Risk register example: Shop opening

Opening a store: fit-out, stock, payments, theft, staff and footfall.

Adapt it to my project (free) Download for Excel (CSV)

Risks35
● Low0
● Moderate26
● High7
● Critical2

Assumptions: Hospitality / retail · Planning / design · 6 people · shop or sales counter, site open to the public, online payments, heavy or repetitive manual handling, tight or immovable deadline, dense urban area, neighbours nearby, personal data processed.

Ref.RiskScorePreventionProtection
R-001 Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer
Consequence : Rushed work, mistakes, penalties, lower quality
16 P4×I4 • Phased delivery
• Pre-identified extra resources
R-002 Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration
Consequence : Mandatory notification, loss of trust, fines, claims
15 P3×I5 • Least-privilege access management
• Breach notification procedure
R-003 MSDs among cashiers and shelf stackers
Cause : Repetitive movements, carrying loads, prolonged standing
Consequence : Pain, sick leave
12 P4×I3 • Ergonomic checkouts
• Task rotation and shelving aids
R-004 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-005 Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas
Consequence : Third-party injury, complaint, civil liability
12 P3×I4 • Solid fencing and controlled access
• Schedule hazardous work when areas are empty
R-006 Musculoskeletal disorders
Cause : Heavy loads, repetitive movements, awkward postures
Consequence : Chronic pain, sick leave, unfitness for work
12 P4×I3 • Handling aids
• Task rotation and handling training
R-007 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-008 Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation
Consequence : Tendinitis, carpal tunnel syndrome, sick leave
12 P4×I3 • Ergonomic analysis of repetitive tasks
• Job rotation
R-009 Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services
Consequence : Worsened injuries, avoidable death
10 P2×I5 • Trained first-aiders on every shift
• Defibrillator and access plan for emergency services
R-010 Verbal or physical violence from shop customers
Cause : Shoplifting interrupted, waiting, refusal of sale, alcohol
Consequence : Injuries, stress, absenteeism
9 P3×I3 • No physical intervention rule
• Support and reporting after incidents
R-011 Voice or video impersonation fraud (deepfake)
Cause : AI-generated call or video meeting imitating an executive or supplier
Consequence : Fraudulent transfer, disclosure of information
9 P3×I3 • Code word and call-back for sensitive requests
• Deepfake awareness
R-012 Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations
Consequence : Stress, verbal aggression, staff burnout
9 P3×I3 • Conflict-management training
• Post-incident support and reporting
R-013 Slip, trip or fall
Cause : Slippery floors, obstacles, poor lighting
Consequence : Injuries to staff or customers
9 P3×I3 • Immediate cleaning and signage
• Anti-slip flooring and suitable shoes
R-014 Seasonal drop in customers
Cause : Seasonality, competition, economic climate
Consequence : Revenue too low to cover fixed costs
9 P3×I3 • Low-season offers and events
• Cash reserve
R-015 High turnover and seasonal staff shortage
Cause : Demanding conditions, split shifts, unattractive pay
Consequence : Poorer service, overload, closing some days
9 P3×I3 • Early hiring and seasonal staff retention
• Rotas known in advance
R-016 Bad online reviews and declining reputation
Cause : Negative customer experiences, no responses, fake reviews
Consequence : Fewer customers and lower revenue
9 P3×I3 • Collect feedback on site
• Fast, professional responses to reviews
R-017 Shrinkage and stock losses in store
Cause : External and internal theft, receiving errors, breakage
Consequence : Lower margin, inventory discrepancies
9 P3×I3 • Security tags, CCTV and receiving checks
• Cycle counts
R-018 Rising rent and occupancy costs
Cause : Lease review, indexation, energy charges
Consequence : Lower profitability
9 P3×I3 • Negotiate lease clauses
• Track rent-to-sales ratio
R-019 No cyber incident response plan
Cause : Roles undefined, emergency contacts unknown, notification duties ignored
Consequence : Slow reaction, greater damage, penalties for late notification
8 P2×I4 • One-page response plan and emergency contacts
• Annual cyber crisis exercise
R-020 Malicious act by an employee or former employee
Cause : Access not removed on departure, excessive rights, labour dispute
Consequence : Data theft or destruction, sabotage
8 P2×I4 • Leaver procedure with same-day access removal
• Six-monthly access review
R-021 Internal fraud or embezzlement
Cause : Insufficient segregation of duties, rare accounting checks, shared bank access
Consequence : Financial losses, misstated accounts, dispute and proceedings
8 P2×I4 • Segregation of duties for payments
• Bank reconciliations and surprise checks
R-022 Poorly managed emergency evacuation
Cause : No instructions, inaudible alarm, untrained staff
Consequence : Panic, injuries during evacuation
8 P2×I4 • Evacuation plan and drill
• Safety PA system and assembly point
R-023 Malicious act or intrusion
Cause : Insufficient access control, unchecked items
Consequence : Theft, vandalism, assault, serious threat
8 P2×I4 • Access control and searches if needed
• Liaison with the police
R-024 Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response
Consequence : Loss of trust, lost customers, pressure from authorities
8 P2×I4 • Crisis communication procedure
• Quick-reaction sheet and press contacts
R-025 Fire in the kitchen or premises
Cause : Greasy hoods and ducts, fryers, electrical installations, cigarette ends
Consequence : Premises destroyed, guests evacuated, long closure
8 P2×I4 • Periodic cleaning of hoods and ducts
• Suitable extinguishers and evacuation drills
R-026 Fall in the cold room or storeroom
Cause : Wet or icy floor, high shelving, poor lighting
Consequence : Sprains, fractures
8 P2×I4 • Non-slip floors and storage at body height
• Stable step and lighting
R-027 Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads
Consequence : Sprains, fractures
8 P2×I4 • Anti-slip nosings and handrails
• Hoists or trolleys for loads
R-028 Accessibility or fire safety non-compliance of the premises
Cause : Fit-out works without checking applicable rules
Consequence : Opening refused, formal notice, extra works
6 P2×I3 • Regulatory check before works
• Inspection before opening
R-029 Till or card payment failure
Cause : Network outage, terminal failure, payment provider down
Consequence : Lost sales, queues
6 P2×I3 • Backup terminal and mobile connection
• Degraded sales procedure
R-030 Hacked or defaced website
Cause : Outdated content management system and plug-ins, weak passwords
Consequence : Hijacked site, malware served to visitors, removal from search results
6 P2×I3 • Automatic updates and fewer plug-ins
• Integrity monitoring and site backup
R-031 Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available
Consequence : Lost contracts, costlier financing, greenwashing accusations
6 P2×I3 • Collect key sustainability indicators
• Verifiable environmental claims
R-032 Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests
Consequence : Challenges, delays, abandonment
6 P2×I3 • Stakeholder map
• Tailored communication plan
R-033 Denial-of-service attack on the website or application
Cause : Exposed service without flood protection, hacktivism or extortion
Consequence : Site unavailable, lost sales, reputational damage
6 P2×I3 • DDoS protection at the host or a CDN
• Maintenance page and crisis messages ready
R-034 Assault or robbery at the till
Cause : Cash in the till, late opening hours, staff alone
Consequence : Injuries, trauma, financial losses
6 P2×I3 • Limit cash and do not close alone
• Robbery instructions
R-035 Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media
Consequence : Loss of trust, lower activity, media crisis
6 P2×I3 • Monitor online mentions
• Ready messages and spokesperson

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Shop opening”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples