Risk register example: ERP implementation

Deploying an ERP: scope creep, data migration, integrations, user adoption and go-live.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate25
● High9
● Critical1

Assumptions: IT / digital project · Planning / design · 15 people · data migration, integration with existing systems, scope likely to change, personal data processed, critical item from a single supplier, tight or immovable deadline, cloud or saas services.

Ref.RiskScorePreventionProtection
R-001 Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory
Consequence : Intrusion, data theft, service outage
16 P4×I4 • Inventory of exposed assets and priority patching
• Regular vulnerability scanning
R-002 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-003 Difficult integration with existing systems
Cause : Poorly documented interfaces, inconsistent data formats
Consequence : Delays, degraded features, double data entry
12 P3×I4 • Early interface inventory and tests
• Manual workaround
R-004 Security vulnerability in the application
Cause : No code review or security testing, outdated dependencies
Consequence : Intrusion, data leak, reputational damage
12 P3×I4 • Code review and automated scanning
• Penetration test before go-live
R-005 Supply disruption of a critical item
Cause : Single supplier, no qualified alternative
Consequence : Work or production stopped while waiting for delivery
12 P3×I4 • Qualify a second supplier
• Safety stock
R-006 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-007 GDPR non-compliance
Cause : Personal data processed without legal basis, record or information of data subjects
Consequence : Data protection authority fine, complaints
12 P3×I4 • Record of processing and impact assessment
• Data minimisation and retention periods
R-008 Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier
Consequence : Production or site stoppage, delays, penalties
12 P3×I4 • Map tier-1 and tier-2 suppliers
• Safety stock for critical components
R-009 Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration
Consequence : Mandatory notification, loss of trust, fines, claims
10 P2×I5 • Least-privilege access management
• Breach notification procedure
R-010 Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation
Consequence : Systems down, data lost, ransom demanded
10 P2×I5 • Patching and endpoint protection
• Tested offline backups
R-011 Backups that cannot be restored
Cause : Backups never tested, incomplete or encrypted by the attacker
Consequence : Permanent data loss after an incident
9 P3×I3 • Quarterly restore test
• Offline or immutable copy
R-012 Underestimated development effort
Cause : Estimates without detailed breakdown, hidden complexity, optimism
Consequence : Schedule and budget overrun
9 P3×I3 • Breakdown estimates by several people
• Incremental delivery and prioritisation
R-013 Accumulated technical debt
Cause : Development shortcuts, no automated tests, missing documentation
Consequence : Slow changes, frequent bugs, high maintenance costs
9 P3×I3 • Automated tests and code review
• Time reserved for paying down debt
R-014 Cloud subscription and hosting cost drift
Cause : Oversized resources, unused licences, price increases
Consequence : Operating budget overrun
9 P3×I3 • Monthly cost and licence review
• Budget alerts
R-015 Account takeover without multi-factor authentication
Cause : Reused or stolen password, email and online tools protected by a single factor
Consequence : Impersonation, data access, fraud sent from a legitimate account
9 P3×I3 • Mandatory multi-factor authentication
• Alerts on unusual sign-ins
R-016 Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion
Consequence : Studies and works to redo, extra costs, delay
9 P3×I3 • Project-specific regulatory watch
• Change-in-law clause
R-017 Scope creep
Cause : Requests added during the project without trade-offs
Consequence : Schedule and budget overrun, overloaded team
9 P3×I3 • Change approval board
• Visible out-of-scope list
R-018 Incomplete or incorrect data migration
Cause : Inconsistent source data, poorly defined transformation rules
Consequence : Errors in production, loss of user trust
9 P3×I3 • Data cleansing and dry runs
• Reconciliation checks and rollback
R-019 Low user adoption
Cause : Users not involved, insufficient training
Consequence : Return to old tools, benefits not achieved
9 P3×I3 • Key users involved from design
• Training and go-live support
R-020 Risky go-live
Cause : Big-bang cutover, no rollback plan
Consequence : Service interruption, inconsistent data
9 P3×I3 • Cutover rehearsal
• Tested rollback plan
R-021 Excessive dependence on the vendor or integrator
Cause : Proprietary customisations, no documentation, skills not transferred
Consequence : Rising costs, inability to change supplier
9 P3×I3 • Exit clauses and documentation deliverables
• Internal skills build-up
R-022 Insufficient testing before go-live
Cause : Compressed acceptance phase, users unavailable, incomplete scenarios
Consequence : Defects in production, loss of user confidence
9 P3×I3 • Acceptance plan with business scenarios
• Go-live criteria
R-023 Late decisions by the client or management
Cause : Slow approval of choices, multiple contacts, postponed trade-offs
Consequence : Delay, wasted team time, rework
9 P3×I3 • Schedule of expected decisions
• Default decision rule
R-024 IT system obsolescence
Cause : Software or equipment without vendor support, scarce skills
Consequence : Unfixable vulnerabilities, breakdowns, emergency migration costs
9 P3×I3 • Multi-year renewal plan
• Isolate legacy systems
R-025 Lack of in-house digital skills
Cause : Reliance on one person or a provider, insufficient training
Consequence : Stalled projects, poor use of tools, security risks
9 P3×I3 • Targeted training plan
• Documentation and support contract
R-026 Unclear objectives and success criteria
Cause : Vision not shared, expected benefits not measurable
Consequence : Diverging expectations, project judged a failure despite delivery
9 P3×I3 • Project charter with measurable objectives
• Benefits review after delivery
R-027 Underestimated project complexity
Cause : Many actors, interdependencies, new technologies
Consequence : Many surprises, schedule and cost drift
9 P3×I3 • Complexity assessment at launch
• Short phases with decision points
R-028 Data loss during a release
Cause : Faulty migration script, no prior backup, no rollback
Consequence : Corrupted data, service outage
8 P2×I4 • Verified backup before every release
• Tested rollback plan
R-029 Vulnerability in an exposed API
Cause : Weak authentication, missing access control, excessive data returned
Consequence : Data leak, fraud
8 P2×I4 • API security testing
• Logging and anomaly detection
R-030 Cloud service misconfiguration
Cause : Storage left public, overly broad rights, logging disabled
Consequence : Data exposed on the internet, large-scale leak
8 P2×I4 • Review of sharing and security settings
• Documented baseline configuration
R-031 Poor performance under load
Cause : No load testing, undersized architecture
Consequence : Slowness, outages at peak times
8 P2×I4 • Realistic load testing
• Monitoring and scalable capacity
R-032 Data protection not built in by design
Cause : Excessive collection, no deletion, data subject rights not planned
Consequence : Costly redesign, non-compliance
6 P2×I3 • Data protection review at design
• Export and deletion features planned
R-033 Unregulated data transfer outside the EU
Cause : Provider or sub-processor outside the EU, no safeguards
Consequence : GDPR non-compliance, need to change tools
6 P2×I3 • Check location and safeguards
• Prefer EU hosting
R-034 Intellectual property infringement
Cause : Use of protected content without rights, no transfer of rights by contractors
Consequence : Dispute, product withdrawal, damages
6 P2×I3 • Assignment-of-rights clause in contracts
• Check licences used
R-035 Unrequested additions by the team (gold plating)
Cause : Features or finishes beyond the need, perfectionism
Consequence : Time and cost overruns without added value
6 P2×I3 • Scope check at each delivery
• Clear definition of done

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “ERP implementation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free