 P2×I4 • Inspect transfer and storage equipment
• Bunding, detectors and spill kits
R-018 Burn from hot fluid or corrosive product
Cause : Opening a pressurised or hot circuit, splash, no PPE
Consequence : Serious burns, eye injury
8 P2×I4 • Drain, cool and depressurise before opening
• Face shield, gloves and safety shower
R-019 Operating without an up-to-date environmental permit
Cause : Undeclared change of activity, operating conditions not met
Consequence : Formal notice, fine, suspension of activity
8 P2×I4 • Register of permit obligations
• Regulatory check before any modification
R-020 Exposure to carcinogens
Cause : Welding fumes, wood dust, solvents, silica
Consequence : Occupational cancers, employer liability
8 P2×I4 • Substitution and local exhaust
• Exposure measurement and health surveillance
R-021 Non-compliance with chemical registration and restriction rules
Cause : Substance subject to authorisation or restriction used unknowingly
Consequence : Forced stop, reformulation, penalties
8 P2×I4 • Watch substances of concern
• Early substitution plan
R-022 Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks
Consequence : Remediation, use restrictions, dispute with the seller
8 P2×I4 • Historical and soil study before acquisition
• Environmental liability warranties
R-023 Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source
Consequence : Explosion, fire, collapse
8 P2×I4 • Regular cleaning and dust extraction
• Venting and isolation of equipment
R-024 Incompatible products stored together
Cause : Acids and bases, oxidisers and flammables side by side
Consequence : Dangerous reaction, fire, toxic gases
8 P2×I4 • Storage plan by hazard class
• Separate bunds and detection
R-025 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
8 P2×I4 • Isolate all energy sources
• Lockout sheets per machine
R-026 Discharge limits exceeded
Cause : Saturated treatment plant, process drift
Consequence : Formal notice, fine, administrative shutdown
8 P2×I4 • Self-monitoring and threshold alarms
• Output reduction procedure
R-027 Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts
Consequence : Damage to installations, business interruption, repair costs
8 P2×I4 • Climate vulnerability assessment of the site
• Weather alert and safety plan
R-028 Site flooding
Cause : Flood-prone area, heavy rain, rising groundwater
Consequence : Damage to works and equipment, extended stoppage
8 P2×I4 • Weather watch and flood alerts
• Store equipment outside flood zone
R-029 Non-compliant safety data sheets and labelling
Cause : Products without up-to-date sheets, misclassified mixtures, missing labels
Consequence : Poor prevention, penalties, customer refusal
6 P2×I3 • Product inventory with current sheets
• Label secondary containers
R-030 Poor management of hazardous waste
Cause : Mixed waste, non-compliant storage, unauthorised disposal route
Consequence : Pollution, penalties, producer liability
6 P2×I3 • Sorting, labelling and bunded storage
• Licensed collectors and traceability
R-031 Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose
Consequence : Soil and water pollution, costly clean-up
6 P2×I3 • Sealed refuelling area
• Spill kit and response procedure
R-032 Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register
Consequence : Fines, liability for fly-tipping
6 P2×I3 • Separate skips and signage
• Register and transfer notes kept
R-033 Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction
Consequence : Respiratory diseases, irritation
6 P2×I3 • Local extraction and wet methods
• Suitable respiratory protection
R-034 Occupational skin disease
Cause : Repeated contact with water, detergents, cement or solvents
Consequence : Eczema, skin allergies, unfitness for work
6 P2×I3 • Substitute irritating products
• Suitable gloves and skin care
R-035 Runaway chemical reaction
Cause : Dosing error, cooling failure, contamination
Consequence : Explosion, toxic release, casualties
5 P1×I5 • Process safety study
• Relief vents and internal emergency plan

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Chemical storage facility”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free