Risk register example: Product launch

Bringing a product to market: quality, suppliers, launch date, compliance and reputation.

Adapt it to my project (free) Download for Excel (CSV)

Risks22
● Low0
● Moderate16
● High4
● Critical2

Assumptions: Other · Planning / design · 10 people · tight or immovable deadline, critical item from a single supplier, suppliers outside europe or long lead times, new technology or method, online payments.

Ref.RiskScorePreventionProtection
R-001 Unachievable end date
Cause : Imposed deadline with no margin, tasks chained without buffer
Consequence : Rushed work, mistakes, penalties, lower quality
16 P4×I4 • Phased delivery
• Pre-identified extra resources
R-002 Data breach
Cause : Application vulnerability, excessive access rights, misconfiguration
Consequence : Mandatory notification, loss of trust, fines, claims
15 P3×I5 • Least-privilege access management
• Breach notification procedure
R-003 Supply chain disruption by an external event
Cause : Conflict, natural disaster, port or logistics blockage at a supplier
Consequence : Production or site stoppage, delays, penalties
12 P3×I4 • Map tier-1 and tier-2 suppliers
• Safety stock for critical components
R-004 Payment fraud (fake supplier or fake CEO)
Cause : Message impersonating a supplier or management, bank detail change not verified
Consequence : Financial loss often unrecoverable
12 P3×I4 • Call-back for any bank detail change
• Dual approval of transfers
R-005 Supply disruption of a critical item
Cause : Single supplier, no qualified alternative
Consequence : Work or production stopped while waiting for delivery
12 P3×I4 • Qualify a second supplier
• Safety stock
R-006 Psychosocial risks and burnout
Cause : Excessive workload, conflicts, lack of recognition, long hours
Consequence : Burnout, absenteeism, resignations, errors
12 P4×I3 • Workload monitoring
• Confidential counsellor and support
R-007 Higher customs duties or trade restrictions
Cause : Trade tensions, sanctions, new import or export barriers
Consequence : Extra costs, customs delays, closed markets
9 P3×I3 • Customs watch and product origin
• Alternative suppliers in other regions
R-008 Delayed delivery from abroad
Cause : Long transport, customs, international logistics disruptions
Consequence : Equipment unavailable on schedule, timeline shifted
9 P3×I3 • Early ordering and shipment tracking
• Local substitute solution
R-009 Adverse exchange rate movements
Cause : Purchases or sales in foreign currency, long delays between order and payment
Consequence : Reduced margin, unpredictable cost price
9 P3×I3 • Invoice in euros where possible
• Currency hedging for large amounts
R-010 Work overload and time pressure
Cause : Unrealistic deadlines, understaffing, frequent interruptions
Consequence : Chronic stress, errors, accidents, absenteeism
9 P3×I3 • Realistic workload planning
• Spot warning signs
R-011 Voice or video impersonation fraud (deepfake)
Cause : AI-generated call or video meeting imitating an executive or supplier
Consequence : Fraudulent transfer, disclosure of information
9 P3×I3 • Code word and call-back for sensitive requests
• Deepfake awareness
R-012 Poor command of a new technology or method
Cause : Lack of experience, limited field feedback
Consequence : Defects, rework, unplanned learning time
9 P3×I3 • Pilot test or prototype
• Expert support
R-013 Uncontrolled use of generative AI tools
Cause : Staff pasting confidential or personal data into public tools
Consequence : Information leak, GDPR non-compliance, loss of trade secrets
9 P3×I3 • AI acceptable-use policy
• Enterprise AI tool with contractual commitments
R-014 Unchecked error produced by an AI system
Cause : Inaccurate output presented as reliable, no review, data bias
Consequence : Wrong decision, customer harm, liability
9 P3×I3 • Human review of content and decisions
• Testing and quality metrics before deployment
R-015 Lack of in-house digital skills
Cause : Reliance on one person or a provider, insufficient training
Consequence : Stalled projects, poor use of tools, security risks
9 P3×I3 • Targeted training plan
• Documentation and support contract
R-016 Underestimated project complexity
Cause : Many actors, interdependencies, new technologies
Consequence : Many surprises, schedule and cost drift
9 P3×I3 • Complexity assessment at launch
• Short phases with decision points
R-017 Breach of international sanctions or export controls
Cause : Sanctioned customer, supplier or good not detected, dual-use items
Consequence : Fines, blocked payments, prosecution
8 P2×I4 • Screen partners against sanctions lists
• Classify sensitive products
R-018 Internal fraud or embezzlement
Cause : Insufficient segregation of duties, rare accounting checks, shared bank access
Consequence : Financial losses, misstated accounts, dispute and proceedings
8 P2×I4 • Segregation of duties for payments
• Bank reconciliations and surprise checks
R-019 No cyber incident response plan
Cause : Roles undefined, emergency contacts unknown, notification duties ignored
Consequence : Slow reaction, greater damage, penalties for late notification
8 P2×I4 • One-page response plan and emergency contacts
• Annual cyber crisis exercise
R-020 Malicious act by an employee or former employee
Cause : Access not removed on departure, excessive rights, labour dispute
Consequence : Data theft or destruction, sabotage
8 P2×I4 • Leaver procedure with same-day access removal
• Six-monthly access review
R-021 Shortage of critical raw materials or components
Cause : Geopolitical tension, concentrated production, global demand
Consequence : Delays, price rises, redesign
6 P2×I3 • Identify at-risk components
• Design allowing alternatives
R-022 Instructions misunderstood because of language
Cause : Multilingual teams, written-only instructions, technical jargon
Consequence : Errors, accidents, procedures not followed
6 P2×I3 • Illustrated and translated instructions
• Check understanding

This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.

Make it yours in 2 minutes

In Risqure, choose “Product launch”, adjust a few answers and get this register with owners, due dates, reminders and exports. Free.

Create my register for free

Other examples in this sector

← All risk register examples