Risk register example: Digital public service
Putting a public service online: citizens’ data, accessibility, procurement, legacy systems and adoption.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Public sector · Planning / design · 10 people · personal data processed, public procurement, integration with existing systems, service must be available 24/7, scope likely to change, cloud or saas services.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Exploitation of an unpatched vulnerability
Cause : Internet-facing software and devices not updated, incomplete asset inventory Consequence : Intrusion, data theft, service outage |
16 P4×I4 | • Inventory of exposed assets and priority patching • Regular vulnerability scanning |
|
| R-002 | Cyberattack paralysing citizen services
Cause : Ransomware, denial of service, interconnected legacy systems Consequence : Services closed, citizens’ data exposed, crisis of trust |
12 P3×I4 | • Digital security plan approved by management |
• Paper-based continuity of essential services |
| R-003 | Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency Consequence : Intrusion via the supply chain, data leak, business interruption |
12 P3×I4 | • Security assessment of critical suppliers • Limited and logged supplier access |
|
| R-004 | GDPR non-compliance
Cause : Personal data processed without legal basis, record or information of data subjects Consequence : Data protection authority fine, complaints |
12 P3×I4 | • Record of processing and impact assessment • Data minimisation and retention periods |
|
| R-005 | Difficult integration with existing systems
Cause : Poorly documented interfaces, inconsistent data formats Consequence : Delays, degraded features, double data entry |
12 P3×I4 | • Early interface inventory and tests |
• Manual workaround |
| R-006 | Lengthy administrative approval times
Cause : Multiple sign-off steps, postponed council or committee Consequence : Project delay, loss of grants |
9 P3×I3 | • Governance calendar in the schedule |
• Signature delegations for routine decisions |
| R-007 | Account takeover without multi-factor authentication
Cause : Reused or stolen password, email and online tools protected by a single factor Consequence : Impersonation, data access, fraud sent from a legitimate account |
9 P3×I3 | • Mandatory multi-factor authentication |
• Alerts on unusual sign-ins |
| R-008 | Funding cut or postponed
Cause : Budget trade-offs, political change, delayed grant Consequence : Project reduced, postponed or abandoned |
9 P3×I3 | • Phasing that allows a clean stop |
• Several funding sources |
| R-009 | Change in political priorities
Cause : Elections, change of majority or lead official, budget trade-offs Consequence : Project resized, suspended or abandoned |
9 P3×I3 | • Phasing in self-contained stages |
• Document benefits and decisions |
| R-010 | Data leak through human error
Cause : Wrong recipient, wrong attachment, overly open sharing link Consequence : Data breach to notify, loss of trust |
9 P3×I3 | • Short, repeated awareness sessions • Send delay and external-recipient warning |
|
| R-011 | Uncontrolled use of generative AI tools
Cause : Staff pasting confidential or personal data into public tools Consequence : Information leak, GDPR non-compliance, loss of trade secrets |
9 P3×I3 | • AI acceptable-use policy • Enterprise AI tool with contractual commitments |
|
| R-012 | Backups that cannot be restored
Cause : Backups never tested, incomplete or encrypted by the attacker Consequence : Permanent data loss after an incident |
9 P3×I3 | • Quarterly restore test |
• Offline or immutable copy |
| R-013 | IT system obsolescence
Cause : Software or equipment without vendor support, scarce skills Consequence : Unfixable vulnerabilities, breakdowns, emergency migration costs |
9 P3×I3 | • Multi-year renewal plan |
• Isolate legacy systems |
| R-014 | Loss of key skills in the administration
Cause : Retirements, recruitment difficulties, mobility Consequence : Slower processing, dependence on contractors |
9 P3×I3 | • Map critical skills |
• Documented procedures and pairs |
| R-015 | Scope creep
Cause : Requests added during the project without trade-offs Consequence : Schedule and budget overrun, overloaded team |
9 P3×I3 | • Change approval board |
• Visible out-of-scope list |
| R-016 | Late decisions by the client or management
Cause : Slow approval of choices, multiple contacts, postponed trade-offs Consequence : Delay, wasted team time, rework |
9 P3×I3 | • Schedule of expected decisions |
• Default decision rule |
| R-017 | Irregularity in a public procurement procedure
Cause : Thresholds misapplied, discriminatory criteria, insufficient advertising Consequence : Annulment, appeals, liability of officials |
8 P2×I4 | • Legal review of tender documents • Train public buyers |
|
| R-018 | No cyber incident response plan
Cause : Roles undefined, emergency contacts unknown, notification duties ignored Consequence : Slow reaction, greater damage, penalties for late notification |
8 P2×I4 | • One-page response plan and emergency contacts • Annual cyber crisis exercise |
|
| R-019 | Cloud service misconfiguration
Cause : Storage left public, overly broad rights, logging disabled Consequence : Data exposed on the internet, large-scale leak |
8 P2×I4 | • Review of sharing and security settings • Documented baseline configuration |
|
| R-020 | Drinking water or sewer network failure
Cause : Ageing pipes, pollution, pump failure Consequence : Water cut, health risk, flooding |
8 P2×I4 | • Network renewal plan |
• Emergency water plan |
| R-021 | Outage at a major digital provider
Cause : Incident at a host, software vendor or operator many services depend on Consequence : Several tools down at once, business blocked |
8 P2×I4 | • Map critical digital dependencies • Degraded operating mode |
|
| R-022 | Backup power failure
Cause : Generator or UPS not tested, insufficient fuel Consequence : Vital equipment stops during a power cut |
8 P2×I4 | • Regular load tests |
• Fuel reserve and supply contract |
| R-023 | Malicious act by an employee or former employee
Cause : Access not removed on departure, excessive rights, labour dispute Consequence : Data theft or destruction, sabotage |
8 P2×I4 | • Leaver procedure with same-day access removal • Six-monthly access review |
|
| R-024 | Litigation over a permit or public decision
Cause : Appeals by residents or associations, insufficient reasoning, procedure not followed Consequence : Project suspended, delays of months or years |
8 P2×I4 | • Early consultation and robust file |
• Schedule including appeal period |
| R-025 | Cash flow strain during the project
Cause : Late client payments, large supplier advances, no down payments Consequence : Cascading late payments, costly borrowing |
8 P2×I4 | • Billing schedule aligned with progress |
• Monthly cash flow plan |
| R-026 | Bribery or conflict of interest
Cause : Unregulated gifts or benefits, opaque intermediaries, untraced purchasing decisions Consequence : Criminal proceedings, exclusion from public tenders, reputational damage |
8 P2×I4 | • Code of conduct and gifts register • Conflict-of-interest declarations and dual purchase approval |
|
| R-027 | Contractual delay penalties
Cause : Tight deadlines, uncapped penalties, undocumented causes of delay Consequence : Major financial losses, dispute with the client |
8 P2×I4 | • Cap penalties when negotiating |
• Record causes of delay |
| R-028 | Dependence on a cloud provider
Cause : Contract without exit clause, data in a proprietary format Consequence : Forced price increases, costly migration, data outside the EU |
8 P2×I4 | • Exit and data location clauses |
• Regular data exports |
| R-029 | Unregulated data transfer outside the EU
Cause : Provider or sub-processor outside the EU, no safeguards Consequence : GDPR non-compliance, need to change tools |
6 P2×I3 | • Check location and safeguards • Prefer EU hosting |
|
| R-030 | Opposition from citizens or residents
Cause : Insufficient consultation, impacts poorly explained Consequence : Appeals, negative media coverage, delay |
6 P2×I3 | • Early public consultation |
• Contact point and request tracking |
| R-031 | Unrequested additions by the team (gold plating)
Cause : Features or finishes beyond the need, perfectionism Consequence : Time and cost overruns without added value |
6 P2×I3 | • Scope check at each delivery • Clear definition of done |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Digital public service”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.