Risk register example: HVAC installation or maintenance

Heating, ventilation and air conditioning works: roofs, refrigerants, electricity and occupied buildings.

Adapt it to my project (free) Download for Excel (CSV)

Risks31
● Low0
● Moderate22
● High8
● Critical1

Assumptions: Maintenance / facilities · Operation · 6 people · work at height (roofs, scaffolding, platforms), electrical work or work near live installations, pressure systems, gas, steam, hazardous chemicals, occupied site (staff, residents, patients nearby), lone work, hot work (welding, cutting, grinding).

Ref.RiskScorePreventionProtection
R-001 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
15 P3×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-002 Risks for cleaning staff
Cause : Mixed products, early or late hours, lone work, repetitive movements
Consequence : Poisoning, MSDs, assaults
12 P3×I4 • Ready-to-use products and no mixing
• Ergonomic equipment and daytime cleaning
R-003 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
12 P4×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-004 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
12 P3×I4 • Mobile platforms instead of ladders
• Visual check before use
R-005 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
12 P3×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-006 Exposure to hazardous chemicals
Cause : Safety data sheets unknown, unsuitable ventilation and PPE
Consequence : Poisoning, burns, occupational disease
12 P3×I4 • Substitute with a less hazardous product
• Inventory, safety data sheets and training
• Eyewash and emergency kit
R-007 Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure
Consequence : Equipment energised or moving with a worker exposed
10 P2×I5 • Lockout procedure with personal padlocks
• Check before restart
R-008 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
10 P2×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-009 Explosion or leak of pressure equipment or gas
Cause : Uninspected equipment, faulty fittings, mishandling
Consequence : Burns, serious injuries, fire
10 P2×I5 • Statutory inspections and maintenance
• Gas detection and emergency procedure
R-010 Poorly defined maintenance contracts
Cause : Unclear scope, response times not set, no indicators
Consequence : Faults left unresolved, disputes with the provider
9 P3×I3 • Specifications with service levels
• Quarterly KPI review
R-011 Unanticipated ageing of installations
Cause : No multi-year replacement plan
Consequence : Repeated failures, urgent unbudgeted investments
9 P3×I3 • Multi-year investment plan
• Emergency budget
R-012 Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking
Consequence : Complaints, imposed working-hour restrictions, delay
9 P3×I3 • Neighbour information and dedicated contact
• Dust control and suitable hours
R-013 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-014 Breakdown of a critical building system
Cause : Heating, ventilation, lifts or generator without preventive maintenance
Consequence : Discomfort or interruption for occupants, costly emergency call-outs
9 P3×I3 • Preventive maintenance plan by criticality
• Rapid response contract and critical spares
R-015 Accident during work on a plant roof
Cause : Roof equipment without safe access, no guardrails
Consequence : Fall from height
8 P2×I4 • Permanent safe access and walkways
• Roof access permit
R-016 Leak of a hazardous product or gas
Cause : Faulty seal, corrosion, handling error during transfer
Consequence : Poisoning, fire, pollution
8 P2×I4 • Inspect transfer and storage equipment
• Bunding, detectors and spill kits
R-017 Burn from hot fluid or corrosive product
Cause : Opening a pressurised or hot circuit, splash, no PPE
Consequence : Serious burns, eye injury
8 P2×I4 • Drain, cool and depressurise before opening
• Face shield, gloves and safety shower
R-018 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
8 P2×I4 • Isolate all energy sources
• Lockout sheets per machine
R-019 Assault on a security guard
Cause : Lone interventions, night patrols, intrusions
Consequence : Injuries, trauma
8 P2×I4 • Intervention rules and remote verification
• Lone-worker alert device
R-020 Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections
Consequence : People trapped, car fall, accident
8 P2×I4 • Maintenance contract and periodic inspections
• Emergency phone and rescue procedure
R-021 Missed statutory periodic inspections
Cause : Deadlines not tracked (lifts, electrical, fire, lifting)
Consequence : Non-compliance, liability in case of accident, insurance refusal
8 P2×I4 • Statutory inspection calendar
• Track closure of findings
R-022 Legionnaires’ disease from water systems
Cause : Stagnant or lukewarm water in pipework, poorly maintained cooling towers
Consequence : Cases of Legionnaires’ disease among occupants, operator liability
8 P2×I4 • Water system management plan
• Procedure in case of positive results
R-023 Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks
Consequence : Remediation, use restrictions, dispute with the seller
8 P2×I4 • Historical and soil study before acquisition
• Environmental liability warranties
R-024 Refrigerant leak
Cause : Poorly maintained air-conditioning or refrigeration systems
Consequence : Environmental harm, non-compliance, breakdown
6 P2×I3 • Statutory leak checks
• Service log and refrigerant recovery
R-025 Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability
Consequence : Fines, producer liability, damaged image
6 P3×I2 • Sorting at source and approved contractors
• Waste register and transfer notes
R-026 Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements
Consequence : Complaints, enforced stoppage, fines
6 P2×I3 • Quieter equipment and acoustic screens
• Noise measurements and adapted hours
R-027 Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose
Consequence : Soil and water pollution, costly clean-up
6 P2×I3 • Sealed refuelling area
• Spill kit and response procedure
R-028 Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register
Consequence : Fines, liability for fly-tipping
6 P2×I3 • Separate skips and signage
• Register and transfer notes kept
R-029 Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction
Consequence : Respiratory diseases, irritation
6 P2×I3 • Local extraction and wet methods
• Suitable respiratory protection
R-030 Occupational skin disease
Cause : Repeated contact with water, detergents, cement or solvents
Consequence : Eczema, skin allergies, unfitness for work
6 P2×I3 • Substitute irritating products
• Suitable gloves and skin care
R-031 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “HVAC installation or maintenance”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free