Risk register example: Works in a school
Renovation while pupils are around or during holidays: child safety, asbestos, deadlines.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Public sector · Execution / works · 12 people · occupied site (staff, residents, patients nearby), vulnerable people (patients, children, elderly), old building (asbestos, lead possible), work at height (roofs, scaffolding, platforms), tight or immovable deadline, public procurement, noise or vibration.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
20 P4×I5 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-002 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
20 P4×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-003 | Vulnerable people exposed to hazards
Cause : Patients, children or elderly people near the activity area Consequence : Serious accident, complaint, facility closure |
16 P4×I4 | • Joint risk assessment with the facility |
• On-site contact and alert procedure |
| R-004 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-005 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-006 | Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building Consequence : Serious delayed illness, works stopped, costly unplanned removal |
15 P3×I5 | • Asbestos and lead survey before works |
• Stop-work procedure on discovery |
| R-007 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-008 | Intrusion or attack in a public building
Cause : Open access, no specific alert, no drills Consequence : Casualties, panic |
12 P3×I4 | • Access control and specific alert |
• Lockdown drill |
| R-009 | Assault on a front-desk or field officer
Cause : Tensions with users, lone work, unwelcome decisions Consequence : Injuries, trauma, absenteeism |
12 P3×I4 | • Secure reception design |
• Supported complaint and assistance |
| R-010 | Accident or missing child at school or on an outing
Cause : Insufficient supervision, poorly prepared outings, uncontrolled access Consequence : Injury, lost child, liability |
12 P3×I4 | • Supervision ratios and name list • Building access control |
|
| R-011 | Abuse of a vulnerable person
Cause : Recruitment without checks, overload, no reporting Consequence : Serious harm to victims, prosecution, loss of trust |
12 P3×I4 | • Background checks at recruitment |
• Reporting and listening procedure |
| R-012 | Burnout and violence in education
Cause : Difficult classes, administrative load, conflict with parents Consequence : Sick leave, resignations, lower teaching quality |
12 P4×I3 | • Management support and incident procedure |
• Support for new teachers |
| R-013 | Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections Consequence : People trapped, car fall, accident |
12 P3×I4 | • Maintenance contract and periodic inspections |
• Emergency phone and rescue procedure |
| R-014 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
12 P4×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-015 | Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads Consequence : Sprains, fractures |
12 P3×I4 | • Anti-slip nosings and handrails • Hoists or trolleys for loads |
|
| R-016 | Poorly prepared emergency evacuation
Cause : Blocked exits, inaudible alarm, no drills, people with reduced mobility forgotten Consequence : Casualties during a fire or leak |
12 P3×I4 | • Annual evacuation drill |
• Appointed evacuation wardens |
| R-017 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-018 | Moving and handling people
Cause : Transfers of patients or residents without equipment, staff alone Consequence : Low back pain, injuries to carer and patient |
9 P3×I3 | • Transfer aids • Training in people-handling techniques |
|
| R-019 | Lengthy administrative approval times
Cause : Multiple sign-off steps, postponed council or committee Consequence : Project delay, loss of grants |
9 P3×I3 | • Governance calendar in the schedule |
• Signature delegations for routine decisions |
| R-020 | Funding cut or postponed
Cause : Budget trade-offs, political change, delayed grant Consequence : Project reduced, postponed or abandoned |
9 P3×I3 | • Phasing that allows a clean stop |
• Several funding sources |
| R-021 | Change in political priorities
Cause : Elections, change of majority or lead official, budget trade-offs Consequence : Project resized, suspended or abandoned |
9 P3×I3 | • Phasing in self-contained stages |
• Document benefits and decisions |
| R-022 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-023 | Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations Consequence : Stress, verbal aggression, staff burnout |
9 P3×I3 | • Conflict-management training |
• Post-incident support and reporting |
| R-024 | Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture Consequence : Bruises, cuts, falls |
9 P3×I3 | • Daily tidy-up and defined storage areas • Regular safety walks |
|
| R-025 | Loss of key skills in the administration
Cause : Retirements, recruitment difficulties, mobility Consequence : Slower processing, dependence on contractors |
9 P3×I3 | • Map critical skills |
• Documented procedures and pairs |
| R-026 | Exposure to noise or vibration
Cause : Noisy tools and machines, long exposure Consequence : Hearing loss, vascular disorders, nuisance to neighbours |
9 P3×I3 | • Quieter equipment and enclosures |
• Hearing protection and health checks |
| R-027 | Breakdown of a critical building system
Cause : Heating, ventilation, lifts or generator without preventive maintenance Consequence : Discomfort or interruption for occupants, costly emergency call-outs |
9 P3×I3 | • Preventive maintenance plan by criticality |
• Rapid response contract and critical spares |
| R-028 | Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions Consequence : Chronic stress, errors, accidents, absenteeism |
9 P3×I3 | • Realistic workload planning |
• Spot warning signs |
| R-029 | Backup power failure
Cause : Generator or UPS not tested, insufficient fuel Consequence : Vital equipment stops during a power cut |
8 P2×I4 | • Regular load tests |
• Fuel reserve and supply contract |
| R-030 | Irregularity in a public procurement procedure
Cause : Thresholds misapplied, discriminatory criteria, insufficient advertising Consequence : Annulment, appeals, liability of officials |
8 P2×I4 | • Legal review of tender documents • Train public buyers |
|
| R-031 | Litigation over a permit or public decision
Cause : Appeals by residents or associations, insufficient reasoning, procedure not followed Consequence : Project suspended, delays of months or years |
8 P2×I4 | • Early consultation and robust file |
• Schedule including appeal period |
| R-032 | Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response Consequence : Loss of trust, lost customers, pressure from authorities |
8 P2×I4 | • Crisis communication procedure • Quick-reaction sheet and press contacts |
|
| R-033 | Opposition from citizens or residents
Cause : Insufficient consultation, impacts poorly explained Consequence : Appeals, negative media coverage, delay |
6 P2×I3 | • Early public consultation |
• Contact point and request tracking |
| R-034 | Exposure to biological agents
Cause : Contact with sick people, waste, animals or contaminated water Consequence : Infections, absences |
6 P2×I3 | • Hand hygiene and recommended vaccination |
• Protective equipment and exposure procedure |
| R-035 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.