Risk register example: ERP implementation
Deploying an ERP: scope creep, data migration, integrations, user adoption and go-live.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: IT / digital project · Planning / design · 15 people · data migration, integration with existing systems, scope likely to change, personal data processed, critical item from a single supplier, tight or immovable deadline, cloud or saas services.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory Consequence : Intrusion, data theft, service outage |
16 P4×I4 | • Inventory of exposed assets and priority patching • Regular vulnerability scanning |
|
| R-002 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-003 | Difficult integration with existing systems
Cause : Poorly documented interfaces, inconsistent data formats Consequence : Delays, degraded features, double data entry |
12 P3×I4 | • Early interface inventory and tests |
• Manual workaround |
| R-004 | Security vulnerability in the application
Cause : No code review or security testing, outdated dependencies Consequence : Intrusion, data leak, reputational damage |
12 P3×I4 | • Code review and automated scanning • Penetration test before go-live |
|
| R-005 | Supply disruption of a critical item
Cause : Single supplier, no qualified alternative Consequence : Work or production stopped while waiting for delivery |
12 P3×I4 | • Qualify a second supplier |
• Safety stock |
| R-006 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-007 | GDPR non-compliance
Cause : Personal data processed without legal basis, record or information of data subjects Consequence : Data protection authority fine, complaints |
12 P3×I4 | • Record of processing and impact assessment • Data minimisation and retention periods |
|
| R-008 | Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier Consequence : Production or site stoppage, delays, penalties |
12 P3×I4 | • Map tier-1 and tier-2 suppliers |
• Safety stock for critical components |
| R-009 | Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration Consequence : Mandatory notification, loss of trust, fines, claims |
10 P2×I5 | • Least-privilege access management |
• Breach notification procedure |
| R-010 | Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation Consequence : Systems down, data lost, ransom demanded |
10 P2×I5 | • Patching and endpoint protection |
• Tested offline backups |
| R-011 | Backups that cannot be restored
Cause : Backups never tested, incomplete or encrypted by the attacker Consequence : Permanent data loss after an incident |
9 P3×I3 | • Quarterly restore test |
• Offline or immutable copy |
| R-012 | Underestimated development effort
Cause : Estimates without detailed breakdown, hidden complexity, optimism Consequence : Schedule and budget overrun |
9 P3×I3 | • Breakdown estimates by several people |
• Incremental delivery and prioritisation |
| R-013 | Accumulated technical debt
Cause : Development shortcuts, no automated tests, missing documentation Consequence : Slow changes, frequent bugs, high maintenance costs |
9 P3×I3 | • Automated tests and code review |
• Time reserved for paying down debt |
| R-014 | Cloud subscription and hosting cost drift
Cause : Oversized resources, unused licences, price increases Consequence : Operating budget overrun |
9 P3×I3 | • Monthly cost and licence review |
• Budget alerts |
| R-015 | Account takeover without multi-factor authentication
Cause : Reused or stolen password, email and online tools protected by a single factor Consequence : Impersonation, data access, fraud sent from a legitimate account |
9 P3×I3 | • Mandatory multi-factor authentication |
• Alerts on unusual sign-ins |
| R-016 | Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion Consequence : Studies and works to redo, extra costs, delay |
9 P3×I3 | • Project-specific regulatory watch |
• Change-in-law clause |
| R-017 | Scope creep
Cause : Requests added during the project without trade-offs Consequence : Schedule and budget overrun, overloaded team |
9 P3×I3 | • Change approval board |
• Visible out-of-scope list |
| R-018 | Incomplete or incorrect data migration
Cause : Inconsistent source data, poorly defined transformation rules Consequence : Errors in production, loss of user trust |
9 P3×I3 | • Data cleansing and dry runs |
• Reconciliation checks and rollback |
| R-019 | Low user adoption
Cause : Users not involved, insufficient training Consequence : Return to old tools, benefits not achieved |
9 P3×I3 | • Key users involved from design |
• Training and go-live support |
| R-020 | Risky go-live
Cause : Big-bang cutover, no rollback plan Consequence : Service interruption, inconsistent data |
9 P3×I3 | • Cutover rehearsal |
• Tested rollback plan |
| R-021 | Excessive dependence on the vendor or integrator
Cause : Proprietary customisations, no documentation, skills not transferred Consequence : Rising costs, inability to change supplier |
9 P3×I3 | • Exit clauses and documentation deliverables • Internal skills build-up |
|
| R-022 | Insufficient testing before go-live
Cause : Compressed acceptance phase, users unavailable, incomplete scenarios Consequence : Defects in production, loss of user confidence |
9 P3×I3 | • Acceptance plan with business scenarios |
• Go-live criteria |
| R-023 | Late decisions by the client or management
Cause : Slow approval of choices, multiple contacts, postponed trade-offs Consequence : Delay, wasted team time, rework |
9 P3×I3 | • Schedule of expected decisions |
• Default decision rule |
| R-024 | IT system obsolescence
Cause : Software or equipment without vendor support, scarce skills Consequence : Unfixable vulnerabilities, breakdowns, emergency migration costs |
9 P3×I3 | • Multi-year renewal plan |
• Isolate legacy systems |
| R-025 | Lack of in-house digital skills
Cause : Reliance on one person or a provider, insufficient training Consequence : Stalled projects, poor use of tools, security risks |
9 P3×I3 | • Targeted training plan |
• Documentation and support contract |
| R-026 | Unclear objectives and success criteria
Cause : Vision not shared, expected benefits not measurable Consequence : Diverging expectations, project judged a failure despite delivery |
9 P3×I3 | • Project charter with measurable objectives |
• Benefits review after delivery |
| R-027 | Underestimated project complexity
Cause : Many actors, interdependencies, new technologies Consequence : Many surprises, schedule and cost drift |
9 P3×I3 | • Complexity assessment at launch |
• Short phases with decision points |
| R-028 | Data loss during a release
Cause : Faulty migration script, no prior backup, no rollback Consequence : Corrupted data, service outage |
8 P2×I4 | • Verified backup before every release |
• Tested rollback plan |
| R-029 | Vulnerability in an exposed API
Cause : Weak authentication, missing access control, excessive data returned Consequence : Data leak, fraud |
8 P2×I4 | • API security testing |
• Logging and anomaly detection |
| R-030 | Cloud service misconfiguration
Cause : Storage left public, overly broad rights, logging disabled Consequence : Data exposed on the internet, large-scale leak |
8 P2×I4 | • Review of sharing and security settings • Documented baseline configuration |
|
| R-031 | Poor performance under load
Cause : No load testing, undersized architecture Consequence : Slowness, outages at peak times |
8 P2×I4 | • Realistic load testing |
• Monitoring and scalable capacity |
| R-032 | Data protection not built in by design
Cause : Excessive collection, no deletion, data subject rights not planned Consequence : Costly redesign, non-compliance |
6 P2×I3 | • Data protection review at design • Export and deletion features planned |
|
| R-033 | Unregulated data transfer outside the EU
Cause : Provider or sub-processor outside the EU, no safeguards Consequence : GDPR non-compliance, need to change tools |
6 P2×I3 | • Check location and safeguards • Prefer EU hosting |
|
| R-034 | Intellectual property infringement
Cause : Use of protected content without rights, no transfer of rights by contractors Consequence : Dispute, product withdrawal, damages |
6 P2×I3 | • Assignment-of-rights clause in contracts • Check licences used |
|
| R-035 | Unrequested additions by the team (gold plating)
Cause : Features or finishes beyond the need, perfectionism Consequence : Time and cost overruns without added value |
6 P2×I3 | • Scope check at each delivery • Clear definition of done |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “ERP implementation”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.