Risk register example: Public building project
A school, sports hall or administrative building: procurement, funding, permits and public access.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Public sector · Planning / design · 40 people · public procurement, permits or authorisations required, work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), excavation, trenches, earthworks, several companies working at the same time, site open to the public, dense urban area, neighbours nearby, fixed-price contract.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
16 P4×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-002 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
15 P3×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-003 | Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground Consequence : Crushing, fatality, major damage |
15 P3×I5 | • Lifting plan for critical lifts • Qualified operators and slingers, inspected gear |
• No one under the load |
| R-004 | Lengthy administrative approval times
Cause : Multiple sign-off steps, postponed council or committee Consequence : Project delay, loss of grants |
12 P4×I3 | • Governance calendar in the schedule |
• Signature delegations for routine decisions |
| R-005 | Loss of a grant through non-compliance
Cause : Deadlines missed, missing evidence, ineligible expenses Consequence : Repayment, funding gap |
12 P3×I4 | • Grant conditions tracker |
• Early extension request |
| R-006 | Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing Consequence : Fractures, head injury |
12 P3×I4 | • Mobile platforms instead of ladders • Visual check before use |
|
| R-007 | Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below Consequence : Serious injury to people below, material damage |
12 P3×I4 | • Toe boards, nets and tethered tools |
• Marked exclusion zone below |
| R-008 | Funding cut or postponed
Cause : Budget trade-offs, political change, delayed grant Consequence : Project reduced, postponed or abandoned |
12 P3×I4 | • Phasing that allows a clean stop |
• Several funding sources |
| R-009 | Change in political priorities
Cause : Elections, change of majority or lead official, budget trade-offs Consequence : Project resized, suspended or abandoned |
12 P4×I3 | • Phasing in self-contained stages |
• Document benefits and decisions |
| R-010 | Rising interest rates and financing costs
Cause : Variable-rate borrowing, financing to renew during the project Consequence : Higher financial charges, lower profitability |
12 P3×I4 | • Fixed or capped rate |
• Rate scenario in the financing plan |
| R-011 | Loss of key skills in the administration
Cause : Retirements, recruitment difficulties, mobility Consequence : Slower processing, dependence on contractors |
12 P4×I3 | • Map critical skills |
• Documented procedures and pairs |
| R-012 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
12 P4×I3 | • External dependency log |
• Prepared workaround |
| R-013 | Damage to underground utilities
Cause : Incomplete utility maps, digging without prior detection Consequence : Gas, power or water outage, explosion, injuries |
12 P3×I4 | • Utility maps and detection before digging |
• Hand digging near utilities |
| R-014 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
12 P3×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-015 | Poorly managed interfaces between work packages or teams
Cause : Unclear responsibilities at boundaries, information not passed on Consequence : Omissions, duplication, delays and disputes |
12 P4×I3 | • Interface matrix |
• Interface review at coordination meetings |
| R-016 | Cash flow strain during the project
Cause : Late client payments, large supplier advances, no down payments Consequence : Cascading late payments, costly borrowing |
10 P2×I5 | • Billing schedule aligned with progress |
• Monthly cash flow plan |
| R-017 | Contractual delay penalties
Cause : Tight deadlines, uncapped penalties, undocumented causes of delay Consequence : Major financial losses, dispute with the client |
10 P2×I5 | • Cap penalties when negotiating |
• Record causes of delay |
| R-018 | Failure of a major customer
Cause : Customer in financial difficulty, revenue concentration, high outstanding balance Consequence : Unpaid invoices, lost revenue, cash strain |
10 P2×I5 | • Monitor key customers’ financial health |
• Credit insurance or payment guarantees |
| R-019 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
10 P2×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-020 | Trench or excavation collapse
Cause : No shoring, slopes too steep, waterlogged ground Consequence : Burial, fatality |
10 P2×I5 | • Systematic shoring or battering • Daily excavation inspection |
|
| R-021 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
10 P2×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-022 | Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals Consequence : Delayed start, idle teams, project to be redesigned |
9 P3×I3 | • Permit back-schedule • Pre-application meeting with authorities |
|
| R-023 | Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion Consequence : Studies and works to redo, extra costs, delay |
9 P3×I3 | • Project-specific regulatory watch |
• Change-in-law clause |
| R-024 | Irregularity in a public procurement procedure
Cause : Thresholds misapplied, discriminatory criteria, insufficient advertising Consequence : Annulment, appeals, liability of officials |
8 P2×I4 | • Legal review of tender documents • Train public buyers |
|
| R-025 | Assault on a front-desk or field officer
Cause : Tensions with users, lone work, unwelcome decisions Consequence : Injuries, trauma, absenteeism |
8 P2×I4 | • Secure reception design |
• Supported complaint and assistance |
| R-026 | Accident or missing child at school or on an outing
Cause : Insufficient supervision, poorly prepared outings, uncontrolled access Consequence : Injury, lost child, liability |
8 P2×I4 | • Supervision ratios and name list • Building access control |
|
| R-027 | Lift breakdown or accident
Cause : Insufficient maintenance, overdue statutory inspections Consequence : People trapped, car fall, accident |
8 P2×I4 | • Maintenance contract and periodic inspections |
• Emergency phone and rescue procedure |
| R-028 | Security incident during a public event
Cause : Unexpected attendance, threat, weather, poor coordination Consequence : Injuries, panic, authority held responsible |
8 P2×I4 | • Safety meeting with police, fire and medical services |
• Command post and cancellation procedure |
| R-029 | Litigation over a permit or public decision
Cause : Appeals by residents or associations, insufficient reasoning, procedure not followed Consequence : Project suspended, delays of months or years |
8 P2×I4 | • Early consultation and robust file |
• Schedule including appeal period |
| R-030 | Bribery or conflict of interest
Cause : Unregulated gifts or benefits, opaque intermediaries, untraced purchasing decisions Consequence : Criminal proceedings, exclusion from public tenders, reputational damage |
8 P2×I4 | • Code of conduct and gifts register • Conflict-of-interest declarations and dual purchase approval |
|
| R-031 | Declining service quality for users
Cause : Long processing times, poor reception, difficult online procedures Consequence : Dissatisfaction, complaints, loss of trust |
6 P2×I3 | • Time and satisfaction indicators |
• Help for digitally excluded users |
| R-032 | Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available Consequence : Lost contracts, costlier financing, greenwashing accusations |
6 P2×I3 | • Collect key sustainability indicators • Verifiable environmental claims |
|
| R-033 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
| R-034 | Appeal or cancellation of the public tender
Cause : Questionable award criteria, procedural error Consequence : Suspension, new procedure, months of delay |
6 P2×I3 | • Legal review of tender documents |
• Traceable bid evaluation |
| R-035 | Opposition from citizens or residents
Cause : Insufficient consultation, impacts poorly explained Consequence : Appeals, negative media coverage, delay |
6 P2×I3 | • Early public consultation |
• Contact point and request tracking |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.
In Risqure, choose “Public building project”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.