Risk register example: Electrical installation upgrade
Bringing an installation up to code: live work, switching, power cuts and inspection.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Maintenance / facilities · Execution / works · 8 people · electrical work or work near live installations, occupied site (staff, residents, patients nearby), site in operation (co-activity with production), work at height (roofs, scaffolding, platforms), lone work, subcontractors involved.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
20 P4×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-002 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
16 P4×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-003 | Interference between work and ongoing operations
Cause : Unexpected start-up of installations, production flows not stopped Consequence : Accident, production stoppage, damage |
16 P4×I4 | • Work permit issued by the operator |
• Direct link with the control room |
| R-004 | Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure Consequence : Equipment energised or moving with a worker exposed |
15 P3×I5 | • Lockout procedure with personal padlocks • Check before restart |
|
| R-005 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-006 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-007 | Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting Consequence : Crushing, electric shock, entanglement |
12 P3×I4 | • Isolate all energy sources • Lockout sheets per machine |
|
| R-008 | Accident during work on a plant roof
Cause : Roof equipment without safe access, no guardrails Consequence : Fall from height |
12 P3×I4 | • Permanent safe access and walkways • Roof access permit |
|
| R-009 | Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections Consequence : People trapped, car fall, accident |
12 P3×I4 | • Maintenance contract and periodic inspections |
• Emergency phone and rescue procedure |
| R-010 | Risks for cleaning staff
Cause : Mixed products, early or late hours, lone work, repetitive movements Consequence : Poisoning, MSDs, assaults |
12 P3×I4 | • Ready-to-use products and no mixing • Ergonomic equipment and daytime cleaning |
|
| R-011 | Assault on a security guard
Cause : Lone interventions, night patrols, intrusions Consequence : Injuries, trauma |
12 P3×I4 | • Intervention rules and remote verification |
• Lone-worker alert device |
| R-012 | Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks Consequence : Remediation, use restrictions, dispute with the seller |
12 P3×I4 | • Historical and soil study before acquisition |
• Environmental liability warranties |
| R-013 | Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads Consequence : Sprains, fractures |
12 P3×I4 | • Anti-slip nosings and handrails • Hoists or trolleys for loads |
|
| R-014 | Poorly prepared emergency evacuation
Cause : Blocked exits, inaudible alarm, no drills, people with reduced mobility forgotten Consequence : Casualties during a fire or leak |
12 P3×I4 | • Annual evacuation drill |
• Appointed evacuation wardens |
| R-015 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-016 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-017 | Poorly defined maintenance contracts
Cause : Unclear scope, response times not set, no indicators Consequence : Faults left unresolved, disputes with the provider |
9 P3×I3 | • Specifications with service levels |
• Quarterly KPI review |
| R-018 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
9 P3×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-019 | Unanticipated ageing of installations
Cause : No multi-year replacement plan Consequence : Repeated failures, urgent unbudgeted investments |
9 P3×I3 | • Multi-year investment plan |
• Emergency budget |
| R-020 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-021 | Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture Consequence : Bruises, cuts, falls |
9 P3×I3 | • Daily tidy-up and defined storage areas • Regular safety walks |
|
| R-022 | Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce Consequence : Accidents in the first weeks |
9 P3×I3 | • Systematic safety induction • Buddy system in the first weeks |
|
| R-023 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
9 P3×I3 | • External dependency log |
• Prepared workaround |
| R-024 | Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in Consequence : Slow diagnosis, poor decisions, repeated interventions |
9 P3×I3 | • Systematic work order close-out |
• Update drawings after changes |
| R-025 | Breakdown of a critical building system
Cause : Heating, ventilation, lifts or generator without preventive maintenance Consequence : Discomfort or interruption for occupants, costly emergency call-outs |
9 P3×I3 | • Preventive maintenance plan by criticality |
• Rapid response contract and critical spares |
| R-026 | Missed statutory periodic inspections
Cause : Deadlines not tracked (lifts, electrical, fire, lifting) Consequence : Non-compliance, liability in case of accident, insurance refusal |
8 P2×I4 | • Statutory inspection calendar |
• Track closure of findings |
| R-027 | Legionnaires’ disease from water systems
Cause : Stagnant or lukewarm water in pipework, poorly maintained cooling towers Consequence : Cases of Legionnaires’ disease among occupants, operator liability |
8 P2×I4 | • Water system management plan |
• Procedure in case of positive results |
| R-028 | Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords Consequence : Physical or digital intrusion, sabotage, espionage |
8 P2×I4 | • Change default passwords and keep an inventory • Separate network for connected devices |
|
| R-029 | Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance Consequence : Unpaid invoices, lost revenue, cash strain |
8 P2×I4 | • Monitor key customers’ financial health |
• Credit insurance or payment guarantees |
| R-030 | Bribery or conflict of interest
Cause : Unregulated gifts or benefits, opaque intermediaries, untraced purchasing decisions Consequence : Criminal proceedings, exclusion from public tenders, reputational damage |
8 P2×I4 | • Code of conduct and gifts register • Conflict-of-interest declarations and dual purchase approval |
|
| R-031 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
| R-032 | Non-compliant subcontracting
Cause : Undeclared subcontractor, posted workers without formalities, missing insurance Consequence : Joint liability, fines, site stoppage |
6 P2×I3 | • Document checks on subcontractors • Prior approval of all subcontracting |
|
| R-033 | Poorly drafted or incomplete contract
Cause : Unclear liabilities, deadlines, acceptance or penalties, no legal review Consequence : Disputes, unpaid work, excessive liability |
6 P2×I3 | • Checklist of essential clauses • Legal review of major contracts |
|
| R-034 | Excessive reliance on external consultants
Cause : Key skills held by contractors, no knowledge transfer Consequence : Loss of control, recurring costs, knowledge leaving |
6 P2×I3 | • Internal-external pairs |
• Knowledge transfer deliverables |
| R-035 | No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified Consequence : Avoidable accidents, non-compliance on inspection |
6 P2×I3 | • Annual review and after every change • Worker participation |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Electrical installation upgrade”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.