Risk register example: Food processing unit
Setting up a food workshop or plant: hygiene, cold chain, machines, approvals and recalls.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Agriculture / food industry · Planning / design · 20 people · food service, machines or production equipment, hazardous chemicals, heavy or repetitive manual handling, permits or authorisations required, new or temporary team, critical item from a single supplier.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Caught in or crushed by a machine
Cause : Guards removed, work without lockout, residual energy Consequence : Amputation, crushing, fatality |
15 P3×I5 | • Lockout of all energy sources • Guards and emergency stops checked |
|
| R-002 | Exposure to plant protection products
Cause : Mixing without protection, poorly calibrated equipment, re-entering the field too soon Consequence : Poisoning, long-term illness |
12 P3×I4 | • Suitable storage and mixing area |
• Protective equipment and re-entry intervals |
| R-003 | Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation Consequence : Tendinitis, carpal tunnel syndrome, sick leave |
12 P4×I3 | • Ergonomic analysis of repetitive tasks • Job rotation |
|
| R-004 | Slip, trip or fall on the same level
Cause : Wet or cluttered floors, cables on the floor, poor lighting, level changes Consequence : Sprains, fractures, sick leave |
12 P4×I3 | • Housekeeping and clear walkways • Lighting and suitable footwear |
|
| R-005 | Exposure to hazardous chemicals
Cause : Safety data sheets unknown, unsuitable ventilation and PPE Consequence : Poisoning, burns, occupational disease |
12 P3×I4 | • Substitute with a less hazardous product • Inventory, safety data sheets and training |
• Eyewash and emergency kit |
| R-006 | Weather impacts on production
Cause : Drought, frost, hail, flooding Consequence : Crop loss, supply disruption |
12 P3×I4 | • Diversify crops or sources |
• Crop insurance |
| R-007 | Falling sale prices or rising input costs
Cause : Market volatility, dependence on one buyer, energy and fertiliser costs Consequence : Negative margin, cash flow difficulties |
12 P3×I4 | • Diversified outlets |
• Cash reserve |
| R-008 | Loss or reduction of farm subsidies
Cause : Conditions not met, incorrect declaration, policy changes Consequence : Lower income, repayments |
12 P3×I4 | • Support with declarations |
• Track conditions and diversify income |
| R-009 | Tractor or farm machinery rollover
Cause : Sloping ground, speed, poorly distributed load, no roll bar or seatbelt Consequence : Driver crushed, death |
10 P2×I5 | • Protective structure and seatbelt worn • Identify dangerous areas |
|
| R-010 | Entanglement in a power take-off or farm machine
Cause : Missing PTO guard, work with engine running, loose clothing Consequence : Amputation, death |
10 P2×I5 | • Shaft guards in good condition • Engine off and key removed before intervention |
|
| R-011 | Chainsaw tree-felling accident
Cause : Unexpected tree fall, kickback, lone work Consequence : Crushing, severe cuts, death |
10 P2×I5 | • Certified chainsaw training |
• Full chainsaw PPE and a partner |
| R-012 | Engulfment in a grain silo or heap
Cause : Grain bridge collapsing, unloading in progress, working alone Consequence : Suffocation, death |
10 P2×I5 | • No entry during unloading |
• Harness, lifeline and attendant |
| R-013 | Falling hay or straw bales
Cause : Unstable stacking, loader handling, poorly stored bales Consequence : Crushing, death |
10 P2×I5 | • Stacking rules and limited height • Protected cab for handling |
|
| R-014 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
10 P2×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-015 | Pesticide residues above limits
Cause : Unauthorised products, pre-harvest intervals not respected, unchecked imports Consequence : Batches rejected, recall, penalties |
9 P3×I3 | • Spray records and pre-harvest intervals • Testing of high-risk materials |
|
| R-016 | Cuts from sharp tools or edges
Cause : Knives, cutters, sheet metal or glass handled without protection Consequence : Lacerations, tendon injuries |
9 P3×I3 | • Retractable-blade tools |
• Suitable cut-resistant gloves |
| R-017 | Undeclared allergens in a product
Cause : Cross-contamination in the workshop, labelling error, recipe change Consequence : Severe allergic reaction in a consumer, recall |
8 P2×I4 | • Allergen control plan • Label check at every change |
|
| R-018 | Mycotoxins in cereals or dried fruit
Cause : Damp storage, late harvest, weather conditions Consequence : Batches destroyed, health risk |
8 P2×I4 | • Drying and ventilated storage |
• Testing on receipt |
| R-019 | Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source Consequence : Explosion, fire, collapse |
8 P2×I4 | • Regular cleaning and dust extraction |
• Venting and isolation of equipment |
| R-020 | Cold chain break
Cause : Refrigeration unit failure, door left open, long dock times Consequence : Lost products, health risk, customer dispute |
8 P2×I4 | • Continuous temperature logging and alerts |
• Non-conforming product procedure |
| R-021 | Microbiological contamination in a food plant
Cause : Inadequate cleaning, wet areas, crossing of clean and dirty flows Consequence : Recall, poisoning, production stoppage |
8 P2×I4 | • Validated cleaning plan and environmental sampling • Zone and flow separation |
|
| R-022 | Listeria or Salmonella contamination
Cause : Contaminated raw materials, poor hygiene, broken cold chain Consequence : Serious poisoning, recall, prosecution |
8 P2×I4 | • Sampling plan and testing |
• Tested withdrawal and recall procedure |
| R-023 | Food fraud at a supplier
Cause : Ingredient substitution, false origin, dubious certificates Consequence : Non-compliant product, image crisis, prosecution |
8 P2×I4 | • Food fraud vulnerability assessment • Supplier audits and authenticity tests |
|
| R-024 | Food poisoning
Cause : Broken cold chain, poor hygiene, undeclared allergens Consequence : Illness, complaints, health inspection |
8 P2×I4 | • Approved caterer and temperature checks • Allergen information |
|
| R-025 | Food product contamination
Cause : Broken cold chain, hygiene, foreign bodies Consequence : Product recall, illness, loss of customers |
8 P2×I4 | • Up-to-date HACCP plan |
• Withdrawal and recall procedure |
| R-026 | Historical soil contamination found on an existing site
Cause : Undocumented past activities, forgotten underground tanks Consequence : Remediation, use restrictions, dispute with the seller |
8 P2×I4 | • Historical and soil study before acquisition |
• Environmental liability warranties |
| R-027 | Alcohol or drug use at work
Cause : Celebrations, recreational use, addiction, no clear policy Consequence : Serious accidents, dangerous behaviour |
8 P2×I4 | • Alcohol and drug policy |
• Remove from dangerous tasks in case of doubt |
| R-028 | Water pollution from effluents or products
Cause : Pit overflow, sprayer rinsing, leaking storage Consequence : Pollution, penalties, loss of subsidies |
6 P2×I3 | • Sufficient storage and washing area |
• Follow the spreading plan |
| R-029 | Foreign body in a food product
Cause : Glass, metal or plastic from equipment or packaging Consequence : Consumer injury, recall, complaints |
6 P2×I3 | • Metal detectors and glass policy |
• Traceability and batch hold |
| R-030 | Occupational skin disease
Cause : Repeated contact with water, detergents, cement or solvents Consequence : Eczema, skin allergies, unfitness for work |
6 P2×I3 | • Substitute irritating products |
• Suitable gloves and skin care |
| R-031 | Migration of substances from food-contact packaging
Cause : Non-compliant material, no declaration of compliance Consequence : Recall, non-compliance, health risk |
6 P2×I3 | • Require declarations of compliance • Migration tests for critical uses |
|
| R-032 | Labelling error on finished products
Cause : Wrong label loaded, recipe change not reflected, wrong date Consequence : Recall, non-compliance, risk for allergic consumers |
6 P2×I3 | • Label check at the start of each batch • Automatic label code reading |
|
| R-033 | Poor waste management
Cause : Unsorted waste, unapproved contractors, no traceability Consequence : Fines, producer liability, damaged image |
6 P3×I2 | • Sorting at source and approved contractors |
• Waste register and transfer notes |
| R-034 | Accidental oil spill
Cause : Refuelling machines, tank leak, burst hydraulic hose Consequence : Soil and water pollution, costly clean-up |
6 P2×I3 | • Sealed refuelling area |
• Spill kit and response procedure |
| R-035 | Failure to sort and trace waste
Cause : Mixed skips, untraced disposal, no waste register Consequence : Fines, liability for fly-tipping |
6 P2×I3 | • Separate skips and signage • Register and transfer notes kept |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.