Risk register example: Cybersecurity programme (NIS2)
Raising the security level of an organisation: phishing, ransomware, remote access, suppliers and compliance.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: IT / digital project · Planning / design · 6 people · remote access or remote work, cloud or saas services, personal data processed, service must be available 24/7, industrial control systems (automation, scada), integration with existing systems.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory Consequence : Intrusion, data theft, service outage |
16 P4×I4 | • Inventory of exposed assets and priority patching • Regular vulnerability scanning |
|
| R-002 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-003 | GDPR non-compliance
Cause : Personal data processed without legal basis, record or information of data subjects Consequence : Data protection authority fine, complaints |
12 P3×I4 | • Record of processing and impact assessment • Data minimisation and retention periods |
|
| R-004 | Security vulnerability in the application
Cause : No code review or security testing, outdated dependencies Consequence : Intrusion, data leak, reputational damage |
12 P3×I4 | • Code review and automated scanning • Penetration test before go-live |
|
| R-005 | Extended service outage
Cause : Hosting failure, failed update, no redundancy Consequence : Users blocked, financial losses, contractual penalties |
12 P3×I4 | • Monitoring and automatic alerts |
• Recovery plan and redundancy |
| R-006 | Difficult integration with existing systems
Cause : Poorly documented interfaces, inconsistent data formats Consequence : Delays, degraded features, double data entry |
12 P3×I4 | • Early interface inventory and tests |
• Manual workaround |
| R-007 | Ransomware attack
Cause : Unpatched computers, backups reachable from the network, no segmentation Consequence : Systems down, data lost, ransom demanded |
10 P2×I5 | • Patching and endpoint protection |
• Tested offline backups |
| R-008 | Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration Consequence : Mandatory notification, loss of trust, fines, claims |
10 P2×I5 | • Least-privilege access management |
• Breach notification procedure |
| R-009 | Account takeover without multi-factor authentication
Cause : Reused or stolen password, email and online tools protected by a single factor Consequence : Impersonation, data access, fraud sent from a legitimate account |
9 P3×I3 | • Mandatory multi-factor authentication |
• Alerts on unusual sign-ins |
| R-010 | Loss or theft of a laptop or phone
Cause : Unencrypted devices, data stored locally, frequent travel Consequence : Data leak, mandatory notification, lost work |
9 P3×I3 | • Encrypt portable devices |
• Remote wipe and central backup |
| R-011 | Data leak through human error
Cause : Wrong recipient, wrong attachment, overly open sharing link Consequence : Data breach to notify, loss of trust |
9 P3×I3 | • Short, repeated awareness sessions • Send delay and external-recipient warning |
|
| R-012 | Cloud subscription and hosting cost drift
Cause : Oversized resources, unused licences, price increases Consequence : Operating budget overrun |
9 P3×I3 | • Monthly cost and licence review |
• Budget alerts |
| R-013 | Accumulated technical debt
Cause : Development shortcuts, no automated tests, missing documentation Consequence : Slow changes, frequent bugs, high maintenance costs |
9 P3×I3 | • Automated tests and code review |
• Time reserved for paying down debt |
| R-014 | Voice or video impersonation fraud (deepfake)
Cause : AI-generated call or video meeting imitating an executive or supplier Consequence : Fraudulent transfer, disclosure of information |
9 P3×I3 | • Code word and call-back for sensitive requests • Deepfake awareness |
|
| R-015 | Intrusion through remote access
Cause : Exposed VPN or remote desktop, weak passwords, personal devices Consequence : Access to internal systems, data theft |
9 P3×I3 | • Patched VPN with two-factor authentication |
• Logging and connection review |
| R-016 | Low user adoption
Cause : Users not involved, insufficient training Consequence : Return to old tools, benefits not achieved |
9 P3×I3 | • Key users involved from design |
• Training and go-live support |
| R-017 | Risky go-live
Cause : Big-bang cutover, no rollback plan Consequence : Service interruption, inconsistent data |
9 P3×I3 | • Cutover rehearsal |
• Tested rollback plan |
| R-018 | Excessive dependence on the vendor or integrator
Cause : Proprietary customisations, no documentation, skills not transferred Consequence : Rising costs, inability to change supplier |
9 P3×I3 | • Exit clauses and documentation deliverables • Internal skills build-up |
|
| R-019 | Insufficient testing before go-live
Cause : Compressed acceptance phase, users unavailable, incomplete scenarios Consequence : Defects in production, loss of user confidence |
9 P3×I3 | • Acceptance plan with business scenarios |
• Go-live criteria |
| R-020 | Uncontrolled use of generative AI tools
Cause : Staff pasting confidential or personal data into public tools Consequence : Information leak, GDPR non-compliance, loss of trade secrets |
9 P3×I3 | • AI acceptable-use policy • Enterprise AI tool with contractual commitments |
|
| R-021 | Backups that cannot be restored
Cause : Backups never tested, incomplete or encrypted by the attacker Consequence : Permanent data loss after an incident |
9 P3×I3 | • Quarterly restore test |
• Offline or immutable copy |
| R-022 | Cloud service misconfiguration
Cause : Storage left public, overly broad rights, logging disabled Consequence : Data exposed on the internet, large-scale leak |
8 P2×I4 | • Review of sharing and security settings • Documented baseline configuration |
|
| R-023 | Vulnerability in an exposed API
Cause : Weak authentication, missing access control, excessive data returned Consequence : Data leak, fraud |
8 P2×I4 | • API security testing |
• Logging and anomaly detection |
| R-024 | No cyber incident response plan
Cause : Roles undefined, emergency contacts unknown, notification duties ignored Consequence : Slow reaction, greater damage, penalties for late notification |
8 P2×I4 | • One-page response plan and emergency contacts • Annual cyber crisis exercise |
|
| R-025 | Outage at a major digital provider
Cause : Incident at a host, software vendor or operator many services depend on Consequence : Several tools down at once, business blocked |
8 P2×I4 | • Map critical digital dependencies • Degraded operating mode |
|
| R-026 | Data loss during a release
Cause : Faulty migration script, no prior backup, no rollback Consequence : Corrupted data, service outage |
8 P2×I4 | • Verified backup before every release |
• Tested rollback plan |
| R-027 | Failure to meet NIS2 obligations
Cause : Entity in scope not registered, missing risk-management measures, incidents not notified Consequence : Fines, management liability, regulator inspection |
8 P2×I4 | • Scope check and registration • Cybersecurity action plan tracked by management |
|
| R-028 | Malicious act by an employee or former employee
Cause : Access not removed on departure, excessive rights, labour dispute Consequence : Data theft or destruction, sabotage |
8 P2×I4 | • Leaver procedure with same-day access removal • Six-monthly access review |
|
| R-029 | Dependence on a cloud provider
Cause : Contract without exit clause, data in a proprietary format Consequence : Forced price increases, costly migration, data outside the EU |
8 P2×I4 | • Exit and data location clauses |
• Regular data exports |
| R-030 | Poor performance under load
Cause : No load testing, undersized architecture Consequence : Slowness, outages at peak times |
8 P2×I4 | • Realistic load testing |
• Monitoring and scalable capacity |
| R-031 | Non-compliance with the EU AI Act
Cause : High-risk AI system not identified, insufficient transparency, missing documentation Consequence : Fines, system withdrawn, reputational damage |
8 P2×I4 | • Inventory and classification of AI uses • User information and technical documentation |
|
| R-032 | Unregulated data transfer outside the EU
Cause : Provider or sub-processor outside the EU, no safeguards Consequence : GDPR non-compliance, need to change tools |
6 P2×I3 | • Check location and safeguards • Prefer EU hosting |
|
| R-033 | Data protection not built in by design
Cause : Excessive collection, no deletion, data subject rights not planned Consequence : Costly redesign, non-compliance |
6 P2×I3 | • Data protection review at design • Export and deletion features planned |
|
| R-034 | Prolonged sitting and screen work
Cause : Poorly adjusted workstations, few breaks, full days at a screen Consequence : Back and neck pain, eye strain |
6 P3×I2 | • Ergonomic workstation set-up • Active breaks and task variation |
|
| R-035 | Isolation and psychosocial risks of remote work
Cause : Little contact with the team, blurred work-life boundaries Consequence : Demotivation, hidden overload, sleep problems |
4 P2×I2 | • Remote-work rules and right to disconnect • Regular team moments |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Cybersecurity programme (NIS2)”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.