Risqure
Risqure › Risk register examples › New production line

Risk register example: New production line

Installing and commissioning a line: machinery, electrical work, supplier dependence and ramp-up.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate9
● High19
● Critical7

Assumptions: Industry / manufacturing · Execution / works · 25 people · machines or production equipment, electrical work or work near live installations, lifting operations (cranes, hoists), site in operation (co-activity with production), new technology or method, critical item from a single supplier, suppliers outside europe or long lead times, tight or immovable deadline, industrial control systems (automation, scada), subcontractors involved.

Ref.RiskScorePreventionProtection
R-001 Caught in or crushed by a machine
Cause : Guards removed, work without lockout, residual energy
Consequence : Amputation, crushing, fatality
25 P5×I5 • Lockout of all energy sources
• Guards and emergency stops checked
R-002 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
20 P4×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-003 Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan
Consequence : Serious accident, shared liability, site stoppage
20 P5×I4 • Prevention plan and joint inspection
• Daily coordination of work
R-004 Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer
Consequence : Rushed work, mistakes, penalties, lower quality
16 P4×I4 • Phased delivery
• Pre-identified extra resources
R-005 Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure
Consequence : Equipment energised or moving with a worker exposed
15 P3×I5 • Lockout procedure with personal padlocks
• Check before restart
R-006 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
15 P3×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-007 Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground
Consequence : Crushing, fatality, major damage
15 P3×I5 • Lifting plan for critical lifts
• Qualified operators and slingers, inspected gear
• No one under the load
R-008 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
12 P3×I4 • Isolate all energy sources
• Lockout sheets per machine
R-009 Modified or new machine not compliant
Cause : Guards removed, change without assessment, acceptance without checks
Consequence : Serious accident, employer liability, enforced shutdown
12 P3×I4 • Risk assessment before any modification
• Safety acceptance of new equipment
R-010 Defeating machine guards
Cause : Inconvenient guards, production pressure, bypassed interlocks
Consequence : Entanglement, amputation
12 P3×I4 • Guard audits and action on bypasses
• Ergonomic improvement of guards
R-011 Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source
Consequence : Explosion, fire, collapse
12 P3×I4 • Regular cleaning and dust extraction
• Venting and isolation of equipment
R-012 Load falling from an overhead crane
Cause : Worn slings, incorrect rigging, overload
Consequence : Crushing, material damage
12 P3×I4 • Check lifting accessories
• Train riggers and crane operators
R-013 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-014 Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier
Consequence : Production or site stoppage, delays, penalties
12 P3×I4 • Map tier-1 and tier-2 suppliers
• Safety stock for critical components
R-015 Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation
Consequence : Tendinitis, carpal tunnel syndrome, sick leave
12 P4×I3 • Ergonomic analysis of repetitive tasks
• Job rotation
R-016 Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection
Consequence : Lacerations, tendon injuries
12 P4×I3 • Retractable-blade tools
• Suitable cut-resistant gloves
R-017 Discharge limits exceeded
Cause : Saturated treatment plant, process drift
Consequence : Formal notice, fine, administrative shutdown
12 P3×I4 • Self-monitoring and threshold alarms
• Output reduction procedure
R-018 Alcohol or drug use at work
Cause : Celebrations, recreational use, addiction, no clear policy
Consequence : Serious accidents, dangerous behaviour
12 P3×I4 • Alcohol and drug policy
• Remove from dangerous tasks in case of doubt
R-019 Supply disruption of a critical item
Cause : Single supplier, no qualified alternative
Consequence : Work or production stopped while waiting for delivery
12 P3×I4 • Qualify a second supplier
• Safety stock
R-020 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-021 Unplanned production stoppage
Cause : Critical equipment failure, no spare parts
Consequence : Late orders, operating losses
12 P3×I4 • Equipment criticality analysis
• Critical spare parts stock
R-022 Adverse exchange rate movements
Cause : Purchases or sales in foreign currency, long delays between order and payment
Consequence : Reduced margin, unpredictable cost price
12 P3×I4 • Invoice in euros where possible
• Currency hedging for large amounts
R-023 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-024 Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks
Consequence : Remediation, use restrictions, dispute with the seller
12 P3×I4 • Historical and soil study before acquisition
• Environmental liability warranties
R-025 Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation
Consequence : Systems down, data lost, ransom demanded
10 P2×I5 • Patching and endpoint protection
• Tested offline backups
R-026 Cyberattack on industrial control systems
Cause : Industrial network connected to office IT, uncontrolled maintenance access
Consequence : Production stopped or disrupted, safety hazard
10 P2×I5 • Industrial network segmentation
• Documented manual fallback mode
R-027 Failure of a bottleneck machine
Cause : Single machine without redundancy, insufficient preventive maintenance, unavailable parts
Consequence : Whole production stopped
9 P3×I3 • Enhanced preventive maintenance on bottlenecks
• Critical spare parts in stock
R-028 Difficult start-up of a new production line
Cause : Long adjustments, lower yield, insufficient operator training
Consequence : Delayed production, scrap, late deliveries
9 P3×I3 • Acceptance tests and gradual ramp-up
• Buffer stock before start-up
R-029 Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers
Consequence : Extra costs, customs delays, closed markets
9 P3×I3 • Customs watch and product origin
• Alternative suppliers in other regions
R-030 Process change without management of change
Cause : Change of material, setting or equipment not assessed
Consequence : Accident, quality failure, non-compliance
8 P2×I4 • Management of change procedure
• Update documents and train
R-031 Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords
Consequence : Physical or digital intrusion, sabotage, espionage
8 P2×I4 • Change default passwords and keep an inventory
• Separate network for connected devices
R-032 Food fraud at a supplier
Cause : Ingredient substitution, false origin, dubious certificates
Consequence : Non-compliant product, image crisis, prosecution
8 P2×I4 • Food fraud vulnerability assessment
• Supplier audits and authenticity tests
R-033 Excessive reliance on external consultants
Cause : Key skills held by contractors, no knowledge transfer
Consequence : Loss of control, recurring costs, knowledge leaving
6 P2×I3 • Internal-external pairs
• Knowledge transfer deliverables
R-034 Shortage of critical raw materials or components
Cause : Geopolitical tension, concentrated production, global demand
Consequence : Delays, price rises, redesign
6 P2×I3 • Identify at-risk components
• Design allowing alternatives
R-035 Hand-arm and whole-body vibration
Cause : Vibrating tools, machines on rough ground, long exposure
Consequence : Vascular and joint disorders, low back pain
6 P2×I3 • Low-vibration tools and suspended seats
• Limit exposure time

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “New production line”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples