Risk register example: Public building project

A school, sports hall or administrative building: procurement, funding, permits and public access.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate14
● High18
● Critical3

Assumptions: Public sector · Planning / design · 40 people · public procurement, permits or authorisations required, work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), excavation, trenches, earthworks, several companies working at the same time, site open to the public, dense urban area, neighbours nearby, fixed-price contract.

Ref.RiskScorePreventionProtection
R-001 Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan
Consequence : Serious accident, shared liability, site stoppage
16 P4×I4 • Prevention plan and joint inspection
• Daily coordination of work
R-002 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
15 P3×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-003 Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground
Consequence : Crushing, fatality, major damage
15 P3×I5 • Lifting plan for critical lifts
• Qualified operators and slingers, inspected gear
• No one under the load
R-004 Lengthy administrative approval times
Cause : Multiple sign-off steps, postponed council or committee
Consequence : Project delay, loss of grants
12 P4×I3 • Governance calendar in the schedule
• Signature delegations for routine decisions
R-005 Loss of a grant through non-compliance
Cause : Deadlines missed, missing evidence, ineligible expenses
Consequence : Repayment, funding gap
12 P3×I4 • Grant conditions tracker
• Early extension request
R-006 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
12 P3×I4 • Mobile platforms instead of ladders
• Visual check before use
R-007 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
12 P3×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-008 Funding cut or postponed
Cause : Budget trade-offs, political change, delayed grant
Consequence : Project reduced, postponed or abandoned
12 P3×I4 • Phasing that allows a clean stop
• Several funding sources
R-009 Change in political priorities
Cause : Elections, change of majority or lead official, budget trade-offs
Consequence : Project resized, suspended or abandoned
12 P4×I3 • Phasing in self-contained stages
• Document benefits and decisions
R-010 Rising interest rates and financing costs
Cause : Variable-rate borrowing, financing to renew during the project
Consequence : Higher financial charges, lower profitability
12 P3×I4 • Fixed or capped rate
• Rate scenario in the financing plan
R-011 Loss of key skills in the administration
Cause : Retirements, recruitment difficulties, mobility
Consequence : Slower processing, dependence on contractors
12 P4×I3 • Map critical skills
• Documented procedures and pairs
R-012 Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision
Consequence : Critical path blocked, delay
12 P4×I3 • External dependency log
• Prepared workaround
R-013 Damage to underground utilities
Cause : Incomplete utility maps, digging without prior detection
Consequence : Gas, power or water outage, explosion, injuries
12 P3×I4 • Utility maps and detection before digging
• Hand digging near utilities
R-014 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
12 P3×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-015 Poorly managed interfaces between work packages or teams
Cause : Unclear responsibilities at boundaries, information not passed on
Consequence : Omissions, duplication, delays and disputes
12 P4×I3 • Interface matrix
• Interface review at coordination meetings
R-016 Cash flow strain during the project
Cause : Late client payments, large supplier advances, no down payments
Consequence : Cascading late payments, costly borrowing
10 P2×I5 • Billing schedule aligned with progress
• Monthly cash flow plan
R-017 Contractual delay penalties
Cause : Tight deadlines, uncapped penalties, undocumented causes of delay
Consequence : Major financial losses, dispute with the client
10 P2×I5 • Cap penalties when negotiating
• Record causes of delay
R-018 Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance
Consequence : Unpaid invoices, lost revenue, cash strain
10 P2×I5 • Monitor key customers’ financial health
• Credit insurance or payment guarantees
R-019 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
10 P2×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-020 Trench or excavation collapse
Cause : No shoring, slopes too steep, waterlogged ground
Consequence : Burial, fatality
10 P2×I5 • Systematic shoring or battering
• Daily excavation inspection
R-021 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
10 P2×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-022 Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals
Consequence : Delayed start, idle teams, project to be redesigned
9 P3×I3 • Permit back-schedule
• Pre-application meeting with authorities
R-023 Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion
Consequence : Studies and works to redo, extra costs, delay
9 P3×I3 • Project-specific regulatory watch
• Change-in-law clause
R-024 Irregularity in a public procurement procedure
Cause : Thresholds misapplied, discriminatory criteria, insufficient advertising
Consequence : Annulment, appeals, liability of officials
8 P2×I4 • Legal review of tender documents
• Train public buyers
R-025 Assault on a front-desk or field officer
Cause : Tensions with users, lone work, unwelcome decisions
Consequence : Injuries, trauma, absenteeism
8 P2×I4 • Secure reception design
• Supported complaint and assistance
R-026 Accident or missing child at school or on an outing
Cause : Insufficient supervision, poorly prepared outings, uncontrolled access
Consequence : Injury, lost child, liability
8 P2×I4 • Supervision ratios and name list
• Building access control
R-027 Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections
Consequence : People trapped, car fall, accident
8 P2×I4 • Maintenance contract and periodic inspections
• Emergency phone and rescue procedure
R-028 Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination
Consequence : Injuries, panic, authority held responsible
8 P2×I4 • Safety meeting with police, fire and medical services
• Command post and cancellation procedure
R-029 Litigation over a permit or public decision
Cause : Appeals by residents or associations, insufficient reasoning, procedure not followed
Consequence : Project suspended, delays of months or years
8 P2×I4 • Early consultation and robust file
• Schedule including appeal period
R-030 Bribery or conflict of interest
Cause : Unregulated gifts or benefits, opaque intermediaries, untraced purchasing decisions
Consequence : Criminal proceedings, exclusion from public tenders, reputational damage
8 P2×I4 • Code of conduct and gifts register
• Conflict-of-interest declarations and dual purchase approval
R-031 Declining service quality for users
Cause : Long processing times, poor reception, difficult online procedures
Consequence : Dissatisfaction, complaints, loss of trust
6 P2×I3 • Time and satisfaction indicators
• Help for digitally excluded users
R-032 Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available
Consequence : Lost contracts, costlier financing, greenwashing accusations
6 P2×I3 • Collect key sustainability indicators
• Verifiable environmental claims
R-033 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan
R-034 Appeal or cancellation of the public tender
Cause : Questionable award criteria, procedural error
Consequence : Suspension, new procedure, months of delay
6 P2×I3 • Legal review of tender documents
• Traceable bid evaluation
R-035 Opposition from citizens or residents
Cause : Insufficient consultation, impacts poorly explained
Consequence : Appeals, negative media coverage, delay
6 P2×I3 • Early public consultation
• Contact point and request tracking

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Public building project”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.