Risk register example: Lift modernisation

Modernising a lift in an occupied building: falls into the shaft, lifting, electricity and residents.

Adapt it to my project (free) Download for Excel (CSV)

Risks28
● Low0
● Moderate15
● High3
● Critical10

Assumptions: Maintenance / facilities · Execution / works · 4 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), electrical work or work near live installations, occupied site (staff, residents, patients nearby), vulnerable people (patients, children, elderly), confined spaces (tanks, pits, sewers).

Ref.RiskScorePreventionProtection
R-001 Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground
Consequence : Crushing, fatality, major damage
20 P4×I5 • Lifting plan for critical lifts
• Qualified operators and slingers, inspected gear
• No one under the load
R-002 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
20 P4×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-003 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
20 P4×I5 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-004 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
16 P4×I4 • Mobile platforms instead of ladders
• Visual check before use
R-005 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
16 P4×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-006 Vulnerable people exposed to hazards
Cause : Patients, children or elderly people near the activity area
Consequence : Serious accident, complaint, facility closure
16 P4×I4 • Joint risk assessment with the facility
• On-site contact and alert procedure
R-007 Accident during an urgent breakdown repair
Cause : Pressure to restart quickly, risk assessment skipped
Consequence : Serious injury, worse breakdown
16 P4×I4 • Quick risk check before each repair
• Stop-work authority backed by management
R-008 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-009 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-010 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
15 P3×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-011 Accident during work on a plant roof
Cause : Roof equipment without safe access, no guardrails
Consequence : Fall from height
12 P3×I4 • Permanent safe access and walkways
• Roof access permit
R-012 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
12 P3×I4 • Isolate all energy sources
• Lockout sheets per machine
R-013 Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections
Consequence : People trapped, car fall, accident
12 P3×I4 • Maintenance contract and periodic inspections
• Emergency phone and rescue procedure
R-014 Poorly defined maintenance contracts
Cause : Unclear scope, response times not set, no indicators
Consequence : Faults left unresolved, disputes with the provider
9 P3×I3 • Specifications with service levels
• Quarterly KPI review
R-015 Unanticipated ageing of installations
Cause : No multi-year replacement plan
Consequence : Repeated failures, urgent unbudgeted investments
9 P3×I3 • Multi-year investment plan
• Emergency budget
R-016 Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking
Consequence : Complaints, imposed working-hour restrictions, delay
9 P3×I3 • Neighbour information and dedicated contact
• Dust control and suitable hours
R-017 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-018 Breakdown of a critical building system
Cause : Heating, ventilation, lifts or generator without preventive maintenance
Consequence : Discomfort or interruption for occupants, costly emergency call-outs
9 P3×I3 • Preventive maintenance plan by criticality
• Rapid response contract and critical spares
R-019 Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements
Consequence : Complaints, enforced stoppage, fines
9 P3×I3 • Quieter equipment and acoustic screens
• Noise measurements and adapted hours
R-020 Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations
Consequence : Stress, verbal aggression, staff burnout
9 P3×I3 • Conflict-management training
• Post-incident support and reporting
R-021 Excessive dependence on the manager or owner
Cause : Decisions, customer relations and know-how concentrated in one person
Consequence : Paralysis in case of absence, loss of company value
9 P3×I3 • Delegations and named deputy
• Key person insurance
R-022 Backup power failure
Cause : Generator or UPS not tested, insufficient fuel
Consequence : Vital equipment stops during a power cut
8 P2×I4 • Regular load tests
• Fuel reserve and supply contract
R-023 Missed statutory periodic inspections
Cause : Deadlines not tracked (lifts, electrical, fire, lifting)
Consequence : Non-compliance, liability in case of accident, insurance refusal
8 P2×I4 • Statutory inspection calendar
• Track closure of findings
R-024 Legionnaires’ disease from water systems
Cause : Stagnant or lukewarm water in pipework, poorly maintained cooling towers
Consequence : Cases of Legionnaires’ disease among occupants, operator liability
8 P2×I4 • Water system management plan
• Procedure in case of positive results
R-025 Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response
Consequence : Loss of trust, lost customers, pressure from authorities
8 P2×I4 • Crisis communication procedure
• Quick-reaction sheet and press contacts
R-026 Exposure to biological agents
Cause : Contact with sick people, waste, animals or contaminated water
Consequence : Infections, absences
6 P2×I3 • Hand hygiene and recommended vaccination
• Protective equipment and exposure procedure
R-027 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan
R-028 Prolonged sitting and screen work
Cause : Poorly adjusted workstations, few breaks, full days at a screen
Consequence : Back and neck pain, eye strain
6 P3×I2 • Ergonomic workstation set-up
• Active breaks and task variation

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Lift modernisation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples