Risk register example: Industrial relocation
Moving machines or a whole plant: dismantling, heavy transport, re-commissioning and lost production.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Industry / manufacturing · Planning / design · 30 people · machines or production equipment, lifting operations (cranes, hoists), road travel or deliveries, electrical work or work near live installations, heavy or repetitive manual handling, several sites, tight or immovable deadline, subcontractors involved.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Road accident while travelling
Cause : Fatigue, tight deadlines, phone use while driving, weather Consequence : Injuries, employer liability, vehicle off the road |
16 P4×I4 | • Driving rules and trip planning • Vehicle maintenance and winter equipment |
|
| R-002 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-003 | Caught in or crushed by a machine
Cause : Guards removed, work without lockout, residual energy Consequence : Amputation, crushing, fatality |
15 P3×I5 | • Lockout of all energy sources • Guards and emergency stops checked |
|
| R-004 | Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation Consequence : Tendinitis, carpal tunnel syndrome, sick leave |
12 P4×I3 | • Ergonomic analysis of repetitive tasks • Job rotation |
|
| R-005 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
12 P4×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-006 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-007 | Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures Consequence : Chronic pain, sick leave, unfitness for work |
12 P4×I3 | • Handling aids • Task rotation and handling training |
|
| R-008 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-009 | Unplanned production stoppage
Cause : Critical equipment failure, no spare parts Consequence : Late orders, operating losses |
12 P3×I4 | • Equipment criticality analysis |
• Critical spare parts stock |
| R-010 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-011 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
10 P2×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-012 | Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure Consequence : Equipment energised or moving with a worker exposed |
10 P2×I5 | • Lockout procedure with personal padlocks • Check before restart |
|
| R-013 | Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground Consequence : Crushing, fatality, major damage |
10 P2×I5 | • Lifting plan for critical lifts • Qualified operators and slingers, inspected gear |
• No one under the load |
| R-014 | Internal fraud or embezzlement
Cause : Insufficient segregation of duties, rare accounting checks, shared bank access Consequence : Financial losses, misstated accounts, dispute and proceedings |
10 P2×I5 | • Segregation of duties for payments |
• Bank reconciliations and surprise checks |
| R-015 | Product recall
Cause : Manufacturing defect, contamination, labelling error Consequence : Withdrawal costs, loss of customers, brand damage |
10 P2×I5 | • Quality checks at critical steps |
• Batch traceability and tested recall procedure |
| R-016 | Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance Consequence : Unpaid invoices, lost revenue, cash strain |
10 P2×I5 | • Monitor key customers’ financial health |
• Credit insurance or payment guarantees |
| R-017 | Failure of a bottleneck machine
Cause : Single machine without redundancy, insufficient preventive maintenance, unavailable parts Consequence : Whole production stopped |
9 P3×I3 | • Enhanced preventive maintenance on bottlenecks |
• Critical spare parts in stock |
| R-018 | Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection Consequence : Lacerations, tendon injuries |
9 P3×I3 | • Retractable-blade tools |
• Suitable cut-resistant gloves |
| R-019 | Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce Consequence : Accidents in the first weeks |
9 P3×I3 | • Systematic safety induction • Buddy system in the first weeks |
|
| R-020 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
9 P3×I3 | • External dependency log |
• Prepared workaround |
| R-021 | Non-conforming product delivered
Cause : Process drift, insufficient inspections Consequence : Claims, recalls, loss of customers |
9 P3×I3 | • Control plan and statistical monitoring |
• Batch traceability |
| R-022 | Raw material shortage
Cause : Tight markets, failing supplier Consequence : Reduced production, higher costs |
9 P3×I3 | • Dual sourcing of critical materials |
• Sized safety stock |
| R-023 | Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in Consequence : Slow diagnosis, poor decisions, repeated interventions |
9 P3×I3 | • Systematic work order close-out |
• Update drawings after changes |
| R-024 | Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions Consequence : Chronic stress, errors, accidents, absenteeism |
9 P3×I3 | • Realistic workload planning |
• Spot warning signs |
| R-025 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
8 P2×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-026 | Modified or new machine not compliant
Cause : Guards removed, change without assessment, acceptance without checks Consequence : Serious accident, employer liability, enforced shutdown |
8 P2×I4 | • Risk assessment before any modification • Safety acceptance of new equipment |
|
| R-027 | Defeating machine guards
Cause : Inconvenient guards, production pressure, bypassed interlocks Consequence : Entanglement, amputation |
8 P2×I4 | • Guard audits and action on bypasses • Ergonomic improvement of guards |
|
| R-028 | Alcohol or drug use at work
Cause : Celebrations, recreational use, addiction, no clear policy Consequence : Serious accidents, dangerous behaviour |
8 P2×I4 | • Alcohol and drug policy |
• Remove from dangerous tasks in case of doubt |
| R-029 | Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source Consequence : Explosion, fire, collapse |
8 P2×I4 | • Regular cleaning and dust extraction |
• Venting and isolation of equipment |
| R-030 | Load falling from an overhead crane
Cause : Worn slings, incorrect rigging, overload Consequence : Crushing, material damage |
8 P2×I4 | • Check lifting accessories • Train riggers and crane operators |
|
| R-031 | Discharge limits exceeded
Cause : Saturated treatment plant, process drift Consequence : Formal notice, fine, administrative shutdown |
8 P2×I4 | • Self-monitoring and threshold alarms |
• Output reduction procedure |
| R-032 | Quality non-conformity found at the customer
Cause : Insufficient final checks, undetected process drift Consequence : Complaints, returns, customer loss |
8 P2×I4 | • Statistical control of critical parameters |
• Eight-step complaint handling |
| R-033 | Hand-arm and whole-body vibration
Cause : Vibrating tools, machines on rough ground, long exposure Consequence : Vascular and joint disorders, low back pain |
6 P2×I3 | • Low-vibration tools and suspended seats • Limit exposure time |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Industrial relocation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.