Risk register example: Industrial cleaning

Cleaning tanks, silos or production areas: chemicals, confined spaces, night work and co-activity.

Adapt it to my project (free) Download for Excel (CSV)

Risks32
● Low0
● Moderate22
● High8
● Critical2

Assumptions: Maintenance / facilities · Operation · 10 people · hazardous chemicals, confined spaces (tanks, pits, sewers), work at height (roofs, scaffolding, platforms), night or shift work, site in operation (co-activity with production), lone work, pressure systems, gas, steam.

Ref.RiskScorePreventionProtection
R-001 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
15 P3×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-002 Electric shock or electrocution
Cause : Work near live parts, incomplete isolation
Consequence : Severe burns, death, fire
15 P3×I5 • Electrical isolation and voltage check
• Up-to-date electrical authorisations
R-003 Risks for cleaning staff
Cause : Mixed products, early or late hours, lone work, repetitive movements
Consequence : Poisoning, MSDs, assaults
12 P3×I4 • Ready-to-use products and no mixing
• Ergonomic equipment and daytime cleaning
R-004 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
12 P3×I4 • Mobile platforms instead of ladders
• Visual check before use
R-005 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
12 P3×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-006 Exposure to hazardous chemicals
Cause : Safety data sheets unknown, unsuitable ventilation and PPE
Consequence : Poisoning, burns, occupational disease
12 P3×I4 • Substitute with a less hazardous product
• Inventory, safety data sheets and training
• Eyewash and emergency kit
R-007 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-008 Interference between work and ongoing operations
Cause : Unexpected start-up of installations, production flows not stopped
Consequence : Accident, production stoppage, damage
12 P3×I4 • Work permit issued by the operator
• Direct link with the control room
R-009 Restart while lockout not properly removed
Cause : Incomplete lockout, poor communication between teams, restart pressure
Consequence : Equipment energised or moving with a worker exposed
10 P2×I5 • Lockout procedure with personal padlocks
• Check before restart
R-010 Asphyxiation or poisoning in a confined space
Cause : Atmosphere not tested, no ventilation, no attendant
Consequence : Death of the worker and often of the improvised rescuer
10 P2×I5 • Entry permit and continuous gas monitoring
• Outside attendant and rescue equipment
R-011 Unanticipated ageing of installations
Cause : No multi-year replacement plan
Consequence : Repeated failures, urgent unbudgeted investments
9 P3×I3 • Multi-year investment plan
• Emergency budget
R-012 Fatigue and reduced alertness from night work
Cause : Shifted hours, insufficient sleep, poor lighting
Consequence : Mistakes, accidents, health problems
9 P3×I3 • Shift and break planning
• Adequate lighting everywhere
R-013 Incomplete equipment history and drawings
Cause : Documentation not updated, maintenance software poorly filled in
Consequence : Slow diagnosis, poor decisions, repeated interventions
9 P3×I3 • Systematic work order close-out
• Update drawings after changes
R-014 Breakdown of a critical building system
Cause : Heating, ventilation, lifts or generator without preventive maintenance
Consequence : Discomfort or interruption for occupants, costly emergency call-outs
9 P3×I3 • Preventive maintenance plan by criticality
• Rapid response contract and critical spares
R-015 Leak of a hazardous product or gas
Cause : Faulty seal, corrosion, handling error during transfer
Consequence : Poisoning, fire, pollution
8 P2×I4 • Inspect transfer and storage equipment
• Bunding, detectors and spill kits
R-016 Burn from hot fluid or corrosive product
Cause : Opening a pressurised or hot circuit, splash, no PPE
Consequence : Serious burns, eye injury
8 P2×I4 • Drain, cool and depressurise before opening
• Face shield, gloves and safety shower
R-017 Assault on a security guard
Cause : Lone interventions, night patrols, intrusions
Consequence : Injuries, trauma
8 P2×I4 • Intervention rules and remote verification
• Lone-worker alert device
R-018 Accident during work on a plant roof
Cause : Roof equipment without safe access, no guardrails
Consequence : Fall from height
8 P2×I4 • Permanent safe access and walkways
• Roof access permit
R-019 Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks
Consequence : Remediation, use restrictions, dispute with the seller
8 P2×I4 • Historical and soil study before acquisition
• Environmental liability warranties
R-020 Unexpected start-up during maintenance
Cause : Residual energy, remote control, controller restarting
Consequence : Crushing, electric shock, entanglement
8 P2×I4 • Isolate all energy sources
• Lockout sheets per machine
R-021 Missed statutory periodic inspections
Cause : Deadlines not tracked (lifts, electrical, fire, lifting)
Consequence : Non-compliance, liability in case of accident, insurance refusal
8 P2×I4 • Statutory inspection calendar
• Track closure of findings
R-022 Legionnaires’ disease from water systems
Cause : Stagnant or lukewarm water in pipework, poorly maintained cooling towers
Consequence : Cases of Legionnaires’ disease among occupants, operator liability
8 P2×I4 • Water system management plan
• Procedure in case of positive results
R-023 Takeover of connected devices
Cause : Cameras, badge readers, sensors or controllers with default passwords
Consequence : Physical or digital intrusion, sabotage, espionage
8 P2×I4 • Change default passwords and keep an inventory
• Separate network for connected devices
R-024 Refrigerant leak
Cause : Poorly maintained air-conditioning or refrigeration systems
Consequence : Environmental harm, non-compliance, breakdown
6 P2×I3 • Statutory leak checks
• Service log and refrigerant recovery
R-025 Assault on a lone or night worker
Cause : Working alone in the evening or at night, handling valuables, isolated areas
Consequence : Injuries, trauma
6 P2×I3 • Lighting, access control and closing procedure
• Lone-worker alarm device
R-026 Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability
Consequence : Fines, producer liability, damaged image
6 P3×I2 • Sorting at source and approved contractors
• Waste register and transfer notes
R-027 Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose
Consequence : Soil and water pollution, costly clean-up
6 P2×I3 • Sealed refuelling area
• Spill kit and response procedure
R-028 Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register
Consequence : Fines, liability for fly-tipping
6 P2×I3 • Separate skips and signage
• Register and transfer notes kept
R-029 Exposure to dust and fumes
Cause : Cutting, sanding, welding or dry sweeping without extraction
Consequence : Respiratory diseases, irritation
6 P2×I3 • Local extraction and wet methods
• Suitable respiratory protection
R-030 Occupational skin disease
Cause : Repeated contact with water, detergents, cement or solvents
Consequence : Eczema, skin allergies, unfitness for work
6 P2×I3 • Substitute irritating products
• Suitable gloves and skin care
R-031 Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements
Consequence : Complaints, enforced stoppage, fines
6 P2×I3 • Quieter equipment and acoustic screens
• Noise measurements and adapted hours
R-032 Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted
Consequence : Harm to mother or child, non-compliance
6 P2×I3 • Specific assessment once pregnancy is announced
• List of at-risk jobs prepared in advance

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Industrial cleaning”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free