Risk register example: Migration to the cloud

Moving systems to the cloud: data migration, security, vendor lock-in, costs and downtime.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate26
● High8
● Critical1

Assumptions: IT / digital project · Planning / design · 8 people · cloud or saas services, data migration, integration with existing systems, service must be available 24/7, personal data processed, critical item from a single supplier, remote access or remote work.

Ref.RiskScorePreventionProtection
R-001 Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory
Consequence : Intrusion, data theft, service outage
16 P4×I4 • Inventory of exposed assets and priority patching
• Regular vulnerability scanning
R-002 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-003 Difficult integration with existing systems
Cause : Poorly documented interfaces, inconsistent data formats
Consequence : Delays, degraded features, double data entry
12 P3×I4 • Early interface inventory and tests
• Manual workaround
R-004 Security vulnerability in the application
Cause : No code review or security testing, outdated dependencies
Consequence : Intrusion, data leak, reputational damage
12 P3×I4 • Code review and automated scanning
• Penetration test before go-live
R-005 Supply disruption of a critical item
Cause : Single supplier, no qualified alternative
Consequence : Work or production stopped while waiting for delivery
12 P3×I4 • Qualify a second supplier
• Safety stock
R-006 GDPR non-compliance
Cause : Personal data processed without legal basis, record or information of data subjects
Consequence : Data protection authority fine, complaints
12 P3×I4 • Record of processing and impact assessment
• Data minimisation and retention periods
R-007 Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier
Consequence : Production or site stoppage, delays, penalties
12 P3×I4 • Map tier-1 and tier-2 suppliers
• Safety stock for critical components
R-008 Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation
Consequence : Systems down, data lost, ransom demanded
10 P2×I5 • Patching and endpoint protection
• Tested offline backups
R-009 Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration
Consequence : Mandatory notification, loss of trust, fines, claims
10 P2×I5 • Least-privilege access management
• Breach notification procedure
R-010 Account takeover without multi-factor authentication
Cause : Reused or stolen password, email and online tools protected by a single factor
Consequence : Impersonation, data access, fraud sent from a legitimate account
9 P3×I3 • Mandatory multi-factor authentication
• Alerts on unusual sign-ins
R-011 Backups that cannot be restored
Cause : Backups never tested, incomplete or encrypted by the attacker
Consequence : Permanent data loss after an incident
9 P3×I3 • Quarterly restore test
• Offline or immutable copy
R-012 Cloud subscription and hosting cost drift
Cause : Oversized resources, unused licences, price increases
Consequence : Operating budget overrun
9 P3×I3 • Monthly cost and licence review
• Budget alerts
R-013 Accumulated technical debt
Cause : Development shortcuts, no automated tests, missing documentation
Consequence : Slow changes, frequent bugs, high maintenance costs
9 P3×I3 • Automated tests and code review
• Time reserved for paying down debt
R-014 Loss or theft of a laptop or phone
Cause : Unencrypted devices, data stored locally, frequent travel
Consequence : Data leak, mandatory notification, lost work
9 P3×I3 • Encrypt portable devices
• Remote wipe and central backup
R-015 Data leak through human error
Cause : Wrong recipient, wrong attachment, overly open sharing link
Consequence : Data breach to notify, loss of trust
9 P3×I3 • Short, repeated awareness sessions
• Send delay and external-recipient warning
R-016 Incomplete or incorrect data migration
Cause : Inconsistent source data, poorly defined transformation rules
Consequence : Errors in production, loss of user trust
9 P3×I3 • Data cleansing and dry runs
• Reconciliation checks and rollback
R-017 Low user adoption
Cause : Users not involved, insufficient training
Consequence : Return to old tools, benefits not achieved
9 P3×I3 • Key users involved from design
• Training and go-live support
R-018 Risky go-live
Cause : Big-bang cutover, no rollback plan
Consequence : Service interruption, inconsistent data
9 P3×I3 • Cutover rehearsal
• Tested rollback plan
R-019 Excessive dependence on the vendor or integrator
Cause : Proprietary customisations, no documentation, skills not transferred
Consequence : Rising costs, inability to change supplier
9 P3×I3 • Exit clauses and documentation deliverables
• Internal skills build-up
R-020 Insufficient testing before go-live
Cause : Compressed acceptance phase, users unavailable, incomplete scenarios
Consequence : Defects in production, loss of user confidence
9 P3×I3 • Acceptance plan with business scenarios
• Go-live criteria
R-021 IT system obsolescence
Cause : Software or equipment without vendor support, scarce skills
Consequence : Unfixable vulnerabilities, breakdowns, emergency migration costs
9 P3×I3 • Multi-year renewal plan
• Isolate legacy systems
R-022 Lack of in-house digital skills
Cause : Reliance on one person or a provider, insufficient training
Consequence : Stalled projects, poor use of tools, security risks
9 P3×I3 • Targeted training plan
• Documentation and support contract
R-023 Underestimated project complexity
Cause : Many actors, interdependencies, new technologies
Consequence : Many surprises, schedule and cost drift
9 P3×I3 • Complexity assessment at launch
• Short phases with decision points
R-024 Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers
Consequence : Extra costs, customs delays, closed markets
9 P3×I3 • Customs watch and product origin
• Alternative suppliers in other regions
R-025 Voice or video impersonation fraud (deepfake)
Cause : AI-generated call or video meeting imitating an executive or supplier
Consequence : Fraudulent transfer, disclosure of information
9 P3×I3 • Code word and call-back for sensitive requests
• Deepfake awareness
R-026 Intrusion through remote access
Cause : Exposed VPN or remote desktop, weak passwords, personal devices
Consequence : Access to internal systems, data theft
9 P3×I3 • Patched VPN with two-factor authentication
• Logging and connection review
R-027 Data loss during a release
Cause : Faulty migration script, no prior backup, no rollback
Consequence : Corrupted data, service outage
8 P2×I4 • Verified backup before every release
• Tested rollback plan
R-028 Cloud service misconfiguration
Cause : Storage left public, overly broad rights, logging disabled
Consequence : Data exposed on the internet, large-scale leak
8 P2×I4 • Review of sharing and security settings
• Documented baseline configuration
R-029 Outage at a major digital provider
Cause : Incident at a host, software vendor or operator many services depend on
Consequence : Several tools down at once, business blocked
8 P2×I4 • Map critical digital dependencies
• Degraded operating mode
R-030 Vulnerability in an exposed API
Cause : Weak authentication, missing access control, excessive data returned
Consequence : Data leak, fraud
8 P2×I4 • API security testing
• Logging and anomaly detection
R-031 No cyber incident response plan
Cause : Roles undefined, emergency contacts unknown, notification duties ignored
Consequence : Slow reaction, greater damage, penalties for late notification
8 P2×I4 • One-page response plan and emergency contacts
• Annual cyber crisis exercise
R-032 Dependence on a cloud provider
Cause : Contract without exit clause, data in a proprietary format
Consequence : Forced price increases, costly migration, data outside the EU
8 P2×I4 • Exit and data location clauses
• Regular data exports
R-033 Poor performance under load
Cause : No load testing, undersized architecture
Consequence : Slowness, outages at peak times
8 P2×I4 • Realistic load testing
• Monitoring and scalable capacity
R-034 Unregulated data transfer outside the EU
Cause : Provider or sub-processor outside the EU, no safeguards
Consequence : GDPR non-compliance, need to change tools
6 P2×I3 • Check location and safeguards
• Prefer EU hosting
R-035 Data protection not built in by design
Cause : Excessive collection, no deletion, data subject rights not planned
Consequence : Costly redesign, non-compliance
6 P2×I3 • Data protection review at design
• Export and deletion features planned

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Migration to the cloud”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free