Risk register example: Warehouse opening

Opening a logistics site: racking, forklifts, IT systems, recruitment and ramp-up.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate18
● High14
● Critical3

Assumptions: Logistics / transport · Planning / design · 40 people · site vehicles, forklifts, construction machinery, heavy or repetitive manual handling, work at height (roofs, scaffolding, platforms), night or shift work, new or temporary team, integration with existing systems, tight or immovable deadline.

Ref.RiskScorePreventionProtection
R-001 Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused
Consequence : Serious injury or death, investigation, site stoppage
20 P4×I5 • Collective protection before any access
• Scaffold handover and daily check
• Rescue-at-height plan
R-002 Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer
Consequence : Rushed work, mistakes, penalties, lower quality
16 P4×I4 • Phased delivery
• Pre-identified extra resources
R-003 Person struck by a vehicle or forklift
Cause : Pedestrians and vehicles sharing routes, poor visibility, reversing
Consequence : Serious injury or death
15 P3×I5 • Traffic plan separating pedestrians and vehicles
• Alarms, reversing cameras and hi-vis
R-004 Fall from a ladder or stepladder
Cause : Ladder used as a workstation, damaged equipment, poor footing
Consequence : Fractures, head injury
12 P3×I4 • Mobile platforms instead of ladders
• Visual check before use
R-005 Musculoskeletal disorders among order pickers
Cause : Repeated loads, high rates, picking at floor or high levels
Consequence : Back pain, sick leave, turnover
12 P4×I3 • Slotting by weight and turnover
• Handling aids
R-006 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-007 Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes
Consequence : Sprains, fractures, sick leave
12 P4×I3 • Housekeeping and clear walkways
• Lighting and suitable footwear
R-008 Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures
Consequence : Chronic pain, sick leave, unfitness for work
12 P4×I3 • Handling aids
• Task rotation and handling training
R-009 Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation
Consequence : Tendinitis, carpal tunnel syndrome, sick leave
12 P4×I3 • Ergonomic analysis of repetitive tasks
• Job rotation
R-010 Falling objects from height
Cause : Unsecured materials and tools, no exclusion zone below
Consequence : Serious injury to people below, material damage
12 P3×I4 • Toe boards, nets and tethered tools
• Marked exclusion zone below
R-011 Forklift accident
Cause : Untrained drivers, cluttered aisles, excessive speed
Consequence : Serious injury, damage to stock and racks
12 P3×I4 • Driving authorisation and training
• Clear aisles and speed limits
R-012 Rising fuel and energy costs
Cause : Price volatility, fuel-hungry fleet, contracts without indexation
Consequence : Lower margins, uncompetitive transport prices
12 P3×I4 • Fuel indexation clause
• Eco-driving and route optimisation
R-013 Difficulty recruiting qualified staff
Cause : Labour shortage, uncompetitive pay, long hiring times
Consequence : Vacant positions, delays, team overload
12 P4×I3 • Anticipate skill needs
• Partnerships and in-house training
R-014 Difficult integration with existing systems
Cause : Poorly documented interfaces, inconsistent data formats
Consequence : Delays, degraded features, double data entry
12 P3×I4 • Early interface inventory and tests
• Manual workaround
R-015 Compromise through a supplier or third-party software
Cause : Provider with broad access, tampered software update, poorly assessed dependency
Consequence : Intrusion via the supply chain, data leak, business interruption
12 P3×I4 • Security assessment of critical suppliers
• Limited and logged supplier access
R-016 Pedestrian struck by a delivery vehicle on site
Cause : Pedestrian and vehicle areas not separated, reversing, blind spots
Consequence : Serious or fatal injuries
10 P2×I5 • Physical separation of traffic
• Traffic plan and driver instructions
R-017 Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people
Consequence : Crushing, fractures, death
10 P2×I5 • Marked exclusion zones
• Audible and visual movement warnings
R-018 Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection
Consequence : Lacerations, tendon injuries
9 P3×I3 • Retractable-blade tools
• Suitable cut-resistant gloves
R-019 Customer delivery delays
Cause : Carrier capacity shortage, road disruption, activity peaks
Consequence : Customer stock-outs, penalties
9 P3×I3 • Shared volume forecasts
• Alternative carriers
R-020 Peak activity without enough resources
Cause : Seasonality, promotions, untrained temporary staff, late hiring
Consequence : Picking errors, accidents, delivery delays
9 P3×I3 • Workload forecast shared with customers
• Induction and training of temporary staff
R-021 New or temporary team unfamiliar with the rules
Cause : Insufficient induction and training, turnover
Consequence : Mistakes, accidents, procedures not followed
9 P3×I3 • Mandatory safety and job induction
• Mentoring by an experienced colleague
R-022 Fatigue and reduced alertness from night work
Cause : Shifted hours, insufficient sleep, poor lighting
Consequence : Mistakes, accidents, health problems
9 P3×I3 • Shift and break planning
• Adequate lighting everywhere
R-023 Accident involving a new or temporary worker
Cause : No safety induction, unfamiliar site and rules, pressure to produce
Consequence : Accidents in the first weeks
9 P3×I3 • Systematic safety induction
• Buddy system in the first weeks
R-024 Raw material shortage
Cause : Tight markets, failing supplier
Consequence : Reduced production, higher costs
9 P3×I3 • Dual sourcing of critical materials
• Sized safety stock
R-025 Backups that cannot be restored
Cause : Backups never tested, incomplete or encrypted by the attacker
Consequence : Permanent data loss after an incident
9 P3×I3 • Quarterly restore test
• Offline or immutable copy
R-026 IT system obsolescence
Cause : Software or equipment without vendor support, scarce skills
Consequence : Unfixable vulnerabilities, breakdowns, emergency migration costs
9 P3×I3 • Multi-year renewal plan
• Isolate legacy systems
R-027 Accident during tail-lift loading or unloading
Cause : Faulty tail lift, unstable load, slope
Consequence : Crushed feet, falling load
8 P2×I4 • Periodic tail-lift inspection
• Safety shoes and stops
R-028 Warehouse management system failure
Cause : Failed update, faulty interface, unavailable server
Consequence : Picking blocked, shipments delayed, customer penalties
8 P2×I4 • Tested updates outside peak periods
• Degraded operating procedure
R-029 Load falling from an overhead crane
Cause : Worn slings, incorrect rigging, overload
Consequence : Crushing, material damage
8 P2×I4 • Check lifting accessories
• Train riggers and crane operators
R-030 Racking collapse
Cause : Damaged racks, overloading, no inspection
Consequence : Injuries, loss of goods
8 P2×I4 • Annual inspection and load signs
• Upright protectors
R-031 Fall or crushing at the loading dock
Cause : Truck driving off unexpectedly, unsecured dock, poor visibility
Consequence : Forklift or person falling, crushing
8 P2×I4 • Wheel chocks or vehicle restraint at the dock
• Dock signals and lighting
R-032 Theft of goods or cargo
Cause : Weak access control, unsecured parking, internal complicity
Consequence : Losses, customer disputes, higher insurance premiums
8 P2×I4 • Access control and CCTV
• Goods-in-transit insurance
R-033 Risks for pregnant or breastfeeding workers
Cause : Exposure to substances, strain or night work not adapted
Consequence : Harm to mother or child, non-compliance
6 P2×I3 • Specific assessment once pregnancy is announced
• List of at-risk jobs prepared in advance
R-034 Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose
Consequence : Soil and water pollution, costly clean-up
6 P2×I3 • Sealed refuelling area
• Spill kit and response procedure
R-035 Picking and delivery errors
Cause : Mixed-up items, labelling, pressure on rates
Consequence : Returns, rework costs, customer dissatisfaction
6 P2×I3 • Barcode scanning checks
• Error analysis and team feedback

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Warehouse opening”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free