Risk register example: Hotel renovation
Renovating a hotel, often while open: guests, noise, fire safety, reopening date and reputation.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Hospitality / retail · Execution / works · 25 people · occupied site (staff, residents, patients nearby), site open to the public, old building (asbestos, lead possible), electrical work or work near live installations, several companies working at the same time, tight or immovable deadline, dense urban area, neighbours nearby.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Accident caused by simultaneous work of several companies
Cause : Uncoordinated simultaneous work, no prevention plan Consequence : Serious accident, shared liability, site stoppage |
20 P5×I4 | • Prevention plan and joint inspection • Daily coordination of work |
|
| R-002 | Accident involving occupants or the public
Cause : Work area poorly separated from occupied areas Consequence : Third-party injury, complaint, civil liability |
16 P4×I4 | • Solid fencing and controlled access • Schedule hazardous work when areas are empty |
|
| R-003 | Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer Consequence : Rushed work, mistakes, penalties, lower quality |
16 P4×I4 | • Phased delivery |
• Pre-identified extra resources |
| R-004 | Inadequate first aid after an accident or collapse
Cause : First-aiders absent or untrained, no defibrillator, difficult access for emergency services Consequence : Worsened injuries, avoidable death |
15 P3×I5 | • Trained first-aiders on every shift • Defibrillator and access plan for emergency services |
|
| R-005 | Exposure to asbestos or lead
Cause : Missing or incomplete pre-works survey on an old building Consequence : Serious delayed illness, works stopped, costly unplanned removal |
15 P3×I5 | • Asbestos and lead survey before works |
• Stop-work procedure on discovery |
| R-006 | Electric shock or electrocution
Cause : Work near live parts, incomplete isolation Consequence : Severe burns, death, fire |
15 P3×I5 | • Electrical isolation and voltage check • Up-to-date electrical authorisations |
|
| R-007 | Verbal or physical violence from shop customers
Cause : Shoplifting interrupted, waiting, refusal of sale, alcohol Consequence : Injuries, stress, absenteeism |
12 P4×I3 | • No physical intervention rule |
• Support and reporting after incidents |
| R-008 | Fall on stairs
Cause : Slippery or damaged steps, poor lighting, carrying loads Consequence : Sprains, fractures |
12 P3×I4 | • Anti-slip nosings and handrails • Hoists or trolleys for loads |
|
| R-009 | Poorly prepared emergency evacuation
Cause : Blocked exits, inaudible alarm, no drills, people with reduced mobility forgotten Consequence : Casualties during a fire or leak |
12 P3×I4 | • Annual evacuation drill |
• Appointed evacuation wardens |
| R-010 | Malicious act or intrusion
Cause : Insufficient access control, unchecked items Consequence : Theft, vandalism, assault, serious threat |
12 P3×I4 | • Access control and searches if needed |
• Liaison with the police |
| R-011 | Slip, trip or fall
Cause : Slippery floors, obstacles, poor lighting Consequence : Injuries to staff or customers |
12 P4×I3 | • Immediate cleaning and signage • Anti-slip flooring and suitable shoes |
|
| R-012 | Seasonal drop in customers
Cause : Seasonality, competition, economic climate Consequence : Revenue too low to cover fixed costs |
12 P3×I4 | • Low-season offers and events |
• Cash reserve |
| R-013 | Fire in the kitchen or premises
Cause : Greasy hoods and ducts, fryers, electrical installations, cigarette ends Consequence : Premises destroyed, guests evacuated, long closure |
12 P3×I4 | • Periodic cleaning of hoods and ducts |
• Suitable extinguishers and evacuation drills |
| R-014 | Fall in the cold room or storeroom
Cause : Wet or icy floor, high shelving, poor lighting Consequence : Sprains, fractures |
12 P3×I4 | • Non-slip floors and storage at body height • Stable step and lighting |
|
| R-015 | Bad online reviews and declining reputation
Cause : Negative customer experiences, no responses, fake reviews Consequence : Fewer customers and lower revenue |
12 P3×I4 | • Collect feedback on site |
• Fast, professional responses to reviews |
| R-016 | Shrinkage and stock losses in store
Cause : External and internal theft, receiving errors, breakage Consequence : Lower margin, inventory discrepancies |
12 P3×I4 | • Security tags, CCTV and receiving checks |
• Cycle counts |
| R-017 | Rising rent and occupancy costs
Cause : Lease review, indexation, energy charges Consequence : Lower profitability |
12 P3×I4 | • Negotiate lease clauses |
• Track rent-to-sales ratio |
| R-018 | Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours Consequence : Burnout, absenteeism, resignations, errors |
12 P4×I3 | • Workload monitoring |
• Confidential counsellor and support |
| R-019 | Nuisance and complaints from neighbours
Cause : Noise, dust, vibration, traffic and parking Consequence : Complaints, imposed working-hour restrictions, delay |
9 P3×I3 | • Neighbour information and dedicated contact • Dust control and suitable hours |
|
| R-020 | Noise exceeding permitted limits
Cause : Noisy equipment, night work, no measurements Consequence : Complaints, enforced stoppage, fines |
9 P3×I3 | • Quieter equipment and acoustic screens |
• Noise measurements and adapted hours |
| R-021 | Dealing with difficult customers, users or patients
Cause : Waiting, frustration, repeated conflict situations Consequence : Stress, verbal aggression, staff burnout |
9 P3×I3 | • Conflict-management training |
• Post-incident support and reporting |
| R-022 | Striking an object or obstacle
Cause : Clutter, temporary storage in walkways, badly placed furniture Consequence : Bruises, cuts, falls |
9 P3×I3 | • Daily tidy-up and defined storage areas • Regular safety walks |
|
| R-023 | Assault or robbery at the till
Cause : Cash in the till, late opening hours, staff alone Consequence : Injuries, trauma, financial losses |
9 P3×I3 | • Limit cash and do not close alone |
• Robbery instructions |
| R-024 | High turnover and seasonal staff shortage
Cause : Demanding conditions, split shifts, unattractive pay Consequence : Poorer service, overload, closing some days |
9 P3×I3 | • Early hiring and seasonal staff retention • Rotas known in advance |
|
| R-025 | Dependency on an external deliverable
Cause : Waiting for a study, equipment or third-party decision Consequence : Critical path blocked, delay |
9 P3×I3 | • External dependency log |
• Prepared workaround |
| R-026 | Poorly managed interfaces between work packages or teams
Cause : Unclear responsibilities at boundaries, information not passed on Consequence : Omissions, duplication, delays and disputes |
9 P3×I3 | • Interface matrix |
• Interface review at coordination meetings |
| R-027 | Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions Consequence : Chronic stress, errors, accidents, absenteeism |
9 P3×I3 | • Realistic workload planning |
• Spot warning signs |
| R-028 | Media crisis after an incident
Cause : Accident, complaint or error made public, late or clumsy response Consequence : Loss of trust, lost customers, pressure from authorities |
8 P2×I4 | • Crisis communication procedure • Quick-reaction sheet and press contacts |
|
| R-029 | Accessibility or fire safety non-compliance of the premises
Cause : Fit-out works without checking applicable rules Consequence : Opening refused, formal notice, extra works |
6 P2×I3 | • Regulatory check before works • Inspection before opening |
|
| R-030 | Stakeholder opposition or disengagement
Cause : Stakeholders not identified, late consultation, conflicting interests Consequence : Challenges, delays, abandonment |
6 P2×I3 | • Stakeholder map |
• Tailored communication plan |
| R-031 | Sustainability requirements not met
Cause : Customers, lenders or regulation demanding carbon or social data that is not available Consequence : Lost contracts, costlier financing, greenwashing accusations |
6 P2×I3 | • Collect key sustainability indicators • Verifiable environmental claims |
|
| R-032 | Online disinformation or smear campaign
Cause : Rumours, fake reviews, manipulated content spread on social media Consequence : Loss of trust, lower activity, media crisis |
6 P2×I3 | • Monitor online mentions • Ready messages and spokesperson |
|
| R-033 | Poor indoor air quality
Cause : Insufficient ventilation, emissive products, dense occupancy Consequence : Discomfort, headaches, absenteeism, spread of infections |
6 P2×I3 | • CO2 sensors and ventilation maintenance • Low-emission materials and products |
|
| R-034 | No up-to-date risk assessment
Cause : Document not updated after a change, new risks not identified Consequence : Avoidable accidents, non-compliance on inspection |
6 P2×I3 | • Annual review and after every change • Worker participation |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.