Risk register example: New production line
Installing and commissioning a line: machinery, electrical work, supplier dependence and ramp-up.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Industry / manufacturing · Execution / works · 25 people · machines or production equipment, electrical work or work near live installations, lifting operations (cranes, hoists), site in operation (co-activity with production), new technology or method, critical item from a single supplier, suppliers outside europe or long lead times, tight or immovable deadline, industrial control systems (automation, scada), subcontractors involved.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Caught in or crushed by a machine
Cause : Guards removed, work without lockout, residual energy Consequence : Amputation, crushing, fatality |
25 P5×I5 | • Lockout of all energy sources • Guards and emergency stops checked |
|
| R-002 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
20 P4×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-003 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
20 P5×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-004 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-005 | Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure Consequence : Equipment energised or moving with a worker exposed |
15 P3×I5 | • Lockout procedure with personal padlocks • Check before restart |
|
| R-006 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
15 P3×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-007 | Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground Consequence : Crushing, fatality, major damage |
15 P3×I5 | • Lifting plan for critical lifts • Qualified operators and slingers, inspected gear |
• No one under the load |
| R-008 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
12 P3×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-009 | Modified or new machine not compliant
Cause : Guards removed, change without assessment, acceptance without checks Consequence : Serious accident, employer liability, enforced shutdown |
12 P3×I4 | • Risk assessment before any modification • Safety acceptance of new equipment |
|
| R-010 | Defeating machine guards
Cause : Inconvenient guards, production pressure, bypassed interlocks Consequence : Entanglement, amputation |
12 P3×I4 | • Guard audits and action on bypasses • Ergonomic improvement of guards |
|
| R-011 | Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source Consequence : Explosion, fire, collapse |
12 P3×I4 | • Regular cleaning and dust extraction |
• Venting and isolation of equipment |
| R-012 | Load falling from an overhead crane
Cause : Worn slings, incorrect rigging, overload Consequence : Crushing, material damage |
12 P3×I4 | • Check lifting accessories • Train riggers and crane operators |
|
| R-013 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-014 | Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier Consequence : Production or site stoppage, delays, penalties |
12 P3×I4 | • Map tier-1 and tier-2 suppliers |
• Safety stock for critical components |
| R-015 | Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation Consequence : Tendinitis, carpal tunnel syndrome, sick leave |
12 P4×I3 | • Ergonomic analysis of repetitive tasks • Job rotation |
|
| R-016 | Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection Consequence : Lacerations, tendon injuries |
12 P4×I3 | • Retractable-blade tools |
• Suitable cut-resistant gloves |
| R-017 | Discharge limits exceeded
Cause : Saturated treatment plant, process drift Consequence : Formal notice, fine, administrative shutdown |
12 P3×I4 | • Self-monitoring and threshold alarms |
• Output reduction procedure |
| R-018 | Alcohol or drug use at work
Cause : Celebrations, recreational use, addiction, no clear policy Consequence : Serious accidents, dangerous behaviour |
12 P3×I4 | • Alcohol and drug policy |
• Remove from dangerous tasks in case of doubt |
| R-019 | Supply disruption of a critical item
Cause : Single supplier, no qualified alternative Consequence : Work or production stopped while waiting for delivery |
12 P3×I4 | • Qualify a second supplier |
• Safety stock |
| R-020 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-021 | Unplanned production stoppage
Cause : Critical equipment failure, no spare parts Consequence : Late orders, operating losses |
12 P3×I4 | • Equipment criticality analysis |
• Critical spare parts stock |
| R-022 | Adverse exchange rate movements
Cause : Purchases or sales in foreign currency, long delays between order and payment Consequence : Reduced margin, unpredictable cost price |
12 P3×I4 | • Invoice in euros where possible |
• Currency hedging for large amounts |
| R-023 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-024 | Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks Consequence : Remediation, use restrictions, dispute with the seller |
12 P3×I4 | • Historical and soil study before acquisition |
• Environmental liability warranties |
| R-025 | Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation Consequence : Systems down, data lost, ransom demanded |
10 P2×I5 | • Patching and endpoint protection |
• Tested offline backups |
| R-026 | Cyberattack on industrial control systems
Cause : Industrial network connected to office IT, uncontrolled maintenance access Consequence : Production stopped or disrupted, safety hazard |
10 P2×I5 | • Industrial network segmentation |
• Documented manual fallback mode |
| R-027 | Failure of a bottleneck machine
Cause : Single machine without redundancy, insufficient preventive maintenance, unavailable parts Consequence : Whole production stopped |
9 P3×I3 | • Enhanced preventive maintenance on bottlenecks |
• Critical spare parts in stock |
| R-028 | Difficult start-up of a new production line
Cause : Long adjustments, lower yield, insufficient operator training Consequence : Delayed production, scrap, late deliveries |
9 P3×I3 | • Acceptance tests and gradual ramp-up |
• Buffer stock before start-up |
| R-029 | Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers Consequence : Extra costs, customs delays, closed markets |
9 P3×I3 | • Customs watch and product origin |
• Alternative suppliers in other regions |
| R-030 | Process change without management of change
Cause : Change of material, setting or equipment not assessed Consequence : Accident, quality failure, non-compliance |
8 P2×I4 | • Management of change procedure • Update documents and train |
|
| R-031 | Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords Consequence : Physical or digital intrusion, sabotage, espionage |
8 P2×I4 | • Change default passwords and keep an inventory • Separate network for connected devices |
|
| R-032 | Food fraud at a supplier
Cause : Ingredient substitution, false origin, dubious certificates Consequence : Non-compliant product, image crisis, prosecution |
8 P2×I4 | • Food fraud vulnerability assessment • Supplier audits and authenticity tests |
|
| R-033 | Excessive reliance on external consultants
Cause : Key skills held by contractors, no knowledge transfer Consequence : Loss of control, recurring costs, knowledge leaving |
6 P2×I3 | • Internal-external pairs |
• Knowledge transfer deliverables |
| R-034 | Shortage of critical raw materials or components
Cause : Geopolitical tension, concentrated production, global demand Consequence : Delays, price rises, redesign |
6 P2×I3 | • Identify at-risk components |
• Design allowing alternatives |
| R-035 | Hand-arm and whole-body vibration
Cause : Vibrating tools, machines on rough ground, long exposure Consequence : Vascular and joint disorders, low back pain |
6 P2×I3 | • Low-vibration tools and suspended seats • Limit exposure time |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.