Risqure
Risqure › Risk register examples › Electrical installation upgrade

Risk register example: Electrical installation upgrade

Bringing an installation up to code: live work, switching, power cuts and inspection.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate19
● High10
● Critical6

Assumptions: Maintenance / facilities · Execution / works · 8 people · electrical work or work near live installations, occupied site (staff, residents, patients nearby), site in operation (co-activity with production), work at height (roofs, scaffolding, platforms), lone work, subcontractors involved.

Ref.RiskScorePreventionProtection
R-001 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
20 P4×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-002 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
16 P4×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-003 Interference between work and ongoing operations
Cause : Unexpected start-up of installations, production flows not stopped
Consequence : Accident, production stoppage, damage
16 P4×I4 • Work permit issued by the operator
• Direct link with the control room
R-004 Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure
Consequence : Equipment energised or moving with a worker exposed
15 P3×I5 • Lockout procedure with personal padlocks
• Check before restart
R-005 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
15 P5×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-006 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
15 P3×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-007 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
12 P3×I4 • Isolate all energy sources
• Lockout sheets per machine
R-008 Accident during work on a plant roof
Cause : Roof equipment without safe access, no guardrails
Consequence : Fall from height
12 P3×I4 • Permanent safe access and walkways
• Roof access permit
R-009 Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections
Consequence : People trapped, car fall, accident
12 P3×I4 • Maintenance contract and periodic inspections
• Emergency phone and rescue procedure
R-010 Risks for cleaning staff
Cause : Mixed products, early or late hours, lone work, repetitive movements
Consequence : Poisoning, MSDs, assaults
12 P3×I4 • Ready-to-use products and no mixing
• Ergonomic equipment and daytime cleaning
R-011 Assault on a security guard
Cause : Lone interventions, night patrols, intrusions
Consequence : Injuries, trauma
12 P3×I4 • Intervention rules and remote verification
• Lone-worker alert device
R-012 Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks
Consequence : Remediation, use restrictions, dispute with the seller
12 P3×I4 • Historical and soil study before acquisition
• Environmental liability warranties
R-013 Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads
Consequence : Sprains, fractures
12 P3×I4 • Anti-slip nosings and handrails
• Hoists or trolleys for loads
R-014 Poorly prepared emergency evacuation
Cause : Blocked exits, inaudible alarm, no drills, people with reduced mobility forgotten
Consequence : Casualties during a fire or leak
12 P3×I4 • Annual evacuation drill
• Appointed evacuation wardens
R-015 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-016 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-017 Poorly defined maintenance contracts
Cause : Unclear scope, response times not set, no indicators
Consequence : Faults left unresolved, disputes with the provider
9 P3×I3 • Specifications with service levels
• Quarterly KPI review
R-018 Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking
Consequence : Complaints, imposed working-hour restrictions, delay
9 P3×I3 • Neighbour information and dedicated contact
• Dust control and suitable hours
R-019 Unanticipated ageing of installations
Cause : No multi-year replacement plan
Consequence : Repeated failures, urgent unbudgeted investments
9 P3×I3 • Multi-year investment plan
• Emergency budget
R-020 Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements
Consequence : Complaints, enforced stoppage, fines
9 P3×I3 • Quieter equipment and acoustic screens
• Noise measurements and adapted hours
R-021 Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture
Consequence : Bruises, cuts, falls
9 P3×I3 • Daily tidy-up and defined storage areas
• Regular safety walks
R-022 Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce
Consequence : Accidents in the first weeks
9 P3×I3 • Systematic safety induction
• Buddy system in the first weeks
R-023 Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision
Consequence : Critical path blocked, delay
9 P3×I3 • External dependency log
• Prepared workaround
R-024 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-025 Breakdown of a critical building system
Cause : Heating, ventilation, lifts or generator without preventive maintenance
Consequence : Discomfort or interruption for occupants, costly emergency call-outs
9 P3×I3 • Preventive maintenance plan by criticality
• Rapid response contract and critical spares
R-026 Missed statutory periodic inspections
Cause : Deadlines not tracked (lifts, electrical, fire, lifting)
Consequence : Non-compliance, liability in case of accident, insurance refusal
8 P2×I4 • Statutory inspection calendar
• Track closure of findings
R-027 Legionnaires’ disease from water systems
Cause : Stagnant or lukewarm water in pipework, poorly maintained cooling towers
Consequence : Cases of Legionnaires’ disease among occupants, operator liability
8 P2×I4 • Water system management plan
• Procedure in case of positive results
R-028 Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords
Consequence : Physical or digital intrusion, sabotage, espionage
8 P2×I4 • Change default passwords and keep an inventory
• Separate network for connected devices
R-029 Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance
Consequence : Unpaid invoices, lost revenue, cash strain
8 P2×I4 • Monitor key customers’ financial health
• Credit insurance or payment guarantees
R-030 Bribery or conflict of interest
Cause : Unregulated gifts or benefits, opaque intermediaries, untraced purchasing decisions
Consequence : Criminal proceedings, exclusion from public tenders, reputational damage
8 P2×I4 • Code of conduct and gifts register
• Conflict-of-interest declarations and dual purchase approval
R-031 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan
R-032 Non-compliant subcontracting
Cause : Undeclared subcontractor, posted workers without formalities, missing insurance
Consequence : Joint liability, fines, site stoppage
6 P2×I3 • Document checks on subcontractors
• Prior approval of all subcontracting
R-033 Poorly drafted or incomplete contract
Cause : Unclear liabilities, deadlines, acceptance or penalties, no legal review
Consequence : Disputes, unpaid work, excessive liability
6 P2×I3 • Checklist of essential clauses
• Legal review of major contracts
R-034 Excessive reliance on external consultants
Cause : Key skills held by contractors, no knowledge transfer
Consequence : Loss of control, recurring costs, knowledge leaving
6 P2×I3 • Internal-external pairs
• Knowledge transfer deliverables
R-035 No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified
Consequence : Avoidable accidents, non-compliance on inspection
6 P2×I3 • Annual review and after every change
• Worker participation

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Electrical installation upgrade”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples