Risk register example: International supply chain
Sourcing from abroad: lead times, customs, supplier failure, quality and currency.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Logistics / transport · Operation · 10 people · suppliers outside europe or long lead times, critical item from a single supplier, tight or immovable deadline, several sites.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-002 | Cargo theft at a parking area
Cause : Stops at unsecured parking, curtains slashed, high-value goods Consequence : Losses, delays, insurance disputes |
12 P3×I4 | • Plan stops at secure parking |
• Tracking and trailer alarms |
| R-003 | Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier Consequence : Production or site stoppage, delays, penalties |
12 P3×I4 | • Map tier-1 and tier-2 suppliers |
• Safety stock for critical components |
| R-004 | Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified Consequence : Financial loss often unrecoverable |
12 P3×I4 | • Call-back for any bank detail change • Dual approval of transfers |
|
| R-005 | Supply disruption of a critical item
Cause : Single supplier, no qualified alternative Consequence : Work or production stopped while waiting for delivery |
12 P3×I4 | • Qualify a second supplier |
• Safety stock |
| R-006 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-007 | Forklift accident
Cause : Untrained drivers, cluttered aisles, excessive speed Consequence : Serious injury, damage to stock and racks |
12 P3×I4 | • Driving authorisation and training • Clear aisles and speed limits |
|
| R-008 | Adverse exchange rate movements
Cause : Purchases or sales in foreign currency, long delays between order and payment Consequence : Reduced margin, unpredictable cost price |
12 P3×I4 | • Invoice in euros where possible |
• Currency hedging for large amounts |
| R-009 | Rising fuel and energy costs
Cause : Price volatility, fuel-hungry fleet, contracts without indexation Consequence : Lower margins, uncompetitive transport prices |
12 P3×I4 | • Fuel indexation clause |
• Eco-driving and route optimisation |
| R-010 | Internal fraud or embezzlement
Cause : Insufficient segregation of duties, rare accounting checks, shared bank access Consequence : Financial losses, misstated accounts, dispute and proceedings |
10 P2×I5 | • Segregation of duties for payments |
• Bank reconciliations and surprise checks |
| R-011 | Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers Consequence : Extra costs, customs delays, closed markets |
9 P3×I3 | • Customs watch and product origin |
• Alternative suppliers in other regions |
| R-012 | Subcontracted carrier failure
Cause : Insufficient peak capacity, bankruptcy, poor service quality Consequence : Missed deliveries, penalties, unhappy customers |
9 P3×I3 | • Panel of qualified carriers |
• Reserved backup capacity at peaks |
| R-013 | Delayed delivery from abroad
Cause : Long transport, customs, international logistics disruptions Consequence : Equipment unavailable on schedule, timeline shifted |
9 P3×I3 | • Early ordering and shipment tracking |
• Local substitute solution |
| R-014 | Customer delivery delays
Cause : Carrier capacity shortage, road disruption, activity peaks Consequence : Customer stock-outs, penalties |
9 P3×I3 | • Shared volume forecasts |
• Alternative carriers |
| R-015 | Peak activity without enough resources
Cause : Seasonality, promotions, untrained temporary staff, late hiring Consequence : Picking errors, accidents, delivery delays |
9 P3×I3 | • Workload forecast shared with customers • Induction and training of temporary staff |
|
| R-016 | Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions Consequence : Chronic stress, errors, accidents, absenteeism |
9 P3×I3 | • Realistic workload planning |
• Spot warning signs |
| R-017 | Resources shared across several projects
Cause : Experts assigned to several projects, conflicting priorities Consequence : Cascading delays, overload |
9 P3×I3 | • Portfolio resource plan |
• Written availability commitment |
| R-018 | Ineffective meetings and excessive reporting
Cause : Meetings without agenda, multiple reports, less productive time Consequence : Demotivated team, delays |
9 P3×I3 | • Short meetings with agenda and decisions • Single dashboard |
|
| R-019 | Breach of international sanctions or export controls
Cause : Sanctioned customer, supplier or good not detected, dual-use items Consequence : Fines, blocked payments, prosecution |
8 P2×I4 | • Screen partners against sanctions lists • Classify sensitive products |
|
| R-020 | Racking collapse
Cause : Damaged racks, overloading, no inspection Consequence : Injuries, loss of goods |
8 P2×I4 | • Annual inspection and load signs |
• Upright protectors |
| R-021 | Fall or crushing at the loading dock
Cause : Truck driving off unexpectedly, unsecured dock, poor visibility Consequence : Forklift or person falling, crushing |
8 P2×I4 | • Wheel chocks or vehicle restraint at the dock • Dock signals and lighting |
|
| R-022 | Theft of goods or cargo
Cause : Weak access control, unsecured parking, internal complicity Consequence : Losses, customer disputes, higher insurance premiums |
8 P2×I4 | • Access control and CCTV |
• Goods-in-transit insurance |
| R-023 | Falling load from poor securing
Cause : Load not strapped, unstable pallets, sudden braking Consequence : Injury during unloading, road accident, damaged goods |
8 P2×I4 | • Load-securing rules and equipment |
• Open doors carefully when unloading |
| R-024 | Lithium battery fire
Cause : Charging of vehicle or tool batteries in unsuitable areas, damaged batteries Consequence : Fire hard to extinguish, toxic smoke, building destroyed |
8 P2×I4 | • Dedicated ventilated charging area |
• Fire detection and quarantine of damaged batteries |
| R-025 | Customs clearance error
Cause : Wrong tariff classification, missing documents, incorrect origin Consequence : Goods held, reassessments, fines |
6 P2×I3 | • Use a competent customs broker • Product sheets with code and origin |
|
| R-026 | Shortage of critical raw materials or components
Cause : Geopolitical tension, concentrated production, global demand Consequence : Delays, price rises, redesign |
6 P2×I3 | • Identify at-risk components |
• Design allowing alternatives |
| R-027 | Instructions misunderstood because of language
Cause : Multilingual teams, written-only instructions, technical jargon Consequence : Errors, accidents, procedures not followed |
6 P2×I3 | • Illustrated and translated instructions • Check understanding |
|
| R-028 | Picking and delivery errors
Cause : Mixed-up items, labelling, pressure on rates Consequence : Returns, rework costs, customer dissatisfaction |
6 P2×I3 | • Barcode scanning checks |
• Error analysis and team feedback |
| R-029 | Different practices from one site to another
Cause : No common standard, teams far apart Consequence : Uneven quality, errors in handovers between sites |
6 P3×I2 | • Common standard and site lead |
• Cross-site audits |
| R-030 | Harassment or discrimination at work
Cause : Inappropriate behaviour tolerated, no reporting procedure Consequence : Victims’ suffering, proceedings, resignations, reputational damage |
6 P2×I3 | • Clear rules and manager training |
• Confidential reporting channel |
| R-031 | Energy use and emissions above targets
Cause : Energy-intensive equipment, no monitoring, habits Consequence : Higher costs, climate targets missed |
6 P3×I2 | • Monthly consumption tracking • Energy efficiency plan |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.