Risk register example: Works in a hospital
Building works in a running hospital: infection control, vulnerable patients, continuity of care.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Healthcare · Execution / works · 30 people · occupied site (staff, residents, patients nearby), vulnerable people (patients, children, elderly), electrical work or work near live installations, service must be available 24/7, noise or vibration, old building (asbestos, lead possible), several companies working at the same time, night or shift work.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
20 P4×I5 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-002 | Vulnerable people exposed to hazards
Cause : Patients, children or elderly people near the activity area Consequence : Serious accident, complaint, facility closure |
16 P4×I4 | • Joint risk assessment with the facility |
• On-site contact and alert procedure |
| R-003 | Medication error
Cause : Unclear prescriptions, interruptions during preparation Consequence : Serious adverse effect for the patient |
16 P4×I4 | • Double check for high-risk drugs • Interruption-free preparation area |
|
| R-004 | Patient fall
Cause : Reduced mobility, medication, cluttered environment, call bell out of reach Consequence : Fracture, longer stay, complaint from the family |
16 P4×I4 | • Fall risk assessment on admission |
• Review every fall |
| R-005 | Diagnostic error or delay
Cause : Workload, tests not followed up, results not passed on, cognitive bias Consequence : Wrong or late treatment, deterioration, complaint |
16 P4×I4 | • Systematic tracking of pending results • Second opinion for complex cases |
|
| R-006 | Delayed response to a life-threatening emergency
Cause : Late alert, incomplete crash cart, untrained staff Consequence : Avoidable death or after-effects |
15 P3×I5 | • Regular emergency skills training |
• Daily crash cart check |
| R-007 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
15 P5×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-008 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-009 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
15 P5×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-010 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-011 | Wrong-site or wrong-patient surgery
Cause : No checklist, site marking omitted, team change Consequence : Operation on the wrong side or patient |
15 P3×I5 | • Surgical safety checklist • Surgical site marking |
|
| R-012 | Patient identification error
Cause : Same names, no wristband, unsystematic checks Consequence : Care or treatment given to the wrong person |
12 P3×I4 | • Two identifiers at every step • Identification wristband |
|
| R-013 | Absconding or missing vulnerable patient
Cause : Cognitive impairment, unsupervised exits, unsecured doors Consequence : Patient in danger, search, liability |
12 P3×I4 | • Secure exits and alert devices |
• Immediate search procedure |
| R-014 | Pressure ulcers or malnutrition in residents
Cause : Reduced mobility, unsuitable meals, insufficient weight monitoring Consequence : Complications, hospital admissions, complaints |
12 P4×I3 | • Risk assessment and repositioning • Monthly weighing and adapted meals |
|
| R-015 | Healthcare-associated infection
Cause : Poor hand hygiene, protocols not followed Consequence : Patient complications, investigation |
12 P3×I4 | • Hand hygiene audits |
• Case reporting and analysis |
| R-016 | Shortage of care staff
Cause : Hiring difficulties, absenteeism Consequence : Overload, lower quality and safety of care |
12 P4×I3 | • Internal relief pool |
• Minimum safe staffing levels |
| R-017 | Cyberattack crippling care systems
Cause : Unpatched workstations, vulnerable connected medical devices, phishing Consequence : Cancelled care, patient transfers, health data leak |
12 P3×I4 | • Network segmentation and updates |
• Downtime care procedures |
| R-018 | Burnout among care staff
Cause : Emotional load, shift work, chronic understaffing Consequence : Absenteeism, resignations, lower quality of care |
12 P4×I3 | • Stable rotas and protected rest |
• Debriefing spaces and psychological support |
| R-019 | Heatwave effects on frail patients and residents
Cause : Rooms not cooled, poor hydration, reduced summer staffing Consequence : Dehydration, hospital admissions, deaths |
10 P2×I5 | • Cooled rooms and heatwave plan |
• Identify the most vulnerable |
| R-020 | Sepsis not recognised in time
Cause : Warning signs not monitored, no early warning score, late escalation Consequence : Septic shock, avoidable death |
10 P2×I5 | • Early warning score and sepsis protocol |
• Rapid response team |
| R-021 | Hospital-acquired venous thrombosis
Cause : Risk assessment not done, prophylaxis missed, prolonged immobility Consequence : Pulmonary embolism, death |
10 P2×I5 | • Thrombosis risk assessment on admission • Early mobilisation |
|
| R-022 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-023 | Moving and handling people
Cause : Transfers of patients or residents without equipment, staff alone Consequence : Low back pain, injuries to carer and patient |
9 P3×I3 | • Transfer aids • Training in people-handling techniques |
|
| R-024 | Blood exposure incident
Cause : Needlestick or cut with a contaminated item, full containers, recapping Consequence : Infection risk, anxiety, medical follow-up |
9 P3×I3 | • Safety devices and containers within reach |
• Displayed procedure |
| R-025 | Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations Consequence : Stress, verbal aggression, staff burnout |
9 P3×I3 | • Conflict-management training |
• Post-incident support and reporting |
| R-026 | Shortage of essential medicines or devices
Cause : Manufacturer stock-out, higher demand, single supplier Consequence : Treatments postponed or substituted, risk of error |
9 P3×I3 | • Shortage watch and safety stock |
• Validated substitution protocols |
| R-027 | Backup power failure
Cause : Generator or UPS not tested, insufficient fuel Consequence : Vital equipment stops during a power cut |
8 P2×I4 | • Regular load tests |
• Fuel reserve and supply contract |
| R-028 | Electronic health record unavailable
Cause : Outage, maintenance, cyberattack Consequence : No access to history and treatments, delays and errors |
8 P2×I4 | • Downtime procedure and backup printouts • Re-entry and checks after recovery |
|
| R-029 | Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response Consequence : Loss of trust, lost customers, pressure from authorities |
8 P2×I4 | • Crisis communication procedure • Quick-reaction sheet and press contacts |
|
| R-030 | Medical device failure or malfunction
Cause : Untracked maintenance, old equipment, misuse Consequence : Interrupted care, measurement error, patient incident |
8 P2×I4 | • Device inventory and maintenance |
• Report device incidents |
| R-031 | Sterilisation failure of medical devices
Cause : Non-compliant cycle, incomplete traceability, damaged packaging Consequence : Infection, patient recall, surgery suspended |
8 P2×I4 | • Cycle validation and daily checks |
• Instrument traceability per patient |
| R-032 | Overexposure to ionising radiation
Cause : Repeated scans, unsuitable settings, insufficient staff protection Consequence : Excessive dose for patients and staff |
6 P2×I3 | • Justify and optimise examinations |
• Dosimetry and protective equipment |
| R-033 | Lack of patient information or consent
Cause : Incomplete information, no written record, language barrier Consequence : Complaint, liability claim |
6 P2×I3 | • Information leaflets and records • Use interpreters |
|
| R-034 | Exposure to biological agents
Cause : Contact with sick people, waste, animals or contaminated water Consequence : Infections, absences |
6 P2×I3 | • Hand hygiene and recommended vaccination |
• Protective equipment and exposure procedure |
| R-035 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.