Risk register example: Machine safety upgrade

Bringing machines up to standard: guarding, lockout, control systems and production interruptions.

Adapt it to my project (free) Download for Excel (CSV)

Risks34
● Low0
● Moderate12
● High15
● Critical7

Assumptions: Industry / manufacturing · Execution / works · 6 people · machines or production equipment, electrical work or work near live installations, site in operation (co-activity with production), industrial control systems (automation, scada), subcontractors involved.

Ref.RiskScorePreventionProtection
R-001 Caught in or crushed by a machine
Cause : Guards removed, work without lockout, residual energy
Consequence : Amputation, crushing, fatality
25 P5×I5 • Lockout of all energy sources
• Guards and emergency stops checked
R-002 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
20 P4×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-003 Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan
Consequence : Serious accident, shared liability, site stoppage
20 P5×I4 • Prevention plan and joint inspection
• Daily coordination of work
R-004 Interference between work and ongoing operations
Cause : Unexpected start-up of installations, production flows not stopped
Consequence : Accident, production stoppage, damage
16 P4×I4 • Work permit issued by the operator
• Direct link with the control room
R-005 Accident during an urgent breakdown repair
Cause : Pressure to restart quickly, risk assessment skipped
Consequence : Serious injury, worse breakdown
16 P4×I4 • Quick risk check before each repair
• Stop-work authority backed by management
R-006 Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure
Consequence : Equipment energised or moving with a worker exposed
15 P3×I5 • Lockout procedure with personal padlocks
• Check before restart
R-007 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
15 P3×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-008 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
12 P3×I4 • Isolate all energy sources
• Lockout sheets per machine
R-009 Modified or new machine not compliant
Cause : Guards removed, change without assessment, acceptance without checks
Consequence : Serious accident, employer liability, enforced shutdown
12 P3×I4 • Risk assessment before any modification
• Safety acceptance of new equipment
R-010 Defeating machine guards
Cause : Inconvenient guards, production pressure, bypassed interlocks
Consequence : Entanglement, amputation
12 P3×I4 • Guard audits and action on bypasses
• Ergonomic improvement of guards
R-011 Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source
Consequence : Explosion, fire, collapse
12 P3×I4 • Regular cleaning and dust extraction
• Venting and isolation of equipment
R-012 Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation
Consequence : Tendinitis, carpal tunnel syndrome, sick leave
12 P4×I3 • Ergonomic analysis of repetitive tasks
• Job rotation
R-013 Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection
Consequence : Lacerations, tendon injuries
12 P4×I3 • Retractable-blade tools
• Suitable cut-resistant gloves
R-014 Discharge limits exceeded
Cause : Saturated treatment plant, process drift
Consequence : Formal notice, fine, administrative shutdown
12 P3×I4 • Self-monitoring and threshold alarms
• Output reduction procedure
R-015 Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks
Consequence : Remediation, use restrictions, dispute with the seller
12 P3×I4 • Historical and soil study before acquisition
• Environmental liability warranties
R-016 Alcohol or drug use at work
Cause : Celebrations, recreational use, addiction, no clear policy
Consequence : Serious accidents, dangerous behaviour
12 P3×I4 • Alcohol and drug policy
• Remove from dangerous tasks in case of doubt
R-017 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-018 Unplanned production stoppage
Cause : Critical equipment failure, no spare parts
Consequence : Late orders, operating losses
12 P3×I4 • Equipment criticality analysis
• Critical spare parts stock
R-019 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-020 Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation
Consequence : Systems down, data lost, ransom demanded
10 P2×I5 • Patching and endpoint protection
• Tested offline backups
R-021 Cyberattack on industrial control systems
Cause : Industrial network connected to office IT, uncontrolled maintenance access
Consequence : Production stopped or disrupted, safety hazard
10 P2×I5 • Industrial network segmentation
• Documented manual fallback mode
R-022 Product recall
Cause : Manufacturing defect, contamination, labelling error
Consequence : Withdrawal costs, loss of customers, brand damage
10 P2×I5 • Quality checks at critical steps
• Batch traceability and tested recall procedure
R-023 Failure of a bottleneck machine
Cause : Single machine without redundancy, insufficient preventive maintenance, unavailable parts
Consequence : Whole production stopped
9 P3×I3 • Enhanced preventive maintenance on bottlenecks
• Critical spare parts in stock
R-024 Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce
Consequence : Accidents in the first weeks
9 P3×I3 • Systematic safety induction
• Buddy system in the first weeks
R-025 Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision
Consequence : Critical path blocked, delay
9 P3×I3 • External dependency log
• Prepared workaround
R-026 Non-conforming product delivered
Cause : Process drift, insufficient inspections
Consequence : Claims, recalls, loss of customers
9 P3×I3 • Control plan and statistical monitoring
• Batch traceability
R-027 Raw material shortage
Cause : Tight markets, failing supplier
Consequence : Reduced production, higher costs
9 P3×I3 • Dual sourcing of critical materials
• Sized safety stock
R-028 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-029 Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords
Consequence : Physical or digital intrusion, sabotage, espionage
8 P2×I4 • Change default passwords and keep an inventory
• Separate network for connected devices
R-030 Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance
Consequence : Unpaid invoices, lost revenue, cash strain
8 P2×I4 • Monitor key customers’ financial health
• Credit insurance or payment guarantees
R-031 Bribery or conflict of interest
Cause : Unregulated gifts or benefits, opaque intermediaries, untraced purchasing decisions
Consequence : Criminal proceedings, exclusion from public tenders, reputational damage
8 P2×I4 • Code of conduct and gifts register
• Conflict-of-interest declarations and dual purchase approval
R-032 Failure to meet NIS2 obligations
Cause : Entity in scope not registered, missing risk-management measures, incidents not notified
Consequence : Fines, management liability, regulator inspection
8 P2×I4 • Scope check and registration
• Cybersecurity action plan tracked by management
R-033 Quality non-conformity found at the customer
Cause : Insufficient final checks, undetected process drift
Consequence : Complaints, returns, customer loss
8 P2×I4 • Statistical control of critical parameters
• Eight-step complaint handling
R-034 Hand-arm and whole-body vibration
Cause : Vibrating tools, machines on rough ground, long exposure
Consequence : Vascular and joint disorders, low back pain
6 P2×I3 • Low-vibration tools and suspended seats
• Limit exposure time

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Machine safety upgrade”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free