Risk register example: Farm building
Building a barn or livestock shed: work at height, machinery, weather and permits.
Adapt it to my project (free) Download for Excel (CSV)
Assumptions: Agriculture / food industry · Execution / works · 8 people · work at height (roofs, scaffolding, platforms), lifting operations (cranes, hoists), machines or production equipment, site vehicles, forklifts, construction machinery, mainly outdoors, works during winter, permits or authorisations required, near water or flood-prone area.
| Ref. | Risk | Score | Prevention | Protection |
|---|---|---|---|---|
| R-001 | Fall from height
Cause : Missing or removed guardrails, scaffold not inspected, harness misused Consequence : Serious injury or death, investigation, site stoppage |
25 P5×I5 | • Collective protection before any access • Scaffold handover and daily check |
• Rescue-at-height plan |
| R-002 | Dropped load or lifting equipment overturning
Cause : Incorrect slinging, misjudged load, wind, unstable ground Consequence : Crushing, fatality, major damage |
20 P4×I5 | • Lifting plan for critical lifts • Qualified operators and slingers, inspected gear |
• No one under the load |
| R-003 | Tractor or farm machinery rollover
Cause : Sloping ground, speed, poorly distributed load, no roll bar or seatbelt Consequence : Driver crushed, death |
15 P3×I5 | • Protective structure and seatbelt worn • Identify dangerous areas |
|
| R-004 | Chainsaw tree-felling accident
Cause : Unexpected tree fall, kickback, lone work Consequence : Crushing, severe cuts, death |
15 P3×I5 | • Certified chainsaw training |
• Full chainsaw PPE and a partner |
| R-005 | Struck or crushed by a moving load
Cause : Suspended loads, pallets, doors or equipment moving near people Consequence : Crushing, fractures, death |
15 P3×I5 | • Marked exclusion zones • Audible and visual movement warnings |
|
| R-006 | Entanglement in a power take-off or farm machine
Cause : Missing PTO guard, work with engine running, loose clothing Consequence : Amputation, death |
15 P3×I5 | • Shaft guards in good condition • Engine off and key removed before intervention |
|
| R-007 | Falling hay or straw bales
Cause : Unstable stacking, loader handling, poorly stored bales Consequence : Crushing, death |
15 P3×I5 | • Stacking rules and limited height • Protected cab for handling |
|
| R-008 | Engulfment in a grain silo or heap
Cause : Grain bridge collapsing, unloading in progress, working alone Consequence : Suffocation, death |
15 P3×I5 | • No entry during unloading |
• Harness, lifeline and attendant |
| R-009 | Contact with an overhead power line
Cause : Tipper, sprayer boom or ladder near a line Consequence : Electrocution, fire |
15 P3×I5 | • Map lines on the farm plan |
• Instructions in case of contact |
| R-010 | Prolonged bad weather
Cause : Rain, frost, snow or strong wind during outdoor work Consequence : Site stoppages, degraded quality (concrete, paint), delay |
15 P5×I3 | • Season-aware scheduling |
• Temporary protection |
| R-011 | Load falling from an overhead crane
Cause : Worn slings, incorrect rigging, overload Consequence : Crushing, material damage |
12 P3×I4 | • Check lifting accessories • Train riggers and crane operators |
|
| R-012 | Fall from a farm building or trailer
Cause : Fibre-cement roofs, hayloft, improvised ladders Consequence : Serious fall |
12 P3×I4 | • Roof work by professionals • Guardrails on raised floors |
|
| R-013 | Combustible dust explosion
Cause : Build-up of wood, flour, sugar or metal dust, ignition source Consequence : Explosion, fire, collapse |
12 P3×I4 | • Regular cleaning and dust extraction |
• Venting and isolation of equipment |
| R-014 | Alcohol or drug use at work
Cause : Celebrations, recreational use, addiction, no clear policy Consequence : Serious accidents, dangerous behaviour |
12 P3×I4 | • Alcohol and drug policy |
• Remove from dangerous tasks in case of doubt |
| R-015 | Extreme weather event
Cause : More frequent and intense storms, floods, heatwaves or droughts Consequence : Damage to installations, business interruption, repair costs |
12 P3×I4 | • Climate vulnerability assessment of the site |
• Weather alert and safety plan |
| R-016 | Repetitive hand and arm movements
Cause : High work rates, unsuitable tools, no rotation Consequence : Tendinitis, carpal tunnel syndrome, sick leave |
12 P4×I3 | • Ergonomic analysis of repetitive tasks • Job rotation |
|
| R-017 | Weather impacts on production
Cause : Drought, frost, hail, flooding Consequence : Crop loss, supply disruption |
12 P3×I4 | • Diversify crops or sources |
• Crop insurance |
| R-018 | Pollution of a watercourse or sensitive environment
Cause : Run-off, fuel stored without bunding, accidental release Consequence : Harm to wildlife and plants, sanctions, costly restoration |
12 P3×I4 | • Bunding, refuelling area and settling ponds |
• Spill kits and alert procedure |
| R-019 | Unplanned production stoppage
Cause : Critical equipment failure, no spare parts Consequence : Late orders, operating losses |
12 P3×I4 | • Equipment criticality analysis |
• Critical spare parts stock |
| R-020 | Product recall
Cause : Manufacturing defect, contamination, labelling error Consequence : Withdrawal costs, loss of customers, brand damage |
10 P2×I5 | • Quality checks at critical steps |
• Batch traceability and tested recall procedure |
| R-021 | Water pollution from effluents or products
Cause : Pit overflow, sprayer rinsing, leaking storage Consequence : Pollution, penalties, loss of subsidies |
9 P3×I3 | • Sufficient storage and washing area |
• Follow the spreading plan |
| R-022 | Lack of seasonal harvest labour
Cause : Worker shortage, administrative constraints, housing Consequence : Harvest delayed or lost |
9 P3×I3 | • Early recruitment and good welcome conditions |
• Partial mechanisation or mutual aid |
| R-023 | Run-off and mudflows from the site
Cause : Bare soil, no retention basin, heavy rain Consequence : Flooding of neighbours, pollution of drains, complaints |
9 P3×I3 | • Temporary stormwater management |
• Clean roads and gullies |
| R-024 | Climate change impacts on the project
Cause : More frequent heatwaves, droughts and heavy rain Consequence : Work stoppages, damage, design to revise |
9 P3×I3 | • Include climate scenarios in design |
• Plan to adapt hours and works |
| R-025 | Falling sale prices or rising input costs
Cause : Market volatility, dependence on one buyer, energy and fertiliser costs Consequence : Negative margin, cash flow difficulties |
9 P3×I3 | • Diversified outlets |
• Cash reserve |
| R-026 | Loss or reduction of farm subsidies
Cause : Conditions not met, incorrect declaration, policy changes Consequence : Lower income, repayments |
9 P3×I3 | • Support with declarations |
• Track conditions and diversify income |
| R-027 | Permit granted late or refused
Cause : Incomplete application, underestimated processing times, third-party appeals Consequence : Delayed start, idle teams, project to be redesigned |
9 P3×I3 | • Permit back-schedule • Pre-application meeting with authorities |
|
| R-028 | Regulatory change during the project
Cause : New standard, law or permit requirement adopted before completion Consequence : Studies and works to redo, extra costs, delay |
9 P3×I3 | • Project-specific regulatory watch |
• Change-in-law clause |
| R-029 | Fire in a farm building or crop
Cause : Hay self-heating, old electrical installations, machinery Consequence : Loss of buildings, stock and animals |
8 P2×I4 | • Monitor stored hay temperature • Electrical installation inspection |
|
| R-030 | Food product contamination
Cause : Broken cold chain, hygiene, foreign bodies Consequence : Product recall, illness, loss of customers |
8 P2×I4 | • Up-to-date HACCP plan |
• Withdrawal and recall procedure |
| R-031 | Animal or plant disease on the farm
Cause : Poor biosecurity, uncontrolled introduction of animals or plants Consequence : Culling or destruction, loss of production, trade restrictions |
8 P2×I4 | • Biosecurity measures |
• Health monitoring and rapid reporting |
| R-032 | Water shortage for irrigation or livestock
Cause : Drought, usage restrictions, borehole failure Consequence : Crop losses, animal stress |
6 P2×I3 | • Water storage and efficient irrigation |
• Drought plan |
| R-033 | Working in the cold
Cause : Low temperatures, wind, humidity, cold stores Consequence : Hypothermia, frostbite, muscle problems, falls on icy ground |
6 P2×I3 | • Suitable clothing and heated rooms • Organise exposure time |
|
| R-034 | Hand-arm and whole-body vibration
Cause : Vibrating tools, machines on rough ground, long exposure Consequence : Vascular and joint disorders, low back pain |
6 P2×I3 | • Low-vibration tools and suspended seats • Limit exposure time |
|
| R-035 | Zoonotic disease from animals
Cause : Contact with sick animals, births, manure, ticks Consequence : Infections, hospital admission |
6 P2×I3 | • Hygiene and gloves at births |
• Inform the doctor about exposure |
This example is indicative. Scores and measures must be adapted to your situation and checked by a competent person (prevention advisor, safety coordinator, data protection officer…). It does not replace the risk assessments required by law.